1 ctcLink Project Update ctcLink Steering Committee
January 15, 2019 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director

2 Agenda Item Description Duration Facilitator 1. Welcome 2 Minutes
1.  Welcome 2 Minutes Christy 2.  Approval of Minutes 3 Minutes Choi 3. DG3 Activities Gate 1 – Initiation Phase/Peer Review - Decision Alternate College Discussion - Decision 30 Minutes 4.  ctcLink Program Status Remediation (CCS, TCC Updates) Deployment Group 2 Deployment Group 3 Deployment Group 4 5.  Governance Update (cELC) 10 Minutes 6. Other Discussion Items Charter Discussion / Membership Christy/Choi 7. Next Meeting Items & Adjourn 5 Minutes Janelle

3 Ctclink Minutes – Approval
December 18, 2018

4 DG3 Activities Gate 1 – Initiation Phase/Peer Review - Decision
Alternate College Discussion - Decision

5 Quality gate 1 initiation phase
Deployment Group 3 (DG3) peer review sessions were held Dec. 3-4, 2018 at SBCTC to assess required Initiation Phase deliverables. Peer review process and ctcLink governance evaluates each college’s readiness to enter a deployment group DG3 Project Managers (PMs) from Cascadia, Lower Columbia, Olympic, Peninsula, and Pierce each presented and discussed how their college created its plans, budgets, business process maps, and other deliverables.

6 PEER REVIEW OUTCOMES & LESSONS
Peer review sessions and rubric-based evaluation process were successful and allowed for in-depth discussions, feedback and enhanced the DG3 PM cohort’s synergy. DG3 Initiation Phase deliverables were determined to be ready for Steering Committee consideration for the Implementation Phase. Lessons Learned It is critical PMs thoroughly know and use the Initiation Phase project schedule. Deliverables, even if considered complete, will continue to evolve during subsequent project phases.

7 Ctclink methodology & quality MILESTONES
Criteria for college entrance into deployment group is evaluated by ctcLink governance and peer review process.

8 Deployment Group 3: Gate 1 Initiation Phase Progress - as of Jan
Initiation Phase Deliverables Cascadia Lower Columbia Olympic Peninsula Pierce Resource Plan and Budget S College Project Charter Baselined MS-Project Schedule OCM Plan Communication Plan Local College Training Plan NR Risk Management Plan Data Cleansing Plan Legacy Business Process Mapping IP Supplemental Systems Assessment Legend NR: Not Received, deliverable not posted to cDR IP: In Progress, draft deliverable has been posted to cDR S: Submitted, final deliverable posted to cDR

9 Initiation Phase SUMMARY
Summarized scoring chart based on peer review conducted by three project managers. Peninsula College refrained from scoring deliverables. See rubric tally sheets for details. Deliverable Cascadia Lower Columbia Olympic Peninsula Pierce Project Charter +   Allocated Resource Plan & Budget * College Project Execution Plans Legacy Business Process Mapping  + Change Impact Assessment ̶  ̶ Supplemental Systems Assessment  * ctcLink Project Management Office Comments Mitigating challenges with some leadership buy-in Starting Change Impact Analysis Continual development of training plan Focus on Change Impact Assessment and begin Change Impact Analysis vs business process mapping Starting Change impact analysis LEGEND  Met all criteria + Additional support needed  ̶ Not received or deliverable did not meet criteria * See consolidated rubric for comments

10 DG3 Additional or Alternate College
Background Following the Peer Review process as well as the initial kick off meetings, Edmonds was approached to see if they would be interested in a role on DG3 if another college was to decide to move to a later deployment. Consideration/Ask Discuss the positive as well as negative in adding an additional college at this time. Discuss perspective from Edmonds, ctcLink PMO, and DG3 colleges feedback.

