Preesall Underground Gas Storage Scheme
Halite Energy Group Community Liaison Panel (CLP) 3rd Meeting 15th January 2019 Confidential
2
Preesall Underground Gas Storage Scheme Masterplan
3
Preesall Underground Gas Storage Scheme
Indicative Time-Line of Events = Phase 1A Activity 2016 2017 2018 2019 2020 2021 2022 2023 2024 Preconstruction surveys & reports Basic Infrastructure & Civils Sea water supply Brine outfall Electricity supply NTS (Gas) connector Gas compound Wellhead compounds etc Cavern washing Approvals & operation
4
Preesall Underground Gas Storage Scheme Status in More Detail
Development Consent Order Pre-Construction Requirements being completed. Section 106 Agreement requirements being met, with more to do; Key Environmental Surveys, Marine Surveys, Archaeological Surveys done in 2018; Key stakeholders engaged; Wyre Council , Natural England, Environment Agency, Lancashire County Council, Health & Safety Executive, Lancashire Wildlife Trust, Marine Management Organisation (MMO), Knott End Golf Club, National Grid, The Crown, The Duchy; Electricity North West. Cavern operating requirements modelled in more detail, better definition, improved safety; UK Government engaged, OFGEM, BEIS, UK Treasury, DEFRA Construction Plan will ensure delivery of first gas by December 2022; and Contracts for advanced works awarded – access road to site, scrub clearance & road preparation
5
Key Preesall Credentials
Preesall Underground Gas Storage Scheme Key Preesall Credentials Preesall Gas Storage Operation: 12 day injection / withdrawal cycle; Capable of cycling 28 times a year; Cycling volume potential of 7.8 bcm per year; Variable cycling cost of 0.31 p/therm; and Preesall’s Competitive Advantage: Faster cycling speed; Lower cycling costs; Virtual cavern design – Preesall can cycle at a higher rate & be worked harder over short time periods (e.g., 6 to 12 hour periods within day); and Significant site development opportunities - a Phase 2 could add caverns doubling WGV and enhancing IRR, utilizing Phase 1 above ground infrastructure.
6
Preesall Underground Gas Storage Scheme January 2019 in Summary
DCO Decision July 2015 Project Delivery Planning Liaison, Surveys, Design and Consents Phase 1a Construction First Gas 2022 Brine outfall Electricity supply NTS connector Gas compound Wellhead compounds etc Cavern washing Approvals & operation Preesall Underground Gas Storage Delivery 6