1 ctcLink Project Update ctcLink Executive Leadership Committee
December 13, 2018 Choi Halladay – District Vice President for Administrative Services, Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director

2 Agenda Item Description Duration Facilitator 1. Welcome 2 Minutes
1.  Welcome 2 Minutes Joyce 2.  Approval of Minutes 3 Minutes 3.  ctcLink Program Status - Remediation (CCS, TCC Updates) - Deployment Group 2 - Deployment Group 3 - Deployment Group 4 20 Minutes Christy 4.  Staffing & Budget Status 5. Governance Update (Working Group, Steering Committee) 5 minutes Christy/Choi 6. Review WACTC Report-Out Talking Points Joyce/Choi 7. Next Meeting Items & Adjourn

3 Ctclink Minutes – Approval
October 4, 2018 November 7, 2018

4 Ctclink program status
Remediation Deployment Group 2 Deployment Group 3 Deployment Group 4

5 ctcLink College Remediation Status Reports – November 12 to 23, 2018
Community Colleges of Spokane R Remediation Items progress this period Closing Fiscal Years Absence of a book-to-bank reconciliation process impacting FY 16 Close. CCS still has an $18 million dollar variance in the “book” cash balance. CCS FY 16 Closing Rules adjustments for Pass 11. PC & CAPC journal process not run since Feb State Auditor questioning variance with Head Start grant revenue. Security role redesign – Project pushed out from September 2018 to February Finance Security Roles matrix delivered to working group 11/14. CCS to review. Absence management (adjunct & part time faculty) – Completion date still TBD. DRS & PEBB – Completion date still TBD Faculty Workload Improvements. Onsite HCM training completed on Oct. 18. Improvements to be implemented in December 2018. Student third-party billing – SBCTC request to deliver now in January CCS continues to reformat invoices manually with a labor-intensive task. CCS agreed to January 2019 delivery. *If status is yellow or red, describe why. Was finally seeing SBCTC activity with CCS key remediation conditions, but over last two weeks, issues or delays seen now with all remediation items except for the FWL Package 2 which appears to be on track. No ‘complete by’ dates yet provided for all remaining remediation items. Remediation conditions were identified in December 2016. Tacoma Community College G Accomplished this period Reached out to local SMEs for updates on 3 HR remediation items: 29976, 20781, and 20491 Planned for next period Receive updates on 3 HR remediation items: 29976, 20781, and 20491 Participate in OAA redesign options ratings See SBCTC update on 10 remediation items Project Team R Accomplished this period Absence Management - Completed development and testing of all the absence balance remediation fixes. We have packaged the absence balance fixes to the CEMLI SE-231 and have migrated the CEMLI to PTS for ERP to System Integration Testing (SIT). Third-Party Billing – Completed 9.0 FDD/TDD and began development work effort Planned for next period Absence Management – The Application Services migrate the project to PQA for Colleges to UAT Test DRS - We are waiting on approval of the formula from SBCTC and then can complete the development. Faculty Workload - Package 2 postponed until spring quarter due to calculations issues discovered during testing; work in progress to resolve Security Role Design – Continue to finalize new role and permission list model. Student Third-Party Billing – Complete development and begin Functional Unit Testing and then begin System Integration Testing. Fiscal Year – Continue to work with FY team and Reporting team on end-to-end Checklist, Queries, and Reporting needed for Month End and Year End close. *If status is yellow or red, describe why. The ctcLink project team in partnership with the FLC’s agreed upon solution plans and completion dates for most of the remaining remediation. A number of the 40 plus remaining remediation items have missed the planned completion dates due to GDR timing, policy decisions as well as impacts from AWS migration and environmental issues.

