Download presentation
Presentation is loading. Please wait.
1
Operations Department
Facilities and Services Planning Allen Independent School District
2
2015 Bond Remaining Projects
Kerr Elementary AHS Phase 3 - B Hall/ Admin/Library New Lowery Freshman Center New Dillard Special Achievement Center - Old Lowery Renovation Data Center/Professional Dev./ Board Room Renovation - Old Annex/Dillard/Early Childhood & Language Support Center Renovation Ag Facility Renovation Marion Elementary School Reno AHS Phase 4 - F Hall & Fire Alarm Technology Multimedia/Infrastructure
3
Future Projects
4
Items Included in a Typical Renovation
Facilities Work Items Included in a Typical Renovation Redesign space to meet instructional strategies Flooring - install no wax flooring & upgrade carpet Tile Wainscot New Water Source Heat Pumps Building Envelope Upgrades including: Spray insulation on exterior walls and addition of Brick Weeps Sound proofing of classroom walls Refresh Devices and Multimedia Furniture Civil upgrades - concrete and drainage Landscape Revitalization or Replacement
5
Allen High School
6
Facilities Work AHS G Hall & Corridor / Renovation - 2020
100,000 sq. ft $16,072,250 AHS/Collin College Area Renovation 16,000 sq. ft $2,357,326 AHS H Hall & Corridor Renovation 50,000 sq. ft $8,631,974 AHS J Hall & Corridor Renovation 123,000 sq. ft $22,759,704 Specialized Learning Technologies - $500,000 Total costs shown represent current construction cost with architect fee, commissioning cost, FFE cost, TE cost and a 10% escalation rate
7
Facilities Work AHS K Hall Renovation - 2023
91,000 Sq. Ft.-$17,977,619 Specialized Learning Technologies - $500,000 AHS Athletic Facility Renovation 71,000 Sq. Ft.- $13,183,876 Fire Alarm HVAC upgrades Replace Boilers Convert grass fields to turf Total costs shown represent current construction cost with architect fee, commissioning cost, FFE cost, TE cost and a 10% escalation rate
8
Facilities Work AHS Collin College HVAC upgrades - $97,651 - 2020
AHS G Hall HVAC Upgrades - $97, AHS H Hall HVAC Upgrades - $105, AHS J Hall HVAC Upgrades - $114, AHS K Hall HVAC Upgrades - $122, Total costs shown represent current construction cost with architect fee, commissioning cost, FFE cost, TE cost and a 10% escalation rate Upgrades will remove areas of the building used on non student days off of the chiller and lower the energy usage.
9
Campus Renovations
10
Ereckson Middle School Renovation
Facilities Work Ereckson Middle School Renovation Year Built: 2004 Potential: 2020 and 2021 Square feet: 273, Total Probable Cost: $ 48,155,835 Includes: Two phases of renovations for the building due to size, new roof (1.6 M), adding HVAC condenser and other HVAC efficiencies. Total Probable Cost includes: Renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
11
Facilities Work Boon Elementary School Renovation
Year Built: Potential: 2021 Square feet: 119, Total Probable Cost: $21,984,710 Includes: Renovation of school, replacement of chillers or conversion to Geothermal HVAC (1.3M). Total Probable Cost includes: Renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
12
Chandler Elementary School Renovation
Facilities Work Chandler Elementary School Renovation Year Built: Potential: 2022 Square feet: 119, Total Probable Cost: $23,748,026 Includes: Renovation of building, replacement of boilers plus HVAC upgrades or convert to geothermal HVAC. Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
13
Facilities Work Evans Elementary School Renovation Year Built: 2008
Potential: 2023 Square feet: 119, Total Probable Cost: $25,169,742 Includes: Renovation of building, Replace boilers plus HVAC upgrades or convert to geothermal HVAC Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
14
Olson Elementary School Renovation
Facilities Work Olson Elementary School Renovation Year Built: 2009 Potential: 2024 Square feet: 119, Total Probable Cost: $26,963,283 Includes: Renovation of building, Replace boilers plus HVAC upgrades or convert to geothermal HVAC Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
15
Curtis Middle School Renovation
Facilities Work Curtis Middle School Renovation Last Renovation: 2009 Potential: 2024 and 2025 Square feet: 211, Total Probable Cost: $47,240,881 Includes: Renovation of building, Replace 4 boilers & tanks, Mechanical upgrades on the HVAC system to allow running smaller areas of the building. Project would be done in two phases due to the size. Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
