Eric Montesinos LIU-SPS coordination meeting 23rd May 2014
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 23rd May 2014
2
(still SSPA, Klystron, IOT)
Amplifiers Drivers (SSA): MS completed : 17 companies selected IT completed : selected company under qualification FC March 2014 Finals (SSA or Tetrodes): MS completed : 7 9 companies selected TS to be send out June 2014 FC December 2014 Combiners (3 dB above 100 kW) In house TTE fellow Transmission lines (coaxial, 345 mm outer) During Winter shutdowns Tetrode vs Diacrode (still SSPA, Klystron, IOT) 23th May 2014 LIU SPS RF
3
April 2014 amplifiers Schedule
2015 2016 Drivers December CERN approval for Series Production (after LD tests) IT : Invitation to Tenders FC : CERN Finance Committee FAT : Factory Acceptance Tests CERN AT : CERN Acceptance Tests LD Tests : Long duration tests : Long Technical Stop, No beams August Pre-series CERN AT October IT sent March First Series FAT June Pre-series FAT December Last Series CERN AT March FC Order placed 2015 2016 2017 2018 2019 March CERN approval for Series Production (after Pre-series LD tests) Finals September First Series FAT June Ready for operation May IT sent December FC Order placed June Pre-series FAT LSS3 upgrade & connection of amplifiers December 2014 Decision for technology September 2015 First RF tests March 2017 CERN full RF tests 23th May 2014 LIU SPS RF
4
April 2014 9 months cavities re-arrangement
4 months RF Power conditioning 5 months LLRF commissioning 2011 2012 2013 2014 2015 2016 2017 2018 2019 Studies Tendering Construction Installation New RF Power Amplifiers and LLRF LLRF Design and proto Commissioning Start up LLRF Tests LLRF Series Studies Coaxial Lines Cavities pickups vacuumCV, EL HBW (kicker and Pickup) LSS3 Tunnel Integration Spare sections New power couplers Studies Authorizations Construction BAF3 RF Building Studies Services Tests 1/4 of full power Full Power 23th May 2014 LIU SPS RF
5
LIU-SPS RF upgrade Working Group Members
Dep-Group Persons BE-RF Eric Montesinos, Charles Julie, Simon Rains, SPS power team, Thomas Bohl, Wolfgang Höfle, Urs Wehrle, Elena Shaposhnikova, Philippe Baudrenghien BE-ABP Ghislain Roy (BE space manager), Patrick Bestmann, Yannis Papaphilippou BE-ASR Marc Tavlet, Christelle Gaignant, Axelle Deleu BE-BI Christian Boccard, Patrick Odier DGS-SEE Guillaume Fontana, Cécile Pinto DGS-RP Nadine Conan, Christophe Tromel EN-CV Mauro Nonis, Michele Battistin, Aurelio Berjillos Barranco, Alexandre Broche EN-EL Guillaume Gros, Jean-Pierre Sferruzza, Christophe Crombez, Denis Ribiollet EN-HE Caterina Bertone, Pascal Brunero, Serge Pelletier, Yann Seraphin, Patrick Vallet, Gilles Roche, Helder Lorenco EN-MEF Frédéric Galleazzi, Yvon Muttoni, David McFarlane, Antoine Kosmicki, Emmanuel Paulat GS-SE Luz-Anastasia Lopez-Hernandez, Laurent Faisandel, Christophe Biot TE-EPC Gilles LeGodec, Christophe Coupat TE-MSC Jérémie Bauche TE-VSC Paolo Chiggiato, Antonio Mongelluzzo, Jose Antonio Ferreira Samoza 23th May 2014 LIU SPS RF