1 Modification 0333A – implementation info
Transmission Workgroup 4 August 2011

2 Mod 0333A Implementation 18 week implementation project started May 2011 In line with expectations set within Mod 0333A, the implementation will be effective from 1 October 2011 Start of gas year busy time for system change (AQ review, DN Interruption) so two stage implementation; Initial implementation to be effective from 1 Oct 2011 Final implementation i.e. Gemini screens etc 16 Oct 2011 Formal Implementation Notice to be issued to Joint Office asap

3 Mod 0333A – error in calculation
Typo in calculation within legal text; Current calculation is However, this should read

4 Mod 0333A – error in calculation
No impact for gas year 2011/12 fixed defaults will be SAP+/ p/kWh from 1 Oct 11 Error will result in higher fixed diff prices for 2012/13 if unchanged Proposal is to raise a consent to modify to amend the text once implemented into UNC