SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE
Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 17, 2012
2
Morrison Creek Construction Along Union Pacific Railroad
Construction started May 1st. Coordinated with Union House Elementary School for placement of crossing guards. Construction scheduled for completion in October 2012.
3
Post Authorization Change Report (PACR)
Preliminary FEMA floodplain information provided by the City of Sacramento contract indicates that a PACR will not be required. Corps will complete verification of FEMA floodplain model by December 2012.
4
Marshall Marik US Army Corps of Engineers 1325 J Street Sacramento, CA 95814-2922 (916) 557-7698