Download presentation
Presentation is loading. Please wait.
Published byMyles Thornton Modified over 5 years ago
1
HARRY ALLEN TRANSFORMER REMEDIAL ACTION SCHEME (RAS)
Presentation to: WECC REMEDIAL ACTION SCHEME RELIABILITY SUBCOMMITTEE (RASRS) November 15, 2017 Adeline Grubb – Transmission Planning Alex Campos – System Protection
2
TRANSMISSION PLANNING INFORMATION FUNCTIONAL DESCRIPTION
Background: Path 35 connects NV Energy and Pacificorp Two parallel 345/230 kV transformers Two parallel phase shifters 345 kV line Rated for 600 MW (North to South) and 580 MW (South to North) FUNCTION: RAS monitors flow on Harry Allen – Red Butte 345 kV line (WECC Path 35). If flow exceeds 410 MVA (686 A) value, the RAS is armed. Once armed, if a trip of one Harry Allen 345/230 kV transformer occurs, the RAS will trip the other Harry Allen 345/230 kV transformer. This effectively protects both transformers from overloading above emergency rating of 409 MVA (violation of NERC-TPL P1-3). Planned In-Service Date: March 2018
3
ONE-LINE DIAGRAM
4
RAS CLASSIFICATION Violations of TPL-001-WECC-CRT-3 System Performance Criteria? No. The Criteria relates to parallel transmission circuits, while this RAS is designed to mitigate thermal overload of two parallel transformers. Maximum load loss of ≥ 300 MW? No Maximum generation loss ≥ 1000 MW? No. Conclusion This RAS is a Local Area Protection Scheme (LAPS).
5
TRANSMISSION PLANNING STUDIES
CONDITION 1: PSLF Power Flow Studies under 407 MW north to south flows on Path 35 (Red Butte to Harry Allen) Loss of one Harry Allen 345/230 kV transformer loads the other parallel transformer to 95% of the emergency rating. CONDITION 2: PSLF Power Flow Studies under 421 MW south to north flows on Path 35 (Harry Allen to Red Butte) Loss of one Harry Allen 345/230 kV transformer loads the other parallel transformer to 96 % of the emergency rating. Maximum Flow Power flow studies under maximum rated North to South flows (600 MW). Power flow studies under maximum rated South to North flows (580 MW). RAS is effective in mitigating overload in both cases. RAS does not cause overloads or low voltage problems under maximum flow on Path 35.
6
CONDITION 1: PRE-CONTINGENCY (P0)
7
P1: HARRY ALLEN 230/345 kV TRANSFORMER #2 OUTAGE; HARRY ALLEN 230/345 kV TRNSFORMER #3 AT 95% LOADING
8
CONDITION 2: PRE-CONTINGENCY (P0)
9
P1: HARRY ALLEN 230/345 kV TRANSFORMER #2 OUTAGE; HARRY ALLEN 230/345 kV TRNSFORMER #3 AT 96% LOADING
10
SUMMARY
11
RAS DESIGN – PHILOSOPHY AND CRITERIA
Redundant systems (System #1 & System #2) with breaker failure protection Primary Action For an overload condition on transformer 2, trip breakers 4505 and 4506 For an overload condition on transformer 3, trip breakers 4504 and 4506 Breaker Failure Action For an overload condition on transformer 2, initiate breaker failure for breakers 4505 and 4506 For an overload condition on transformer 3, initiate breaker failure for breakers 4504 and 4506 RAS failure is a non-credible event Failure of a single component, element, or system will not effect successful operation of the RAS
12
RAS DESIGN – LOGIC 30 cyc pickup for inrush current
MVA ≤ 390 for RAS disarm Breaker status from spare 52b contacts to 2440 Load detection supervision from 487E relays
13
RAS DESIGN – LOGIC HARDWARE
Detection - Redundant SEL-487E relays Separate CT and PT inputs Monitors loading on banks 2 and 3 Detects load on low-side and high-side breakers for additional supervision Logic Processing and Tripping - Redundant SEL-3555 RTACs Sequential Event Recorder (SER) Indications to RTU and back to SCADA Initiates tripping and breaker failure Communication Logic Processing - Redundant SEL-3555 RTACs Communication to SEL-2440’s via SEL Fast Messaging Communication to SEL-3354 RTAC RTU via DNP
14
RAS DESIGN – ARCHITECTURE
15
SCADA Indications SCADA Point Response Code
345KV HA XFMR RAS SYS 1 & 2 DEFEATED NA 345KV HA XFMR RAS SYS #1 ACTIVE 345KV HA XFMR RAS SYS #1 TRIP INITIATED 1R 345KV HA XFMR RAS SEL RLY TRBL 345KV HA XFMR RAS SEL BAD COMM 2R 345KV HA XFMR RAS SYS #1 SUSPECT 345KV HA XFMR RAS SEL RLY TRBL 345KV HA XFMR RAS SEL BAD COMM 345KV HA XFMR RAS SYS #2 ACTIVE 345KV HA XFMR RAS SYS #2 TRIP INITIATED 345KV HA XFMR RAS SEL RLY TRBL 345KV HA XFMR RAS SEL BAD COMM 345KV HA XFMR RAS SYS #2 SUSPECT 345KV HA XFMR RAS SEL RLY TRBL 345KV HA XFMR RAS SEL BAD COMM 345KV HA XFMR RAS SEL-87T/AT2 BAD COMM 345KV HA XFMR RAS SEL-87BU/AT2 BAD COMM 345KV HA XFMR RAS SEL-87T/AT3 BAD COMM 345KV HA XFMR RAS SEL-87BU/AT3 BAD COMM
16
CONCLUSION Scheme is fully redundant
Designed to prevent overload on transformer 2 or 3 at Harry Allen for loss of the other Classified as a Local Area Protection Scheme (LAPS) Initiation of RAS results in: Transformers 2 and 3 at Harry Allen out of service Interruption of WECC Path 35 (loss of Harry Allen-Red Butte 345kV line) RAS failure is a non-credible event Failure of a single component, element, or system will not effect successful operation of the RAS Scheme is fully redundant Planned In-Service Date: March 1, 2018
17
QUESTIONS?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.