11 Edmonds CC as DG3 Backup - Analysis
Benefits/Risk Reduction for Project Overall Pros for Edmonds Community College Geographic proximity to other DG3 Cohort members will support collaboration DG3 cohort: we are geographically close to Cascadia, Olympic and we can help each other. Working with Pierce (good plan for GP/Starfish). Lower Columbia, Peninsula and Pierce were Wave1. They have done a lot of the work and can help the group from that experience. We also think we can help DG3 be successful. Potentially reduce number of DG4 colleges Six schools in DG3 vs. nine in DG4. Edmonds doing project tasks along with DG3 will help later if Edmonds goes live at same time as DG4. We can be a bridge school. Edmonds will mitigate Payroll risks involving Bellevue Payroll proof of concept with Bellevue. Edmonds ready to bring Payroll in-house as needed to mitigate any risks here. Edmonds has committed project resources and the capacity to help other colleges if needed Edmonds wants to continue to be in a leadership position and help other schools. It is critical that DG3 is successful. Edmonds has taken a leadership role and demonstrated commitment to success of the Project as a whole and can bring that to DG3 (and beyond). Edmonds has been working on getting ready for a long time The work we have done on readiness and engagement will pay off sooner; people are more willing to change when there is a sense of urgency. The longer the delay, the harder to get/keep the commitment. Common Process investment that benefits the entire system Investment in common process and learning about the new system and processes will not be lost (which will happen the longer we wait) Edmonds leadership was already committed to DG3 early on We voted to be part of DG3 from the beginning because we feel we are ready. Project budget in place / approved We have an adequate budget to do this project. Resources are engaged and ready to go We have the needed project resources in place and committed, along with a strong project Steering Committee and supportive leadership

12 Edmonds CC in DG3 – PMO/PM review
Question Recommendation/Vote DG3 PMs Do the DG3 College PMs approve making a recommendation to the Steering Committee to add Edmonds to DG3? No – 3 (Pierce, LCC, Peninsula) *LCC – Not until “alternate” is defined Yes – 2 (Olympic, Cascadia-follow up call) – *OC - Will add value and expertise to DG *CC - EdCC will need to go through DG3 Peer Review process and Pre-Kick off prior to DG3 Kick-Off *Discussion/concern regarding “alternate” definition. If DG3 is ready and Edmonds is ready, what happens? *Concerns re resource strain on project team ctcLink PMO Weighing the risks and opportunities, does the ctcLink PMO recommend adding Edmonds to DG3? PROS Reduce DG4 size (9 to 8) PM/OCM expertise added to cohort EdCC Leadership ready and committed resources for success Edmonds Initiation Phase readiness CONS Resource strain on project staff Bellevue does EdCC payroll Lack of visibility into SME readiness, past and current OCM activities

13 Ctclink program status
Remediation Deployment Group 2 Deployment Group 3 Deployment Group 4

14 Pilot remediation overview & status
Date Total Open Items Open Items With a Plan to Complete (Appendix A) Open Items Needing a Replacement Solution (Appendix A) Open Items That Were Closed, but Reopened in Remediation Agreement (Appendix B) 2016, 2017, 2018 Financial Books Security Role Redesign  Absence Management DRS Redistribution Faculty Workload Student Invoice & Third-Party Billing Continuing Education Online Admissions Budget Planning Financial Aid Customizations 11/29/17 195 101 10 84 12/13/18 41 29 2 DRS – Department of Retirement Systems

15 ctcLink Replacement Solutions – Status as of December 2018
RFP Publish Solution Decision Continuing Education RFP was developed and approved by Governance RFP proposals due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Vendor demos scheduled for December 19, 2018 Solution presented to Governance for approval in January 10/15/18 January 2019 Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft Universities and Colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions If needed, develop RFP TBD Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution February 2019 Physical Inventory (Asset Tracking) Vendor Solutions being evaluated New PeopleSoft functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/18 Delayed to evaluate new functionality in PeopleSoft

