1 PROGRESS on EE VPTs, Dees 1 - 4 D Cockerill 31.1.2008
CMS Jim

2 VPTs To PNPI ? CMS Jim

3 VPTs – put aside/rejected at RAL
Total of 1203 VPTs put aside or rejected in RAL/Brunel tests Total of VPTs accepted for use at CERN in RAL/Brunel tests Total of VPTs needed Put aside or failed in 1.8T rig at RAL or 4T rig at Brunel CMS Jim

4 Dee progress Bat naked SCs per week for past 2 weeks now at > SC 386 Projections (updated ) Dee1 ` Motherboard trigger mapping from next week on SU#1 Dee2 SC mounting Finish next week Validation J-L Faure, J-M Raymond Feb Dee4 Dismount 20 SCs in –15 Feb Dee3 Fibres onto BP –22 Feb Start SC mounting /22 Feb CMS Jim

5 Dee progress CMS Jim

6 Dee1 assembly Uva fibres UVa stability fibres installed on LH quad
LV cabling started on Dee1, using LV jig plates for correct positioning. CMS Jim

7 Additional info CMS Jim

8 VPT leakage currents, CERN acceptance rig
CMS Jim

9 VPT visual inspection, off-axis anodes
Yield at 1.8T Pedestal width CMS Jim

10 SC assembly Crystal delivery, naked SC assembly profile and HV tested SCs Over halfway in production for naked and tested SCs All naked SCs for EE by 4 June 2008 SCs HV tested, ready or mounted CMS Jim

11 Dee assembly – SC mounting
Dee1 SC mounting completed on Mon 19 Nov Smooth follow on for SC mounting on Dee2, 1st quad done Expect to complete SC mounting on Dee2 by Feb 14 Dee3 SCs mounted by 10 Apr Dee4 SCs mounted by 20 Jun (assuming 9 weeks per Dee if 17.5 SCs mounted per week) CMS Jim

12 From VPT to mounting on Dee
Activity Test/comment VPT reception/sorting HV test VPT - crystal gluing 75/d VPT/crystal multibox Naked SC assy 14/w HV card mounting Shipment Mount on loader arm Mount fibres/bolt to Dee CMS Jim