Presentation is loading. Please wait.

Presentation is loading. Please wait.

Minuteman Vocational Technical Regional High School Progress

Similar presentations


Presentation on theme: "Minuteman Vocational Technical Regional High School Progress"— Presentation transcript:

1 Minuteman Vocational Technical Regional High School Progress
December 17th 2018 – January 22nd 2018

2 January 22nd View of Area A+B – Upper Level
Prime & First Coat of Painting Complete Ceiling Grid installation in progress January 22nd View of Area A+B – Lower Level MEP Devices – Lights, Cord Reels, Grilles installation in progress

3 January 18th View of Area A+B – Roof Level
Roof Top equipment has been set, connections to equipment in progress. January 22nd View of Area A+B – Main Elect. Rm Permanent switchgear has been set. Distribution and terminations in progress.

4 January 18th View of Area G – Roof Level
Roof Top Air Handlers have been set & connected. Metal Panel screen wall around perimeter of units in progress. January 22nd View of Area G – Upper Level Prime & First Coat of Painting Substantially Complete Ceiling Grid Installation to commence.

5 January 22nd View of Area E – East Elevation
Roof Soffit Sheathed & AVB Complete. Masonry Stone Veneer in progress on lower level.

6 January 22nd View of Area E – Media Center
Rough-in of Overhead MEP’s in Progress Wall Framing in Progress on Upper and Lower Levels.

7 January 22nd View of Area D – Upper Level
Sheetrocking activities completed. Taping & Sanding Activities nearing completion.

8 January 22nd View of Area D – Gymnasium
Rough-in of large overhead MEP’s is complete. Prime painting of walls, roof deck and MEP’s in progress.

9 January 22nd View of Area D – Mechanical Room
Boilers, Pumps, Chiller and Water Heaters have been set. Terminations to equipment is in progress.

10 January 22nd View of Area E+F – Cafeteria
Rough-in of overhead MEP’s is complete. Soffit framing in progress. Sheetrocking activities on Upper Level in progress.

11 January 22nd View of Area F – East Elevation
Curtain Wall installation substantially complete. Architectural stone veneer complete. Metal panel installation in progress. January 22nd View of Area F – Lower Level Interior CMU wall construction complete. Interior wall framing in progress.

12 January 22nd View of Area C – West Elevation
Masonry Veneer activities complete on the Theater tower. Veneer activities on the lower level in progress. January 22nd View of Area C – Mezzanine Level Misc Metal stairs and railings in progress. Overhead rough-in of MEP’s in progress.

13 January Construction Schedule Look Ahead:
Area A+B Complete Taping on Lower Level B Commence Prime Painting on Lower Level B Commence installation of Lights, Registers and other MEP devices in ceiling grid Area G Complete taping activities on the Lower Level Continue prime painting activities on the Lower Level Commence Ceiling Grid installation on the Upper Level Area E Complete Curtain Wall & Window System installation Complete Rough-In of OH MEP’s on all levels Complete Wall Framing activities on all levels Continue Rough-In of in-wall MEP’s Continue Sheetrocking activities Area D Complete Masonry Veneer activities Complete Taping activities on Upper Level Continue Terminations of MEP’s to equipment in Mechanical Room Commence Prime Painting on Upper Level Area F Complete Rough-In of OH Duct work. Continue Wall Framing activities Commence Rough-In of in-wall MEP’s Area C Complete exterior masonry veneer on remaining elevations. Continue Rough-In of OH MEP’s over the theater space. Exterior/Sitework Complete setting balance of equipment curbs and equipment on all roof levels. Permanent power established for the building targeted for mid-February Project team currently coordinating with National Grid to obtain a schedule for the gas installation

14


Download ppt "Minuteman Vocational Technical Regional High School Progress"

Similar presentations


Ads by Google