6 Remediation summary – Appendix A
Date Total Open Agreement w/Plan Needs Improvement 11/29/2017 111 101 10 12/13/2018 39 29 Issues without Detailed Plan (Needs Improvement) Continuing Education Application Online Admissions Application Hyperion / Create Budget Application

7 REMEDIATION SUMMARY – APPENDIX A Open Items and Additional Critical Issues
Date Total Open Agreement w/Plan Needs Improvement 11/29/2017 111 101 10 12/13/2018 39 29 College Remediation Acceptance Conditions Financial books for fiscal years 2016 and 2017 CCS Security Audit / proper system internal controls  Absence Management Framework Accurate reporting to the Department of Retirement Services (DRS) and the Public Employee Benefit Board (PEBB) Faculty Workload Student account and student third party billing statements must be configured into an easily readable and accurate statement Chart of Account Re-design Task Based Security Re-design Absence – No Proration / xfer jobs will not automatically xfer balances, two accruals for classified and for multiple jobs, the colleges have to manually track and update to ensure accuracy.

8 REMEDIATION SUMMARY – APPENDIX A Closed Items Agreement with Solution
Date Total Closed Agreement w/Solution Needs Improvement Needed Clarification 11/29/2017 264 180 52 32 12/13/2018 262 2 Issues closed where college did not agree with solution (Categories of those issues that “Need Improvement”) Need clarifications (Not understanding requirement/solution) Request additional training Enhancement requests Open ERP Support Service Desk tickets

9 Other ctcLink Project Activities – Status as of Dec. 7, 2018
New Solution Status RFP Publish Solution Decision Physical Inventory (Asset Tracking) Vendor Solutions being evaluated New PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 Delayed to evaluate new functionality within PS Continuing Education RFP was developed and approved by Governance RFP proposals due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Vendor demos scheduled for December 19, 2018 Solution presented to Governance for approval in January 10/15/2018 January 2019 Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft Universities and Colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions If needed, develop RFP TBD Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution February 2019 Accessibility Continued discussions with Appsian (formerly Grey Heller) Accessibility Vendor to assist with testing of ctcLink Validation approach using Appsian solution on ctcLink versions being discussed and coordinated. N/A DG2 System Integration Testing – March 2019 Guided Pathways Steering Committee approved approach for gathering business requirements for Guided Pathways March – June 2019

10 Project Overall Status – November 12 to 23, 2018
G Program is on track and making expected progress Key activities are being executed per timeline and budget Scope Y Monitoring scope and timing of Chart of Accounts, Budgeting Tool, Continuing Education, Online Admissions Application, and OBIA implementations Schedule Analyzing resource overlap between DG2 and DG3 tasks Project Plan has been baselined but will need a second baseline once training activities are defined Budget ctcLink Budget currently tracking under budget: Delayed hiring Timing of re-implementation of solutions (Continuing Education, Online Admissions Application, Budget) Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment is still underway due to the rework of key solutions. Deployment Group 2 (DG2) is in the Structure Phase, focused on Local Configuration and Conversion activities. DG2 Go-Live is scheduled for October The Global Design/Configuration Framework and previous Common Process Workshops (CPW) recommendations continue to move through governance for approval. DG3 is gearing up as 2018 winds down: Peer Review Readiness, Dec. 5-6; Pre Kick-Off, Dec Individual College DG3 Kick-offs will be mid-January 2019 and official DG3 Kick-Off is Jan. 28, 2019 Remediation work continues to be a priority working in parallel with the Deployment activities. The Continuing Education RFP closed Nov. 15 and work on the OAA solution is underway. Remediation Status Campus Solutions Open Tab - 13/45 Closed Tab – 2/13 Financial Management Open Tab - 14/39 Closed Tab – 1/35 Human Capital Management Open Tab - 09/25 Closed Tab – 0/07 Faculty Workload Package 2 postponed until Spring Quarter due to calculations issues discovered during testing, work in progress to resolve DRS Waiting on approval of the formula from SBCTC and then can complete the development. Absence Management Waiting on migration to begin UAT Security Audit Controls Incorporated into Security Redesign Student Billing FDD/TDD is complete and development work in progress Budget Planning Solution Begin sub-committee in Jan 2019 to review and finalize requirements Online Admissions Solution OAA workgroup to begin reviewing other OAA options Continuing Education Solution RFP closed, proposals under review. Team responding to questions to shortlist vendors, schedule demos for work group. Risks Mitigating Actions H ctcLink PMO – Guided Pathways (GP) Impact to Academic Structure If there’s a requirement to reconfigure the Program Plan structure, there could be a scope/budget/timeline impact. Continue to monitor GP requirements gathering via future workshop. M ctcLink Campus Solutions – Student Experience in 9.2 CS team has expressed concern about how students will execute transactions in 9.2. More FLUID development may be needed or create tiles to re-direct. CS team has been working with ctcLink Tech team. C Clark - Global Implementation Led by SBCTC Governance at multiple levels at Clark has been implemented. Better reporting on status is helping. Clark has suggested ctcLink use existing listservs for the pillars regarding decisions made at SBCTC. This information has been shared with ctcLink Communications team. LEGEND: Critical High Moderate Low C H M L LEGEND: High Medium Low Issues LEGEND: High Medium Low Status Update H ctcLink CS – Student Financials (SF) Conversion Logic – Negative Charges/Fee Code Transfers Meeting with Student Financials (SF) team, Legacy and Technical resources on Nov. 14 to discuss and review SF extract logic for conversion. Clark – CS Conversion of Sensitive Data Cycle #2 data – sexual orientation and gender identity are being converted into service indicators, which makes this information available to all that are validating data. CS team did try to resolve this by getting security added to this. In the future, this should not be viewable during data validation or should be uploaded for a small test group or during Cycle #5. H M L 10

