An Investigation into the Failure of Belly Dump Trailers
Mr Peter Airey BE GradDipAdmin FIEAust CPEng RPEQ Managing Director - Airey Taylor Consulting Engineers & Scientists Chairman – Advanced Substructures Ltd
3
Dump Truck Arrangement
Product Mass = ~70,000kg/trailer = 211,000kg total Dump Truck Mass = 16,000kg Dolly Mass = 3,500kg
4
Typical Failure
5
Investigation Methodology
Max. Horizontal Design Load = 320 kN Mass Flow, Squad Containers: Geometry Type C2
6
Stress Modelling & Analysis
SAP2000 Static and Dynamic Finite Element Analysis Quantify working stresses in trailer body Particular focus on welded arm connections
7
Stress Modelling & Analysis
Combination of principal stresses evaluated using “Von Mises” criterion: 𝜎 1 2 − 𝜎 1 𝜎 2 + 𝜎 2 2 ≤ 𝜎 𝑦 2
8
Stress Modelling & Analysis
Figure 4 Ed = 1.2G + 1.5Q (Fig. 4) Stresses limited further at welded connections to prevent fatigue failure AS/NZS – Cl & 11.6: Detail Category 56 Fatigue Stress = 90 Mpa (106 cycles) Maximum Von Mises Stress of 320MPa at arm connection and 460MPa at access hatch
9
Conclusions Limiting fatigue stresses exceeded in multiple locations
Problem locations determined via analysis correlated with areas of repeat failure Design-generated issue Mechanical design of such scale requires qualified structural design input