1 Turner Subcontract Closeout
Jim Dee, Procurement Compliance Mgr and Carol Silva, Subcontract Administrator May 14, 2009

2 Turner Subcontract Closeout
Distributed a Project Closeout Guide with Forms to ensure systematic final acceptance and all contractual requirements are met. Notice of Substantial Completion 11/17/2008 Physical Completion 4/24/2009

3 Turner Subcontract Closeout
Turner Subcontract Overview DOE Approved Value $95,640,600 Available Ceiling $1,363,712  Current Total Value (Thru Mod.81) $94,276,888 Trade value $81,138,049 Turner fee value $13,138,839 Closed FCO Process w/ Mod 80 & deobligated $264,624

4 Turner Subcontract Closeout
Pending PCO/COR Status Owner Actions Value Turner Construction 13 $495,608 SLAC Facilities 1 $27,048 SLAC Procurement 10 $16,087 Total 24 $538,743

5 Turner Subcontract Closeout
Retention Turner retention dollar amount $479,025  Total Trades retention dollar amount $5,821,383 NO retention amounts shall be paid without AMD express authorization No final retention amounts have been released

6 Turner Subcontract Closeout
Activities Redline as-built’s sent to Jacobs for Record Drwgs 23 of 26 trade subcontracts require closeout binders Turner off-site to SJ Offices AAA Mediation Townsend Audit – Phase II (audit of Western Maint T&M subcontract, etc.)