11 Deployment Group 2 Self-Reported Status – November 12 to 23, 2018
Clark College G Accomplished this period Held 90-minute validation overview sessions to demonstrate to validators how Clark is conducting validation, where to find information, and basic PeopleSoft navigation. About 30 staff attended. Creating data validation files for staff to validate and track their work. Data Validation Labs – 11 hours of labs over 3 days have been held. Change Action Plans with FM teams Planned for next period Continue data validation Continue meetings to complete Change Action Plans Schedule CS meetings requested by project staff Planned, but not completed Update Communication Plan SBCTC Agency G Accomplished this period SBCTC Liaisons & Governance meeting held (1 of 2) 11/16 HCM & FIN Data Validation Introduction meetings attended 11/14-15 Data Validation completed for “Purchasing Orders” and “Vouchers” Planned for next period Complete one last piece of UAT Homework ECD no later than 12/7 Completion of HCM and FIN Data Validation effort 11/16-12/11 Working Group charter approved ECD 12/7 SBCTC Liaisons & Governance meeting (2 of 2) 11/27 Planned, but not completed Completion/approval of agency work breakdown structure to graphically represent all work needed for success, ECD 12/21/18 Meet to discuss how contracts will go into ctcLink and how different departments might do different parts of the work (new PM will inquire with Working Group on this) ECD 12/21/18 Submit PS query samples/requests – (new PM will inquire with Working Group on this) ECD 12/21/18 Community Colleges of Spokane R Accomplished this period 1 Finance resources focused on end of month and FY Close tasks. 2 Initial planning meeting for Chart of Accounts Planned for next period Identify and follow up on any outstanding CCS BPFG homework. Review of Finance Security Roles Matrix Create CCS Chart of Accounts Plan Create CCS Security Redesign Plan Planned, but not completed *If status is yellow or red, describe why. SBCTC progress was being made on Remediation Conditions and Items, but delays and issues have cropped up. FY Close making progress but at Risk with no book to cash detailed reconciliation report or process. Security Redesign slipped out to February. College implementation and mapping will be time intensive impacting all departments Tacoma Community College G Accomplished this period Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in Data Validation Attended PM Summit Participated in PM training (Ivy Brent) Planned for next period Participate in Conversion Cycle 2 Data Validation 1099 BPFG Sessions Planned, but not completed

