Presentation is loading. Please wait.

Presentation is loading. Please wait.

US TBM Cost Activity Tom Mann December 12 – 14, 2005.

Similar presentations


Presentation on theme: "US TBM Cost Activity Tom Mann December 12 – 14, 2005."— Presentation transcript:

1 US TBM Cost Activity Tom Mann December 12 – 14, 2005

2 Meeting Objectives December 12 – 14, 2005
Cost Activity Scope Cost Activity Schedule ITER Schedule Detailed Cost Presentations R & D Evaluations Total Project Cost (TPC) Cost Range US TBM Schedule Cost Report Outline Summary To DOE

3 US TBM Cost Activity Scope

4 US TBM Costing Activity Milestones
12-Aug-05 Costing Activity Initiated 31-Aug-05 WBS established for Level 6 and lower Responsible persons for Level 6 and lower assigned 7-Sep-05 WBS for Level 6 and lower revised 9-Sep-05 Conceptual design summaries for DCLL and HCCB issued 6-Oct-05 Initial schedule and base cost estimate for WBS level 6 of DCLL and HCCB 27-Oct-05 Initial schedule and base cost estimate for engineering design, procurement/fabrication, and ancillary equipment 7-Nov-05 R&D decision criteria established 30-Nov-05 Complete revised schedule and cost estimate for WBS level 6 and lower (include contingency factor) 12-14 Dec-05 “Physical” Meeting (all information about costing will be presented and discussed) 16-Dec-05 R&D priorities finalized 13-Jan-06 Initial Draft Costing Activity Report Due 15-Feb-06 Complete Draft of Final Costing Activity Report 22-23 Feb-06 Physical meeting (internal review of draft report) 1-Mar-06 Complete incorporating comments into the Report 15-Mar-06 Send Final TBM Cost Estimate Report to DOE 28-Mar-06 “External” review

5 ITER Preliminary Summary Schedule

6 Total Project Costs & Cost Range
Minimum TPC Estimated TPC Maximum TPC 1.8 Test Blanket 1.8.1 DCLL System and Testing Goals Test Module Administration/Integration R&D Tritium Permeation -2.8 Thermofluid MHD 12 SiC/SiC FCI Fab and Properties 2.25 SiC /FS/PbLi Compatibility & Chem 0.75 FS Box Fabrication & Material Issues ----- He Systems Subcomponent Tests 0.84 PbLi/H2O Hydrogen Production 2.4 Be Joining to FS 4.7 Virtual DCLL TBM 4.3 Advanced Diagnostics 2.7 Integrated Mock Ups, ¼ to ½ Scale 4.34 Engineering 16.93 Preliminary Design Detailed Design Title III Fabrication/Procurement 1.28 Assembly, Testing and Installation 2.48 Helium Flow Loop (P+S) 2.66 1.12

7 US TBM Milestones

8 Meeting Summary Review Activity Cost Estimates
Determine R & D Priorities Establish Preliminary Cost Base Line Begin Schedule Integration Including ITER Interfaces Establish Final Report Outline and Writing Assignments – Draft Due January 13, 2006 Report Progress


Download ppt "US TBM Cost Activity Tom Mann December 12 – 14, 2005."

Similar presentations


Ads by Google