Commissioning Procedure for bKAGRA Phase 1 (2017.9-2018.3)
JGW-T December 16, 2016 Updated based on latest schedule on June 12, 2017 Commissioning Procedure for bKAGRA Phase 1 ( ) Yuta Michimura Department of Physics, University of Tokyo see, also, JGW-T for interferometer design and commissioning schedule
2
Major Updates v X and Y CRYp installation almost at the same time (much earlier X installation) - MICH lock at room temp. before cooling down (instead of cooling ETMY first) - AS cannot be used when room temp. lock since SR3 is not ready - SR2 won’t be ready by Phase 1 deadline
3
Vacuum Layout Legend chamber duct bellows gate valve optical table
TRY Vacuum Layout EYT GVbrty φ100 Legend chamber duct bellows gate valve optical table EYC IFI EYA GVetmy φ100 GVitmy φ100 IYA POP IYC GVbsy φ150 IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP GVbsx φ150 GVitmx φ100 GVetmx φ100 GVbrtx φ100 SR2 POS SR3 AS SRM
4
8.31 9.7 TRY Expected Situation EYT PSL & IMC ready, beam reached PRM (by ) BS (by ) soon ready and PRs (by ) ready SR2 (by ) and SR3 (by ) not ready EYT BRT installation ( ) EYC EYA Yarm evacuated IYA PR3-2 not connected GV closed IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS Xarm evacuated bellows around BS not connected SR3 bellows between SR2 and SR3 not connected AS SRM SR2 ( ), SR3 ( ) installation
5
9.22 TRY Connect PR3-2 Duct EYT connect PR3-2 duct to start initial alignment connect it after the start of ETMY CRYp installation EYT BRT installation ( ) EYC ETMY CRYp installation starts ( ) EYA control 300K was skipped? IYA connect PR3-2 duct IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS SR3 AS SRM SR2 ( ), SR3 ( ) installation
6
Alignment from IMMT to PR3
TRY Alignment from IMMT to PR3 EYT beam spot on PR3 has to be off the center by -5 mm in Y, since there’s no ITM wedge EYT BRT installation ( ) EYC ETMY CRYp done ( ) EYA IYA steer IMMT2 to center the beam on PRM and PR2 IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS steer PR2 to -5 mm off in Y from the center of PR3 SR3 AS SRM SR2 ( ), SR3 ( ) installation
7
Alignment from PR3 to Xend
TRY Alignment from PR3 to Xend EYT need to calculate the beam position on GV windows EYT BRT installation done EYC EYA EYA NAB installation starts ( ) Thorlabs PDA100A (DC PD) IYA ?? mm of the center of GVitmx window IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS steer PR3 to center the beam on BS and reach EXA Thorlabs PDA100A (DC PD) SR3 AS SRM SR2 ( ), SR3 ( ) installation
8
Alignment from BS to Yend
TRY Alignment from BS to Yend EYT need to calculate the beam position on GV windows EYC EYA EYA NAB installation ( ) Thorlabs PDA100A (DC PD) IYA ?? mm of the center of GVitmy window IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS +5.6 mm off the center in Y of EXT BRT (although the beam reach EXT, BRT is not ready yet at this point) SR3 steer BS to reach EYA AS SRM SR2 ( ), SR3 ( ) installation
9
TRY Beam Collimation EYT measure the beam profile at PR3, PR2 and IXA (or IYA) adjust PR2-PR3 lengths if beam looks bad (we won’t try PRMI at first, so we don’t have to move PR2/3 if the beam is not terrible) EYC alignment of TMSY BRT And TRY table optics (maybe too dim) ( ) EYA EYA NAB installation ( ) IYA ETMX CRYp installation starts ( ) IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS block so that beam don’t reach Xend beam profiling beam profiling (adjust PR2-3 length) SR3 AS SRM SR2 ( ), SR3 ( ) installation
10
TRY Align ETMY EYT align ETMY ~1.5 month after ETMY CRYp installation completion also align TMSY EYC align ETMY so that the beam reach REFL EYA EYA NAB installation ( ) slit at EYA for ETMY alignment IYA ETMX CRYp installation done ( ) IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS block so that beam don’t reach Xend Thorlabs PDA100A (DC PD) SR3 AS block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
11
TRY Align ETMX EYT align ETMX right after ETMX CRYp installation completion EYC EYA EYA NAB installation ( ) IYA align POP in-vac optics align ETMX so that the beam reach REFL IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS SR3 AS block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