16 Project Overall Status – Dec. 24, 2018 to Jan. 4, 2019
Y Program is on track and making expected progress Key activities for UAT testing and training are behind schedule Scope Monitoring scope and timing of Chart of Accounts, Budgeting Tool, Continuing Education, Online Admissions Application, and OBIA implementations Schedule Analyzing resource overlap between DG2 and DG3 tasks Project Plan has been baselined but will need a second baseline once training activities are defined Budget G ctcLink Budget currently tracking under budget: Delayed hiring Timing of re-implementation of solutions (Continuing Education, Online Admissions Application, Budget) Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment is still underway due to the rework of key solutions. Deployment Group 2 (DG2) is in the Construct Phase, focused on Local Configuration, Conversion activities and Project Team Functional and Technical Unit Testing. DG2 Go-Live is scheduled for October DG3 is engaged in peer review and pre-kickoff activities, with an official DG3 Kick-off scheduled for January 28, DG4 will begin tracking Initiation Phase activities in January. Remediation work continues to be a priority, working in parallel with the Deployment activities. Following vendor demos in December, the Continuing Education workgroup expects a recommendation for ctcLink governance in January. The OAA workgroup reviewed online admission solutions in use at other colleges and is developing a short list of solutions for further evaluation. Remediation Status Campus Solutions 13 of 45 remain open Closed Tab – 2 of 13 remain open Financial Management 14 of 39 remain open Closed Tab – 1 of 35 remain open Human Capital Management 9 of 25 remain open Closed Tab – 0 of 7 remain open Faculty Workload Package 2 postponed due to calculations issues discovered during testing, work in progress to resolve. DRS Redistribution Waiting on approval of formula from SBCTC and then can complete the development. Absence Management ERP Support SIT and then college UAT Security Audit Controls Incorporated into Security Redesign Student Billing Budget Planning Solution Sub-committee begins Jan 2019 to review, finalize requirements Online Admissions Solution OAA workgroup reviewing other OAA options. Discussions and demos with OAA preferred college solutions. Continuing Education Solution RFP closed, proposals evaluated, vendor demos completed. Recommendation by work group to Governance pending. Risks Mitigating Actions H First large deployment DG3 and repeatable approach. This will be the largest deployment group for our project to engage with and manage. We plan to monitor our approach so that it is repeatable for future deployment groups. Security Re-Design – delayed from vendor, expected in February or March 2019. A Security Framework will be built to allow for College understanding and application of the PeopleSoft Security. Colleges will need adequate time to review, assign users to roles and test their user security roles. M OCM: Business Transformation – most critical for Finance department is user adoption of the new Chart of Accounts (COA). In November 2018, the FIN Team has developed and provided Finance SMEs (specially for Tacoma CC and Spokane District) with documentation and workshops regarding the new Chart of Accounts re-design. This information is instrumental in helping SMEs adopt the new Chart of Accounts and its associated business processes. LEGEND: Critical High Moderate Low C H M L LEGEND: High Medium Low Issues LEGEND: High Medium Low Status Update H ctcLink Training – The development of the Training Content is behind schedule due to the alignment of the training team and new approach to Training delivery. The training scope content is being defined and we have training vendors to help address the delay in the buildout of training content in preparations of training delivery for DG2 colleges and SBCTC. M ctcLink User Acceptance Testing (UAT) Framework – The UAT framework is behind schedule due to formalizing the approach for college use and organizational change management adoption The UAT testing framework is being finalized and test scripts and supporting documentation for UAT is being developed for DG2 colleges and SBCTC. H M L 16

17 Community Colleges of Spokane Tacoma Community College
Deployment Group 2 Self-Reported Status – Dec. 24, 2018 to Jan. 4, 2019 Clark College G Accomplished this period Over 49,000 records validated (the bulk being the General Ledger) in 40 validation files. This work involved 46 staff. Provided Data Validation Lessons Learned to Christy Campbell. Reached out to faculty about a communication plan. Christy Campbell met with Steering Team to discuss updates to the project. Planned for next period Continue meetings to complete Change Action Plans Change action plans into a work plan document. Update Communication Plan Planned, but not completed Update communication plan Change actions plans – postponed meeting to work on data validation *If status is yellow or red, describe why. SBCTC Agency G Accomplished this period SBCTC Agency Data Cleansing complete, Jan. 3, 2019 SBCTC Work Group co-developed the agency Change Impact Analysis and Planning spreadsheet, Jan. 2, 2019 SBCTC Work Group sub-team (3 members, including HR, completed first business process review from current state to future state noting changes and planned actions Jan. 2, 2019) Planned for next period Complete UAT Homework, estimated completion date Jan.4, 2019 SBCTC Work Group charter to be revised based on 2019 plan Additional ADKAR training to be scheduled by 1/18/19 Planned, but not completed Meet to discuss how SBCTC contracts will go into ctcLink and how different departments might do different parts of the work Community Colleges of Spokane R No activities reported for this period. Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in Data Validation P-Card BPFG Sessions Chart of Accounts Redesign Session Kickoff Participated in ctcLink Security redesign activities Planned for next period Participate in Conversion Cycle 3 Data Validation as needed Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Planned, but not completed *If status is yellow or red, describe why.

