Progress Report (October 2 - 9, 2002)
TX and RX layouts completed and approved Part ordering/layout submission today Final revision of optical power link budget Produced rough outline for first paper Known Issues: Have not received PDs due to vendor error
2
Planned Work (October 10 – October 17, 2002)
Confirm unconnectorized PDs arrive Friday Follow up with vendor to provide information regarding connectorized PDs ordered but not shipped Begin build after receiving board and parts Begin writing report body
3
Gantt Chart
4
Revised PCB Layout Added second TX layout to board
Anticipate second layout may avoid interference from feedback loop Minor change to RX layout: replaced jumper with inductor Probable that board testing will be behind schedule
5
Optical Power Link Budget