GA developed for production scheduling

Similar presentations


Presentation on theme: "GA developed for production scheduling"— Presentation transcript:

1

2 GA developed for production scheduling

3 Chromosome representation

4 Crossover Operation

5 Mutation Operation

6 Fitness function Minimise :  Pe(Ec+Ep) +  Pt(Tp)
Where Ec = max (0, Dc - Fc) Ep = max (0, Dp - Fp) Tp = max (0, Fp - Dp)

7 Example problem Component Product 1st Operation Assembly Time

8 Resource profile Resource overload

9 New schedule from GA

10 Resource profile of new schedule

11 Scheduling problems

12 Experimental factors

13 Scatter plot of responses

14 Evaluation regression models

15 Scheduling a larger problem
497 machining operations 39 assembly operations 24 machines

16 Comparison of penalty costs