18 Deployment Group 2 – DG2

19 Deployment Group 3 – DG3 Completed DG3 Pre-Kick-Off – Nov. 2, 2018
Began bi-weekly DG3 meetings – Nov. 7, 2018 Peer Review meetings for readiness – Dec. 5-6, 2018 College Pre-Kick-Off meetings – Dec , 2018 College Leadership Discussion College ctcLink Project Team Olympic College Pre-Kick-Off meeting – Jan. 25, 2019 DG3 Official Kick-Off – Jan. 28, 2019, 2 –3:30 p.m.

20 Deployment Group 4 – DG4 College Initiation Plans Built – Complete
Begin percent-complete tracking in plan (PWA) – In progress Begin dashboard reporting for DG4 readiness – January 2019

21 Budget Status – as of December 31, 2018

22 ctcLink Quality Assurance Scorecard
Moran Technology Consulting | November 2018 Overall: Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 RISK STATUS PROJECT AREA DESCRIPTION/NOTES G SBCTC/Governance Governance framework continues to work as expected. Program Management Project Management Office (PMO) is fully staffed. Morale good. Y Phase Scope QA concerned about implementation schedules for replacement solutions. Will know more once solutions are selected. Schedule Status QA concerns re: overlap of schedules and resource constraints. Testing New automated testing software will add value/benefit, but requires resources up front. Training Development behind schedule. PMO is taking appropriate actions to recover the schedule. Configurations/Data Conversion The new standard Chart of Accounts has been configured and vetted with system-wide finance groups. Organizational Change Management (OCM) OCM is actively engaged in multiple areas, all focused on getting DG2 and DG3 colleges ready for deployment. Project Staffing Staffing is good. Overlap of Deployment Groups 2 and 3 may require additional resources. Technical Environment SBCTC continues to monitor system performance but there have been no outages since early September 2018. Paul: Cover any items not already discussed. LEGEND GREEN YELLOW RED Risk Description Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost.

23 WA State Office of the Chief Information Officer (OCIO) Oversight
Overall: Y WA State Office of the Chief Information Officer (OCIO) Oversight WA State Office of the Chief Information Officer (OCIO) Oversight OCIO’s Conditions to new ctcLink Investment Plan Approval Status G 1 Project must remain in-line with SBCTC and OCIO policies Complete 2 QA (Moran) to report to ctcLink executive sponsor and State CIO 3 Follow pre-determined OFM funding gates and approvals 4 Monthly status reporting 5 Continue reporting on Remediation items in Integrated Work Plan Y 6 OCIO approval of the 3 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application In Progress 7 OCIO must be notified prior to use of contingency funds N/A 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live Planned as Activities in Project Work Plans 9 Process and timeline for filling the SBCTC CIO position by 1/31/2018 Note: New ctcLink Investment Plan approved by OCIO, with above conditions, on Jan. 19, 2018.

24 Ctclink Governance Update
ctcLink Steering Committee (SC) ctcLink Working Group (WG) ctcLink SC Charter reviewed, updated, sign-off ctcLink WG Charter reviewed, updated, sign-off Decisions / Recommendations Deployment Group 2 – Timeline Global Framework FSCM/HCM GDR - Approved CS GDR – Pending review CPW Processes New Hire Grants Management Absence Management Benefits Lifecycle Course Management Manage Beginning of Term Class Scheduling Financial Aid ISIR Guided Pathways Proposal Decisions / Recommendations to SC CS GDR – Approved Enhancement Requests Additional Actions Better and more efficient presentation of decision materials Prep time for SC Create Template for items to be presented to WG Define which and how items come to WG

25 Questions?

26 Remediation Open – Finance
# Item # Description Status Planned Date Adjusted Date 1 19057 Ability for each organizational unit to develop and modify a budget at any level of the organizational structure and at any level of the program structure, throughout the budget development process. Open DG3 2/1/2020 Needs RFP 2 19297 Distribute and report labor costs based on user-defined criteria, with full integration and reconciliation of data between GL, Payroll, and Student. 8/1/2018 10/24/2019 Training Materials 3 19299 Provide a journal entry toolset, including but not limited to a standardize spreadsheet template, to facilitate streamlined journal entry and upload. 4 19304 Standardize sub-objects and mapping to a system-wide structure for each unique GL created at the college-level. 1/1/2018 7/1/2019 New COA 5 19323 Supports GL account verification across applications. 2/1/2018 TBD FY Deliverable 6 19342 Support vendor payment advance process based on user-defined criteria (e.g., each college is authorized to draw an advance against the State Treasurer, with the amount equal to 17% of preceding biennium's monthly allocation). 12/1/2017 Need SB Process 7 19382 Integrate seamlessly with receivables processes to collect funds from vendors and recover overpayments.

