1
Monitoring Structures & Processes to ensure that the pothole reparation project across the 9 Provinces has the necessary delivery impact" 02 August 2011
2
Background Commitment to job creation made in the President’s State of the Nation Addresses Minister of Transport in his budget speech made commitment to roll out Zibambele road maintenance programme nationally Transport agencies required to also heed the call for job creation
3
Key Outputs It is a “conditional grant” to address the following key outputs Collected traffic volumes data and pavement condition data Updated road asset management systems Squared kilometres of preventative, routine and emergency maintenance work Percentage of roads for which condition of roads changed from poor and very poor to at least fair Ensure job creation & contractor development through the above activities
4
Key Pillars of the Programme
Increase investment in maintenance of key arterial routes to support the rural economy Increased focus in the cost efficient use of labour absorptive methodologies in road construction and maintenance; Know your network: A focused attention on deployment of local resources to support road network asset management Improving Access to Schools and Clinics and other public facilities Delivering a Safe Road environment
5
Provincial Roads Maintenance Grant Allocations to provinces
Vote Name of allocation Province 2011/12 2012/13 2013/14 Transport (Vote 36) R'000 Provincial Roads Maintenance Grant Eastern Cape Free State Gauteng, Includes Coal Haulage 74 4.4 0.9 KwaZulu-Natal Limpopo Mpumalanga 511 659 808 Northern Cape North West Western Cape Unallocated - TOTAL
6
Targets for job creation per province
7
Monitoring Structures & Processes for S’hamba Sonke Programme
Business Plan Guidelines were issued to Provinces to address the key pillars of the S’hamba Sonke Programme Assessment of Provincial Business Plans to verify S’hamba Sonke requirements are being addressed Selection of and Gazetting Projects. Standard Reporting Formats have been issued to the provinces to track progress.
8
Work in Progress Setting up & operating a National / Centralised Call Centre to report Potholes Finalisation of mechanisms to: Update of the Road Authorities Database (Contact Information) Redirect the compliant to the correct Road Authority Follow-up and reporting back to the callers Development of guidelines for Provincial Road Authorities to develop a Road Asset Management Plan that is compliant with the requirements of the Government Immovable Assets Management Act (GIAMA).
9
Work in Progress Finalisation and rollout the Program Management Unit - Nationally and Provincially DoT processing its support appointment for Project Management Unit Challenges - Funding Constraints by National Treasury for the Project Management Unit
10
Progress Overview Prov PRMG Allocation 2011/12 Amount Transferred
13 May 2011 Spent to date Job creation data Comments Work opportunities Full time equivalent Women Youth EC N/A Job creation data pending FS 75 029 81 926 610 48 260 354 GP 55 017 1409 774 564 These are planned. All projects has not started KN 39 574 5 124 30 400 9700 LM 97 817 19 187 No figures 13 187 754 MP 518 NC 86 085 88 472 3 299 323 2 233 959 NW 57 642 21 962 198 56 WC 61 191 2 056 Only WO received TOTAL 66 851 6 960 46 854 12 331
11
Current challenges and how are we addressing them within the roads projects lease indicate
Challenges in road infrastructure delivery Eg Norms and standards / reviewing and developing them Costing models for similar type road structure / putting in place effective costing model for infrastructure Industry monopolization / collusion / developing effective industry understanding , and industry monitoring Funding models / developing alternative funding models and operational models
12
THANK YOU