CAWG Wind Survey March 28, 2011 Dallas, TX ESWG
For questions contact Tim Miller
3
CAWG survey Results & Review
Agenda Item 3: CAWG survey Results & Review
4
CAWG Wind Survey Overview
Survey focus: Business as Usual future Feb 28: SPP had received all initial responses March 2: Sent out first draft of survey CAWG ESWG March 10: CAWG conference call March : Siting plan developed from survey March 28: ESWG endorsement requested
5
CAWG Survey – Wind Generation
Net Additions & Removals -> change to “Known wind plans in-service by 2012” Additional Wind Added in Siting Plan -> change to “Additional wind added to meet targets” 9,965 should be rounded up to 9,966 to match the pie chart, or vice-versa
6
CAWG Survey – Renewable Energy
Larger font sizes
7
Wind Siting Plan Future 1: Business as Usual
Targets provided in wind survey 9,965 MW wind 14.4% renewable req. Future 2: EPA Rules with Additional Wind 20% RES requirement 13,784 MW wind Make sure 9,965 consistent with 9,966 or whatever throughout
8
Wind Siting Allocation
ITP10 siting utilizes similar approach as ITP20 siting plan Additional wind to meet targets distributed to NE, KS, OK, and TX sites Capacity factors pulled from NREL dataset Based on 100 meter hub heights