27 Remediation Open – Finance, cont’d
# Item # Description Status Planned Date Adjusted Date 8 19454 Create and maintain as many payment forms and templates, including remittance detail, as required to meet institutional needs and local needs of individual colleges. Open 8/1/2018 10/24/2019 Training Materials 9 19633 Enable reconciliation process based on user-defined business rules (e.g., able to identify transaction source). 1/1/2018 TBD FY Deliverables 10 19747 Calculate and report indirect costs based on user-defined criteria. 2/1/2019 ERP Support 11 19968 Track grants separately from G/L Chart of Accounts and reconcile the two. 12 20212 Comparison of Actual to Budget (Revenues/Receipts and Expenditures) 12/29/2017 2/1/2020 Need RFP 13 N/A - 39 Must configure system to utilize correspondence to vendors for all PO’s. 1/1/2019 14 N/A - 41 College needs a budget development system that allows for adequate budget building process. DG3 15 19713 Dispose of financial and non-financial assets. Closed DG2

28 Remediation Open – Human Resources
# Item # Description Status Planned Date Adjusted Date 1 20596 Faculty Workload to generate and modify documents and pay for adjunct faculty based on user-defined criteria (4 Phases to resolve / 2 Phases remaining) Open 3/1/2018 Package /30/2018 Package /20/2018 2 29976 Develop and Re-run the ESD report 12/1/2017 TBD TCC to Test 3 37532/ 55698 Bio-Demo data values not aligned with CS and HCM Closed ERP in Progress 4 20753 Establish contract pay based on user-defined criteria. 1/1/2019 10/24/2019 Needs CPW 5 20573 Need ability to report on department budgets Needs Budget Tool 6 N/A - 27 Step Movement / Needs CEMLI 7 N/A - 29 Spokane would like to participate in UAT process for upcoming DGs implementing the Recruitment module. DG2 8 N/A - 31 Migrate ctcLink framework to Wave 1 framework (related to Absence Management) 9 N/A - 32 Create “day” definition / Absence Management and Time & Labor issue 10 N/A - 34 Provide list of employees missing area codes / Legacy Data Issue 9/14/2018

29 Remediation Open – Campus Solutions
# Item # Description Status Planned Date Adjusted Date 1 20797 Support continuing education registration process where student can browse courses without logging on Open DG3 2/1/2020 Needs RFP 2 20901 Provide the ability for continuing education students to enroll directly in classes (i.e., application is not required). 3 21359 Allow payment online for continuing education based on user name and password. 4 21505 Perform third-party billing based on user-defined criteria (e.g., by student, consolidated) . 5/1/2018 10/24/2019 GDR Approved 5 20814 6 21293 Support streamlined admissions processing and user interface. (Online Admissions Application) 7 N/A - 13 Effective Dating: FA Term, FA Budget and other areas have defective Effective Dating 12/1/2017 TBD 8 N/A - 15 Reconciliation queries haven’t worked correctly or accurately since Go Live. 3/1/2018 FY Deliverable 9 N/A - 22 Error/exception report identifying discrepancies between financial aid system and the general ledger (2nd Journal Set)

30 Remediation Open – Campus Solutions, cont’d
# Item # Description Status Planned Date Adjusted Date 10 N/A – 12 SAP Setup Effective Dating doesn’t work (Oracle Bug ID ) Open 6/1/2018 TBD 11 N/A – 17 Converted student account balances must be completely audited / corrected to reflect the ending balances from Legacy. FY Deliverable 12 N/A – 18 Reports to reconcile student financial transactions for a given day to the general ledger by item type, chartstring and fund. 5/1/2018 13 N/A – 19 Need accurate reports in the CS pillar for Student Financials to summarize data such as insurance, fees, waivers, etc. 9/30/2018 14 21451 Maintain academic standing for financial aid eligibility, based on multiple, user-defined criteria Closed N/A 15 21338 Track satisfactory academic progress (SAP).


Download ppt "ctcLink Project Update ctcLink Steering Committee"