1 Technical report Mats Lindroos

2 Consolidation project; part financed by ISC
Outline Shutdown work Consolidation project; part financed by ISC Extensions

3 Shutdown work Migration of control system to JAVA
Good progress Acceptance tests planned for March Work coordinated by Jose Sanchez (AB/OP) Emittance measurements on-line Renovation of stepping motor system General shutdown work

4 And the Emittance LA2 Experiment After HRS Magnet
Fredrik Wenander, Tomas Fritioff, Tim Giles

5 ISOLDE consolidation HRS: Comment: Status: Milestones:
Existing pool face windings restricted to corrections for masses below 13 due to “unexpected” field suppression from iron yoke Status: In progress Milestones: Emittance meters for 2004 run Study of external correctors and pool face shaping (simple) for 1 June 2003 Implementation of possible improvement for run in 2004 Budget from ISOLDE collaboration: Total: 300 kchf Committed: 5 kchf Responsible: Tim Giles and Thomas Fritioff

6 A New Emittance Meter for ISOLDE
Tomas Fritioff

7 A New Emittance Meter for ISOLDE
Beam energy keV Emittance p mm mrad Emittance meter should be small, 10 cm. Tomas Fritioff

8 ISOLDE consolidation RFQ cooler: Status: Milestones:
In progress Milestones: Specification and budget for 15 March 2003 Drawings for 1 October 2003 Assembly complete for 1 March 2004 Off line tests finished 1 November 2004 Commissioning 1 March 2005 Budget from the ISOLDE collaboration and BMBF (LMU) Responsible: Ari Jokinen and Ivan Podadera

9 General Purpose RFQ cooler
Ari Jokinen, Ivan Podadera, Tomas Fritioff

10 ISOLDE consolidation RILIS: Status: Milestones:
In progress Milestones: Laser beam diagnostics - mid 2003 CVL beam guidance (screening of the laser beams) - mid 2003 Automated beam positioning - mid 2004 Automated laser power monitoring - mid 2004 Budget from the ISOLDE collaboration: Total: 220 Committed: 110 kchf Responsible: Valentin Fedosseev

11 ISOLDE consolidation Beam transport: Status: Milestones:
In progress Milestones: Emittance measurements in Off-line period Documentation and proposal by 1 July 2003 Budget from the ISOLDE collaboration Total: 140 kchf Committed: 140 kchf Responsible: Fredrik Wenander and Tim Giles

12 ISOLDE consolidation Tape station hardware Status: Milestones:
In progress Milestones: Definition March 2003 Budget from ISOLDE collaboration: Responsible: Gerrit Jan Focker and Philippe Dessange

13 Extensions Radioactive laboratory off class A (building 179)
Details for financing under finalization Solid state laboratory (building 115) Financed through ISC Extension of hall Financing under discussion with the main part being external

14 Building 170