Download presentation
Presentation is loading. Please wait.
1
Installation of Photon Beam Transport to FEH
C.E. Rago – Group Leader Experimental Systems Engineering May 14, 2009
2
Presentation Project History Project Requirements XRT NEH
Detailed Vacuum Design Design Status Ray Trace What is missing? NEH Hutch 1 Hutch 2 Hutch 3 Budget & Schedule Safety Issues
3
Project History LLNL V58 Design for NEH / XRT
Alternative Design Proposal / Improved understanding of future expansion. Design and conserve open space. Presented Budget and Schedule for XRT Design Change = $ 759 K$ Limited Account Approval January 06, 2009 / XRT Manufacture Requested all Materials & Equipment in January All major orders now placed. Added XPP and LLNL Interfaces to Hutches 1,2,3. Added CD4 X-ray detection in Hutch 4 alcove. Partnered with SLAC MFD for Practice and Procedure Integrated CXI, XCS, & Future Requirements Photon Controls Rack Placement and Tunnel Power Order let. Phase 7 Cable Requirement Updated
4
System Requirements Detailed Vacuum Design– LCLS 1.5-002 Schedule
UHV Compatible All parts cleaned and assembled by MFD to SLAC UHV Specification Peak pressure < 10E-5 Torr Greater than 10 year pump life (87 K Hours) SLAC Performance Expectation Out gassing / Chemical Clean with No Bake / 5 X E Days Measured lower at LCLS DUMP Worst Case Condition Maximum Pump Pressure / 3.4 X E-8 Torr Maximum System Pressure / 4.2 X E-7 Torr Gamma Life Data is 400 KH at 1 X E-7 Torr Pump Life > 40 years. Schedule CD-4 Milestone - Beam to FEH is 3/10/2110 P3 XRT Components Installed – Early Finish _
5
Close to FDR XRT Design Status No Design Issues
Installation, System Schematics, some Design Details Not Complete! Hutch 1 Assembly (XPP) Waiting LLNL P4’s & P5 documentation Pump Tee Adjusting Supports waiting Design Detail Resources No Design Issues Vacuum Components and Drifts Designed and With MFD Vacuum Cable information complete for Phase 7 Arnett DC Integration Design Coordinator NEH : XRT : Into FEH
6
XPP in Hutch 2
7
XPP in Hutch 3
8
XRT A
9
XRT B
10
XRT C
11
No FEL Wall Strike Ray Trace Peter Stephan Ray Trace
Potential Collimators for FEH Additional shielding with Mirror Installation
12
Ray Trace
13
What is Missing? P1 Beam Pipe Supports Manufacture
B4C Shield 10” : 2 X 4” MFD Welding Procedures Purge Gas / Weld Performance 10” Hand Butt Welds M-Valve locations for Roughing Completed Documentation Phase 1 Alignment Vacuum System Integration with Photon Controls All mechanical interface information to PC and Cables AC Utilities to Tunnel Welding Service UHV Bake Power Control Racks PPS
14
Phase 1 Beam Pipe Support
15
Phase 1 Beam Pipe Support
16
XTOD Budget Remains K$
17
Budget Up’s Additions since January Estimate:
RP change between Collimator:126 & Stopper :132 Purchase of VVPG:XRT1:111 from LLNL (3X) Rack Design and Installation Design of A.C. Power to XRT NEH Vacuum and Supports Hutch Wall Shielding LLNL efficiency costs Procurement Issues Documentation Installation Documentation Mechanical Schematics
18
Schedule Schedule CD-4 P3 Milestone - Beam to FEH is 3/10/2110
XRT Components Installed – EF _
19
Schedule
20
Safety Issues MFD Practice and Procedures Orbital Welding
Welding Purge Transportation and Rigging (UHV) Alignment Pump Down & Vacuum System Control until XRT Operational
21
March End Commitments K$ 529.0 Labor & Material 353.7
March 09 Cost Balance March End Commitments K$ Labor & Material Material Up Labor to Complete K$ Indirect’s Allowance K$ Budget Allowance K$ April Cost to Complete K$ Plan to Under Run K$
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.