12 Deployment Group 3 – DG3 Completed DG3 Pre-Kick-Off – Nov. 2, 2018
Began bi-weekly DG3 meetings – Nov. 7, 2018 Peer Review meetings for readiness – Dec. 5-6, 2018 College Pre-Kick-Off meetings – Dec , 2018 College Leadership Discussion College ctcLink Project Team Additional Pre-Kick-Off meetings – January 2019 DG3 Official Kick-Off – Jan. 28, 2019

13 Deployment Group 3: Gate 1 Initiation Phase Progress - as of Dec
Initiation Phase Deliverables Cascadia Lower Columbia Olympic Peninsula Pierce Resource Plan and Budget C College Project Charter Baselined MS-Project Schedule OCM Plan Communication Plan Local College Training Plan NR Risk Management Plan Data Cleansing Plan Legacy Business Process Mapping IP Supplemental Systems Assessment Legend NR: Not Received, deliverable not posted to cDR IP: In Progress, draft deliverable has been posted to cDR C: Complete, final deliverable posted to cDR

14 Deployment Group 4 – DG4 College Initiation Plans Built – Complete
Begin percent-complete tracking in plan (PWA) – In progress Begin dashboard reporting for DG4 readiness – January 2019

15 Moran Technology Quality Assurance Report
Report Recommendations as of October 2018 Y Status/QA# Findings ctcLink Responses R QA 0132 Agency Financial Reporting System (AFRS) CEMLI Status is a QA concern. During the Remediation Project, due to resource constraints, this work was put on-hold. Reporting to State OFM has now resurfaced and the ctcLink Project team needs to get this work completed and operational to meet SBCTC reporting requirements to the State OFM. The AFRS CEMLI is a priority for SBCTC including the ctcLink project. Resources are allocated to complete the AFRS CEMLI work. We will continue to track this work to make sure the work is progressing. SBCTC has requested this work be complete by new Fiscal Year, July 2018. UPDATE: The team has made great progress, but has requested a separate testing environment to complete testing. The new timeline to complete testing and the migration to production is late October 2018. Y QA 0140 The new concept for Training Delivery has major benefits for the ongoing education of college administrative staff in ctcLink business process and PeopleSoft functionality. QA would recommend that the revised scope of the training model be widely communicated to the stakeholders at this time given the positive expectations for the resulting outcomes. The training team is working on the new training approach for ctcLink. We are developing a prototype of the new approach and will evaluate once it is complete. We are also looking at the overall content development scope and looking at external vendors to help build out the self-paced training. As we finalize the approach, we will work with the colleges for feedback. QA 0142 QA recommends that SBCTC ensure that The Burgundy Group delivers a fully documented Technical Architecture of the ctcLink System as they have implemented it in the Amazon Web Services environment. ctcLink Technical and ERP Support staff require this documentation. This Technical Architecture documentation has been requested at this time. QA will continue to report on this Open item until it has been received, reviewed, and accepted. The ctcLink Technical Project Manager will work with the SBCTC Application Services Director to work with our managed services provider Burgundy to develop the ctcLink production and project fully documented Technical Architecture. QA 0143 During the FLC Phase Project, the status of CEMLI delivery and testing was problematic. Many of these CEMLIs were not delivered until 2 weeks before Go-live, were not tested, and resulted in many operational errors. QA team recommends that a list of all CEMLIs be made available for review and maintained, indicating the pillar and business process related to the CEMLI, the latest status of testing, and any issues that will impact software readiness. This list should be made the responsibility of the Pillar PM with periodic reviews with the Technical Lead responsible for CEMLIs. QA team would like to review this list monthly. Deployment Group 2 implementation includes the retrofit development for all Campus CEMLIs (Customizations), The original list had not been consistently updated so the team has rebuilt the CEMLI Master document for Project and Support in parallel with the development retrofit.

