Download presentation
Presentation is loading. Please wait.
1
Operations/Failure Analysis
Status of Equipment/Production Readiness Plans in Case of Part/Systems Failure For Each Stand Type
2
Inventory The US testing group has finished a complete inventory of all components of used in hybrid/module/rod testing The inventory is available on the UCSB CMS website In the process, we have identified many more potential failure modes for our stands than we previously anticipated DAQ equipment, cables, Vienna box interlock spares, chillers, CAEN power supplies, etc. We have contacted all the people responsible for the components and hopefully we can receive all the spares we need before production fully starts
3
DAQ Components The request for spare components has been out of over 5 months now. We still need: 2 TSC 1 FED (replacement for broken UCSB board) 3 TPO 2 CCU25 4 VUTRI 6 PAACB 11 hybrid-to-utri boards All requests acknowledged and accepted. No ETA given for any of the parts.
4
Cables We have 48 different cable types in the systems
29 types have no spares 8 more have inadequate number of spares Most can cause a complete system failures We have requested spares for all cables that we can not make ourselves Duccio and Wim have already responded We are making a number of the cables ourselves Ribbon cables for the TRHX box for the Module LT stands TPO-to-VUTRI control cables
5
CAEN Power Supplies With the new crate rented from CERN, we have the exact number we need CERN has recently ordered more CAEN crates (SYS127) and controller cards (A128HS and A1303). We have requested one set as a spare for the US With the UCR ordered controller modules: We will have spares of all modules at both UCSB and FNAL
6
Assorted Equipment Issues (I)
UCSB needs to order/manufacture a spare of all components used in 4 hybrid test box Both FNAL and UCSB have found a spare NIM and VME crate A spare set of LeCroy modules needs to be located for pulser logic of 4 hybrid thermal cycler Spare computers with hybrid/module software needs to be assembled and tested for UCSB/FNAL Spare computers with module LT/single rod/multi-rod/interlock software needs to assembled and tested for UCSB/FNAL
7
Assorted Equipment Issues (II)
Torino has agreed to supply spare Vienna box interlock equipment for each site Vienna has agreed to supply spare Vienna box sensors (RH% and T) to both FNAL and UCSB We have ordered a spare chiller for both the hybrid thermal cyclers and the Vienna boxes
8
Test Stand Failure Analysis
We have a draft of the US testing operations/failure analysis document available at: The process was really useful; it got us to think of worse case failure scenarios and how we could operate under such conditions
9
4 Hybrid Thermal Cycler Biggest strength is the large over-capacity we have in the group We can test ~90 hybrids per day with expected peak rate of 45 hybrid per day assuming 400 per week from company If global failure, move production to other sites As long as we have a stockpile of bonded hybrids, it will not affect production. Otherwise, production slowed due to shipping times The stands have three primary weakness: software, the Peltier element, and the NESLAB chiller Backup computer and spare Peltier elements at each site reduces these risks We have ordered a spare chiller which can be shipped in case of a chiller failure UCSB obtaining spares of all other components which could be shipped overnight in case of failure
10
ARCS module testing We are in the best shape with these stands
We can test ~17 modules/stand/day with expected peak rate of production of 30. Rate made possible by improvements of ARCS software and automation of data handling FNAL has 4 stands, UCSB has 3 stands, UCR has 1 stand Both sites have a complete live spare Obtained spare cables to reduce stand down-time to minimum Repairs from Aachen have only taken 2-4 weeks in past Biggest headache would be a complete failure of CMS database No wire bonding data, sensor data, or hybrid data Will have to find all faults during testing. May require each part to be tested twice. Would have to check testing results against known failures after database is working. Running more than two stands should remove back-log of parts.
11
Module LT systems Since expected production rate exceeds testing capacity (30 vs 15 modules a day) any failure would increase fraction of sampled modules Only way to clear backlog is weekend testing We are exploring reduction of tests to increase capacity to 20 per day To prevent failures, spares acquired or ordered of almost all components: Power supplies, DAQ components, cables, chillers, interlocks, etc. We also modified Vienna box to be more stable/long-lived Brass plates and extender connectors If the stand is completely non-operational, production can still continue All production should be TOB. Only produce what can be assembled/tested on rods. Would reduce production capacity to ~20 modules a day
12
Single Rod System Test systems have over-capacity
2-4 rod assembled a day with ~8 rod test capacity/stand/day Same issues with DAQ equipment/CAEN HV as module LT Ordered 6 extra MUX to remove need of recabling Cables from Duccio ordered: electrical and optical Two pieces of equipment with no spares in foreseeable future: OEC & Delphi LV power supply In both cases, take OEC or PS from multi-rod stand (with multi-rod loss of capacity of 7% and 12%) If single rod stand fails completely, production can still continue a slower rate Test rods as they are loaded into multi-rod stand. Adds 1 day per test cycle Will have to reduce rod assembly rate to match testing rate UCSB should switch to mostly TEC production
13
Multi-rod System Most complex system with least amount of experience
Same potential problems as module LT or single rod systems plus: Chiller Interlocks Freezer infrastructure UR have thought about different operational scenarios for these components; will have to be revisited after accumulation of more experience Spares in hand of all components that company believe could likely fail Plan for finding and removing leaks in the cooling system needed 1 or 2 spare C6F14 loads needed at both sites
14
Multi-rod System (2) Interlocks
Spares of sensors, etc. that can be easily replaced already ordered If interlock hardware fails: Company has 48 hour express repair plan Power supply interlocks would be used Control of system by hand until repair made If case of complete system failure, rod assembly at site can still proceed at a lower rate All rods will have to be tested with single rod stand Single rod stand would have to reproduce as many of the multi-rod stand’s testing until multi-rod available Only way to remove the backlog of rods assembled would be the reduction of the testing cycle time.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.