Protected Bicycle Lanes Finally Pedal Their Way to KC…
PRESENTATION FOR: MWITE DISTRICT CONFERENCE Protected Bicycle Lanes Finally Pedal Their Way to KC…
2
Armour Boulevard Protected Bike Lanes
January 2013: Corridor Study Parking & Traffic analysis Recommendation for “Road Diet” : CMAQ Funding Grants Fall 2015: Design Process Preliminary Design = “Road Diet” Final Design = Protected Bicycle Lanes June 2017: PS&E for Bids
3
Armour Boulevard Protected Bike Lanes
Project Corridor: Broadway Boulevard to The Paseo Total Length = 1.25 miles (20 blocks) Four Travel Lanes + Parallel Parking 35 mph Speed Limit Ex. “Sharrow” Markings ADT Range: 8,000 – 10,000 (West End) 6,000 – 8,000 (East End)
4
Armour Boulevard – Early 1900s
5
Armour Boulevard – 1920s & ‘30s
6
Armour Boulevard – 1940s & ‘50s
7
Armour Boulevard - Today
Broadway Blvd. to Main Street Broadway Blvd. Armour Blvd. Main Street
8
Armour Boulevard - Today
Gillham Road to Holmes Street Gillham Road Holmes Street Armour Blvd.
9
Armour Boulevard - Today
Troost Avenue to The Paseo Troost Avenue Armour Blvd. The Paseo
10
Parking Inventory
11
Parking Accumulation Study
12
“Road Diet” Capacity Analysis
13
“Road Diet” Recommendation
14
“Road Diet” Recommendation
“Road Diet” Configuration: Curb Bulb-outs at Crossings Median Refuge Islands Boulevards under KCMO Parks control No support for any Geometric Modifications Public Works could do PM & Signing only
15
Preliminary “Road Diet” Design
11’ Through Travel Lanes 7’ Parallel Parking Lanes 10’ Center Left-Turn Lane 56’ Face-Face Width Available 5’ Designated Bicycle Lanes
16
Preliminary “Road Diet” Design
Public Involvement Open House Meetings during Study Design Review Meetings w/ Neighborhood HOAs and “BikeWalkKC” advocates Support for Protected Bike Lanes option Political Directive from City Council to PW
17
Final Design – Protected Bike Lanes
Typical Section: 11’ Through Travel Lanes 8’ Parallel Parking Lanes 4’ Buffer Space 5’ Designated Bicycle Lanes 56’ Face-Face Width Available
18
Final Design – Protected Bike Lanes
Armour Blvd. & Main Street Intersection
19
Final Design – Protected Bike Lanes
Designated Bike Boxes for Cyclists
20
Final Design – Protected Bike Lanes
Two-Stage Left-Turn Queue Boxes for Cyclists
21
Final Design – Protected Bike Lanes
Bus Stop Designs for Transit
22
Final Design – Protected Bike Lanes
Buffer Space Delineators
23
Armour Boulevard Protected Bike Lanes
Where are we now? PS&E plans on June 2, 2017 Est. Const. Cost = $466,000 City’s Bidding Strategy Package with Annual Resurfacing contract Need MODOT approval for combined bid Bids due in July 2017 Construction completed by Fall 2017 Effective utility coordination is key to the success of any project. At GBA, we’ve developed a more thorough and in depth process starts before the surveyors are even in the field. We work with each utility individually, verifying existing locations, identifying potential conflicts, reviewing relocation plans. Make sure to look at traffic signal plans, retaining wall footings, sanitary sewer plans, tree removals, roadway subgrade depth, storm sewer, fencing, etc. We ask the utility owners about the condition of their lines or if they have plans for improvements in the near future. If requested, we can provide oversight for the relocations to make sure they’re installed per plan and document for future use.
24
Q & A
25
THANK YOU!