16 Moran Technology Quality Assurance Report
Report Recommendations as of October 2018 – cont’d Y Status/QA# Findings ctcLink Responses Y QA 0144 The current status of the Training Materials is a major area of QA concern. There are approximately 60 Courses to be developed for use with DG2 and DG3. QA recommends that a list of all planned Training Courses be made available for review and maintained, including the status of course components including Quick Reference Guides (QRGs), Step-wise Tutorials/Instructions, On-Line References materials linked to Business Processes, and Videos. QA team would like to review this list monthly. Training is a critical area within the ctcLink project. There is a new training manager and training approach. The scope of courses, their mode of delivery, and actual content is being evaluated by the new manager. Once the scope has been finalized, the team will begin to develop the training content as well as we are preparing for a vendor to help with the self-paced training content. QA 0145 11/2/2018: The schedule for development of Training Course materials required for DG2 has now become YELLOW and probably will be RED next month until the PMO has implemented a series of corrective actions to fully recover it. There are 60 courses to be developed. The pilot course was to be completed in September and is still not completed. QA recommends that the PMO expedite bringing on qualified contractors/consultants to recover the schedule. QA 0146 The current delay in completing the new Security framework for the ctcLink could benefit from the colleges completing a work effort in parallel to completion of the security software. One approach could be to use a spreadsheet to collect information regarding business process/tasks, approval authorizations, and assign organizational roles. The security redesign is currently underway and is scheduled to be completed on time in order to utilize it in UAT. OCIO Investment Plan Conditions – October 2018 G Condition Status G 6 OCIO approval of the 3 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application Planned Y 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live

17 staffing update Employees - Open Roles
1 Student Financials Analyst - posted 2 Finance Analysts - posted 1 Applications Configuration Management – posted

18 Budget Status – as of October 31, 2018
Christy

19 Ctclink Governance Update
ctcLink Steering Committee (SC) ctcLink Working Group (WG) ctcLink SC Charter reviewed, updated, sign-off ctcLink WG Charter reviewed, updated, sign-off Decisions / Recommendations Deployment Group 2 – Timeline Global Framework FSCM/HCM GDR - Approved CS GDR – Pending review CPW Processes New Hire Grants Management Absence Management Benefits Lifecycle Course Management Manage Beginning of Term Class Scheduling Financial Aid ISIR Guided Pathways Proposal Decisions / Recommendations to SC CS GDR – Approved Enhancement Requests Additional Actions Better and more efficient presentation of decision materials Prep time for SC Create Template for items to be presented to WG Define which and how items come to WG

20 Questions?

21 Remediation Open – Finance
# Item # Description Status Planned Date Adjusted Date 1 19057 Ability for each organizational unit to develop and modify a budget at any level of the organizational structure and at any level of the program structure, throughout the budget development process. Open DG3 2/1/2020 Needs RFP 2 19297 Distribute and report labor costs based on user-defined criteria, with full integration and reconciliation of data between GL, Payroll, and Student. 8/1/2018 10/24/2019 Training Materials 3 19299 Provide a journal entry toolset, including but not limited to a standardize spreadsheet template, to facilitate streamlined journal entry and upload. 4 19304 Standardize sub-objects and mapping to a system-wide structure for each unique GL created at the college-level. 1/1/2018 7/1/2019 New COA 5 19323 Supports GL account verification across applications. 2/1/2018 TBD FY Deliverable 6 19342 Support vendor payment advance process based on user-defined criteria (e.g., each college is authorized to draw an advance against the State Treasurer, with the amount equal to 17% of preceding biennium's monthly allocation). 12/1/2017 Need SB Process 7 19382 Integrate seamlessly with receivables processes to collect funds from vendors and recover overpayments.

