Coronado Elementary School Project Status

Similar presentations


Presentation on theme: "Coronado Elementary School Project Status"— Presentation transcript:

1 Coronado Elementary School Project Status
Facilities Subcommittee Meeting April 14, 2015 Coronado ES Project Status

2 Building A – Main Entrance
Coronado ES Project Status

3 Building A – From Northwest
Coronado ES Project Status

4 Coronado ES Project Status
Lunch Shelter Coronado ES Project Status

5 Coronado ES Project Status
Playground Coronado ES Project Status

6 Coronado ES Project Status
Typical Classroom Coronado ES Project Status

7 Project Schedule Summary
Bid Date: October 22, 2013 BOE Award Date: November , 2013 Notice to Proceed January 6, 2014 Duration 510 Days Approved time extensions 0 Days Revised contract completion date June 9, 2015 Potential time extension 21 Days Anticipated completion date June 30, 2015 Coronado ES Project Status

8 Coronado ES Project Status
Project Cost Summary Bid Amount $26,974,910* (10/22/13) Change Order Summary (through 04/08/15) Approved C.O.’s $706,109 (2.62%) C.O.’s in Progress $65,833 (0.24%) C.O.’s Under Review $529,775 (1.96%) Rejected C.O.’s* $80,195 _______ $1,341,842 (4.62%) Note: Rejected C.O.’s (0.03%) are potential claims. Additional undetermined issues are possible through completion of project. (* 14.5% over estimate) Coronado ES Project Status