CONGREGATIONAL INFO SESSION #2 By The Building Committee
April 30, 2017
2
CAPITAL CAMPAIGN 1 PLEDGES
OUTSTANDING NEWS !!!!! CAPITAL CAMPAIGN 1 PLEDGES $3,475,169 THANK YOU!!!!!!
3
NOT NEEDED FOR FULL BUILDOUT !!!!
FANTASTIC NEWS !!!!! 85,000 SF NOT NEEDED FOR FULL BUILDOUT !!!!
4
MEETS OUR MNET NEEDS IN FULL !!
AMAZING NEWS !!!!! 68,000 SF MEETS OUR MNET NEEDS IN FULL !! SAVES $3.5 M PRAISE GOD!!
9
CONSTRUCTION BUDGET TOTAL BUDGET FOR SGC $12,729,807
SJB 04/30/17 TOTAL AVAILABLE $ 4,974,638 SELL CURRENT FACILITY $ 1,500,000 CAMPAIGN 1 PLEDGES $ 3,475,169 ADDITIONAL GIFTS & CAMPAIGN $ 2,780,000 TOTAL BUDGET FOR SGC $12,729,807
10
CONSTRUCTION COST ESTIMATE
SJB 04/30/17 SITE WORK, 68,000 SF BLDG, FEES, FURNISHINGS, AVL, 10% CNTGY: Range Cost Budget Difference LOW $ 13.5M $ 12.7M $ 0.8M ($140/SF) MED $ 14.3M $ 12.7M $ 1.6M ($150/SF) HIGH $ 15.5M* $ 12.7M $ 2.8M ($175/SF) * 5% Contingency on building; 10% contingency on rest
11
WAYS TO SAVE FOR DEBT-FREE PROJECT
SJB 04/30/17 REDUCE OVERALL BUILDING SIZE LESS EXPENSIVE FINISHES – INTERIOR LESS EXPENSIVE FINISHES – EXTERIOR CUT BACK ON SITE WORK PHASE THE PROJECT DIRECT UNDESIGNATED GIFTS & ESTATES TO FUND PROJECT NEXT 6 YRS
12
June 11 945 – 1045AM Sanctuary & 1100AM – 1200PM MPR
CONGREGATIONAL INFO SESSIONS DESIGN UPDATES BY THE BUILDING COMMITTEE AND Q&A June – 1045AM Sanctuary & 1100AM – 1200PM MPR July – 1045AM Sanctuary & 1100AM – 1200PM MPR Aug – 1045AM Sanctuary & 1100AM – 1200PM MPR
13
QUESTIONS ??? & COMMENTS