16
Facilities Work Cheatham Elementary School Renovation Year Built: 2010
Potential: 2025 Square feet: 119, Total probable cost: - $28,589,033 Includes: Renovation of building, replacement of boilers plus HVAC upgrades or convert to geothermal HVAC Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
17
Facilities Work Athletic Turf Replacement - $2,360,723
Curtis Stadium Eagle Stadium Lowery Stadium- 2022 AHS Track Stadium AHS Stadium - $318,250 Sealants and misc Athletic Track Resurface - $431,551 AHS Track Stadium Lowery Stadium
18
Early Childhood Renovation - 2020 Agriculture Science Center - 2021
Facilities Work Early Childhood Renovation Square feet: 90, Total Probable Cost - $12,311,773 Agriculture Science Center Square feet: Estimated 62, Total Probable Cost- $11,567,353 Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
19
Administration Building Renovation
Facilities Work Administration Building Renovation Year Built: 2008 Construction and Square feet: 62, Total Probable Cost: $12,496,910 Total Probable Cost includes: renovation cost, escalation cost based on 10% annually, all soft cost including: architectural fee and reimbursables, commissioning cost, FFE & TE
20
Student Nutrition Equipment Upgrades- All Campuses
Maintenance Bond Work Student Nutrition Equipment Upgrades- All Campuses
21
Maintenance Work HVAC Replacement and Efficiencies - $1,153,656
Soundproof classroom walls - $3,196,988 LED lighting efficiencies (interior & site) - $1,722,528 District Concrete Work (AHS fire lane, Vaughan bus, misc.) - $1,770,963 Breezeway waterproofing at renovated ES sites - $1,783,583 District Electrical Upgrades - $607,147 District Waterproofing - $1,000,000
22
Transportation Purchase New School Buses - $4,611,115
Vehicle Maintenance Equipment - $120,662 Bus Rider Safety Solution - $474,198 Retrofit Existing Buses with Seat Belts - $1,004,656 Communication Equipment - $19,578 Total costs are based on current cost with 3% a year escalation
23
Security Security Door/Window Frames/Resistant Film - $1,124,483
Security Camera Upgrades and Additions - $791,300 Access Control System Upgrades and Additions - $870,121 Cost are based on current cost with 3% a year escalation
24
Technology Fiber WAN Expansion - $1,500,000 WAN connectivity
Current 10-year contract Unite Private Networks Services end in 2022 Current costs $360,000 per year Change services to Region 10 Fiber Consortium Estimated annual cost approx. $36,000 per year. Bandwidth would increase from 1GB to 10GB for most campuses Larger facilities bandwidth would increase from 10GB to 40GB
25
Technology Technology Computer Refresh - $17,000,000
Established ongoing lifecycle management strategy End-user computer devices Instructional technologies Purpose Proactively plan for the procurement Upkeep of campus technologies Avoid operational risk Not retaining out of date/older hardware Less reliable hardware Unsupported hardware
26
Technology Classroom Multimedia - $8,300,000
Recommending replacement of end-of-lifespan projectors with interactive flat panel displays Increased collaboration options with multi-touch capabilities Allows multiple students working on the board at the same time Built-in screen casting and screen sharing capabilities More durable than projector Do not require constant recalibration of the system Do not require the bulb maintenance or filter replacements Commercial LED panels rated for up to 50,000 hours of use before replacing. Projectors rated 8, ,000 hours Recommend to Install interactive flat panel displays in K-8 classrooms
27
Technology Infrastructure Upgrades - $13,000,000
Wireless Infrastructure Upgrades Network Connectivity/Switch Upgrades Server Storage Voice Over IP Upgrades (VoIP) IP Bell/PA Structured Cabling Cell Phone Repeater- 2 story, AHS, LFC
28
Facilities and Services Planning
Cost of Work/Budgeting Renovation / Construction / Maintenance items - $355,093,392 Technology Projects - $39,800,000 Transportation Projects - $6,230,208 Security Projects - $2,785,904 Total - $ 403,909,505
29
Any questions?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.