12
11.8-11.14 Align Aux Optics 11.20-11.24 align REFL, POP, TRY
EYT align REFL, POP, TRY EYC align TRY table optics (maybe too dim) EYA EYA NAB installation ( ) IYA align POP in-vac optics IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS align REFL table optics SR3 AS block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
13
2.12-2.16 Michelson LSC 11.27-12.1 lock Michelson with REFL_Q
TRY Michelson LSC EYT lock Michelson with REFL_Q SR3/2 is not yet ready EYC EYA EYA NAB installation done ( ) IYA IYC EXT BRT installation starts ( ) PRM misaligned IFI IMM PRM PR3 PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS lock Michelson SR3 AS align POP table optics block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
14
Prepare for EY Evacuation
TRY Prepare for EY Evacuation EYT preparation works before evacuation EYA NAB won’t be suspended if no time; EY evacuation is first priority EYC prepare for EY evacuation EYA IYA IYC EXT BRT installation ( ) IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS align POP table optics SR3 AS block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
15
TRY EY Evacuation EYT monitor beam at REFL, POP, TRY during evacuation (EXT BRT alignment without ETMX; +5.6 mm off the center in Y at EXT) EYC evacuate EYA+EYC EYA IYA IYC EXT BRT installation ( ) IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS SR3 AS block so that beam don’t reach SR3 SRM SR2 ( ), SR3 ( ) installation
16
Prepare for EX Evacuation
TRY Prepare for EX Evacuation EYT preparation works before evacuation EXA NAB installation is currently scheduled ; it won’t be suspended if no time; EX evacuation is first priority EYC EYA IYA IYC EXT BRT installation ( ) IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS prepare for EX evacuation SR3 install fixed SR2? AS SRM SR2 ( ), SR3 ( ) done
17
TRY EX Evacuation EYT monitor beam at REFL, POP, TRY, AS during evacuation TRX will be available afterwards AS alignment (CHECK: beam spot position on SR3) steer SR3 to center the beam on SR2 measure beam profile at SR2 and SR3 AS for Phase 1 is a reflected beam from SR2, extracted at SR3 chamber EYC EYA IYA IYC EXT BRT installation ( ) IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS evacuate EXA+EXC SR3 AS keep GVetmx closed (we can open this if we have spare time) AS alignment with fixed SR2? SRM
18
12.8 12.27 TRY EY Cooling Starts EYT monitor beam at REFL, POP, TRY during cool down EYC cool down ETMY EYA keep GVetmy closed (we can open this if we have spare time) IYA IYC EXT BRT installation ( ) IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS SR2 installation continues? ( ) SR3 AS SRM
19
1.2 TRY EX Cooling Starts EYT monitor beam at REFL, POP, TRY, AS during cool down EYC cool down ETMY EYA IYA IYC EXT BRT installation ( ) PRM misaligned IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS cool down ETMX keep Michelson locked SR3 AS SRM installation ( ) SRM
20
2.1 TRY Start Test Run EYT note that central area cannot be evacuated before SRs completion (7.10) since no GV between BS and SRM EYC cool down ETMY EYA alignment of TMSX BRT and TRX table optics (maybe too dim) ( ) IYA IYC EXT BRT installation ( ) PRM misaligned IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS cool down ETMX keep Michelson locked SR3 AS SRM installation ( ) SRM
21
Apr-Jun PRMI??? PR2-PR3 length adjust PRMI alignment, locking
TRY PRMI??? EYT PR2-PR3 length adjust PRMI alignment, locking connect remaining bellows/ducts evacuate central area open GVs (GVsrm should be closed) EYC cool down ETMY EYA PR2-PR3 length adjust (Michelson re-alignment needed) IYA central area evacuation PRM alignment to make PRC IYC IFI IMM PRM PR3 PR2 BS IXC IXA EXA EXC EXT TRX REFL POP SR2 POS SR2 installation continues? ( ) cool down ETMX lock PRMI with ASC SR3 AS GVsrm: closed SRM installation ( ) SRM
22
Some Notes Update NAB installation schedule?
Confirm beam spot positions at GVs