22 Remediation Open – Finance, cont’d
# Item # Description Status Planned Date Adjusted Date 8 19454 Create and maintain as many payment forms and templates, including remittance detail, as required to meet institutional needs and local needs of individual colleges. Open 8/1/2018 10/24/2019 Training Materials 9 19633 Enable reconciliation process based on user-defined business rules (e.g., able to identify transaction source). 1/1/2018 TBD FY Deliverables 10 19747 Calculate and report indirect costs based on user-defined criteria. 2/1/2019 ERP Support 11 19968 Track grants separately from G/L Chart of Accounts and reconcile the two. 12 20212 Comparison of Actual to Budget (Revenues/Receipts and Expenditures) 12/29/2017 2/1/2020 Need RFP 13 N/A - 39 Must configure system to utilize correspondence to vendors for all PO’s. 1/1/2019 14 N/A - 41 College needs a budget development system that allows for adequate budget building process. DG3 15 19713 Dispose of financial and non-financial assets. Closed DG2

23 Remediation Open – Human Resources
# Item # Description Status Planned Date Adjusted Date 1 20596 Faculty Workload to generate and modify documents and pay for adjunct faculty based on user-defined criteria (4 Phases to resolve / 2 Phases remaining) Open 3/1/2018 Package /30/2018 Package /20/2018 2 29976 Develop and Re-run the ESD report 12/1/2017 TBD TCC to Test 3 37532/ 55698 Bio-Demo data values not aligned with CS and HCM Closed ERP in Progress 4 20753 Establish contract pay based on user-defined criteria. 1/1/2019 10/24/2019 Needs CPW 5 20573 Need ability to report on department budgets Needs Budget Tool 6 N/A - 27 Step Movement / Needs CEMLI 7 N/A - 29 Spokane would like to participate in UAT process for upcoming DGs implementing the Recruitment module. DG2 8 N/A - 31 Migrate ctcLink framework to Wave 1 framework (related to Absence Management) 9 N/A - 32 Create “day” definition / Absence Management and Time & Labor issue 10 N/A - 34 Provide list of employees missing area codes / Legacy Data Issue 9/14/2018

24 Remediation Open – Campus Solutions
# Item # Description Status Planned Date Adjusted Date 1 20797 Support continuing education registration process where student can browse courses without logging on Open DG3 2/1/2020 Needs RFP 2 20901 Provide the ability for continuing education students to enroll directly in classes (i.e., application is not required). 3 21359 Allow payment online for continuing education based on user name and password. 4 21505 Perform third-party billing based on user-defined criteria (e.g., by student, consolidated) . 5/1/2018 10/24/2019 GDR Approved 5 20814 6 21293 Support streamlined admissions processing and user interface. (Online Admissions Application) 7 N/A - 13 Effective Dating: FA Term, FA Budget and other areas have defective Effective Dating 12/1/2017 TBD 8 N/A - 15 Reconciliation queries haven’t worked correctly or accurately since Go Live. 3/1/2018 FY Deliverable 9 N/A - 22 Error/exception report identifying discrepancies between financial aid system and the general ledger (2nd Journal Set)

25 Remediation Open – Campus Solutions, cont’d
# Item # Description Status Planned Date Adjusted Date 10 N/A – 12 SAP Setup Effective Dating doesn’t work (Oracle Bug ID ) Open 6/1/2018 TBD 11 N/A – 17 Converted student account balances must be completely audited / corrected to reflect the ending balances from Legacy. FY Deliverable 12 N/A – 18 Reports to reconcile student financial transactions for a given day to the general ledger by item type, chartstring and fund. 5/1/2018 13 N/A – 19 Need accurate reports in the CS pillar for Student Financials to summarize data such as insurance, fees, waivers, etc. 9/30/2018 14 21451 Maintain academic standing for financial aid eligibility, based on multiple, user-defined criteria Closed N/A 15 21338 Track satisfactory academic progress (SAP).