Presentation is loading. Please wait.

Presentation is loading. Please wait.

Reducing Project Duration

Similar presentations


Presentation on theme: "Reducing Project Duration"— Presentation transcript:

1 Reducing Project Duration
Chap 9 Reducing Project Duration

2 Why Reduce the Project Time?
Chap 9 Time to Market competition technology Unexpected delays weather equipment failure design issues Imposed deadlines top management goals Focus: Reduce time at Min Cost or Max profit Reassignment of key resources equipment other priority project people

3 Options Overtime Adding Resources easy if available use in moderation
Chap 9 Overtime easy use in moderation impact on morale productivity Core Project Team allows for focus shared goal program manager control Do it twice – Fast & Correctly redefine task for interm solution likely more costly, time & money use only when agreed by client Adding Resources if available issue of productivity more coordination required delay in training Outsourcing frees up internal resources lose of control may reduce costs core competency issue

4 Options when resources are constrained
Chap 9 Fast Tracking review for parallel activities reconsider precedents Critical Chain Individual buffers vs Aggregate buffers Forward vs Backward scheduling Worst Case vs Average time estimates Reducing Project Scope transfer some activities to client Compromise Quality establish what level of quality is required rather than is preferred. Using the Critical Chain Method, projects can be completed more quickly and with greater scheduling reliability. The difference between traditional and Critical Chain scheduling is in how uncertainty is managed. In traditional project scheduling, uncertainty is managed by padding task durations, starting work as early as possible, multi-tasking, and focusing on meeting commitment dates. The following bullet points illustrate some of the problems associated with traditional project scheduling: Padding task durations (providing worst-case estimates) is done to ensure a high probability of task completion. The knowledge that there is so much safety time built into tasks results in various time wasting practices, e.g., waiting until the last moment to complete a task. As a result, all the safety time can be wasted at the start of the task so that, if problems are encountered, the task over-runs. Starting work as early as possible, even when not scheduled, is a response to worst-case estimates. When workers give worst-case estimates, they don’t expect to stay busy with just one task – so they multi-task, working on several tasks at once by switching between them. The result is that everything takes a long time to complete and very little completes early. With the focus on meeting commitment dates (start and finish), output from a task completed early will rarely be accepted early by the next person needing this output. So, any effort spent in finishing early will be wasted. Early delivery of one task can’t be used to offset lateness on another. Lateness, however, is always passed on and the lost time can’t be made up without cutting the specifications or increasing resources allocated to subsequent tasks, if possible. Given the these issues, it’s not surprising that the most projects are always late. In Critical Chain scheduling, uncertainty is primarily managed by (a) using average task duration estimates; (b) scheduling backwards from the date a project is needed (to ensure work that needs to be done is done, and it is done only when needed); (c) placing aggregate buffers in the project plan to protect the entire project and the key tasks; and (d) using buffer management to control the plan. The key tasks are those on which the ultimate duration of the project depends, also known as the Critical Chain.

5 Project Costs to Consider
Chap 9 Project Indirect Costs overhead costs ( supervisor, admin, consultants, interest) typically linear cost increase as project time increases Rate of change is constant Project Direct Costs labor, materials, equipment and sometimes subcontractors mostly curvilinear costs decrease as project time increases longer time the resources can be spread out short time requires more resources at premium costs Source of Costs? Objective is to find the Optimum Total Costs Total Costs = Indirect costs + Direct Costs

6 Crashing A Project Characteristics Costs of crashing'
Chap 9 Characteristics Costs of crashing' Shortening of completion time Benefits of crashing Effective reduction only when critical path is reduced Steps Identify regular time and costs Identify crashing time & costs Identify critical path(s) Find the minimal crashing cost on the critical path Subtract the associated time from the event on the critical path Recalculate the cost and time to complete Redefine critical paths Continue until the all the available crashing time has been used Select the min cost Note: If there are more than one critical path then an equal amount of time must be removed from each critical path.

7 Practical Considerations
Chap 9 Collecting Crash Times can be difficult defining the cost and time an activity can be reduced by adding resources can be subjective. Relationship between Costs & Time may not be linear. Some argue the relationship is curvilinear Long projects may require NPV computations Consider risks of crashing each activity, not all the same. crashing an activity can add to potential for mistakes, while others not. Impact of crashing on Morale & Motivation forcing a crash of a project can foster resentment by WP owner. overtime maybe a problem for those receiving and those not.

8 What if Cost is not the issue?
Chap 9 Reduce Project Scope Have Owner take more responsibility Outsourcing part or all of the project Brainstorm cost-saving options Review Priority Matrix

9 PERT Example Enter tasks and relationships in a Gantt chart format
Chap 9 Task Predecessor Optimistic time Pessimistic Time Most Likely time A B C A,B D C E C F E G C H D,F,G I G,F J H K I,J Enter tasks and relationships in a Gantt chart format Enter times using PERT toolbar. Determine Critical Path. What is the range of completion times for the project? Using MS Excel determine the probability of completing the project in 75 days?

10 Crashing Project Time Chap 9 Activity Normal Cost Max Crash Time Crash Cost/Day A $ $ 500 B $ $1000 C $ D $ $3000 E $ $1000 F $ $1000 G $ $3000 H $ $2000 I $ $2000 J $ $1000 K $ $1000 What activities would you recommend “crashing” to reduce the time by 5 days? If you could save $700 per day how far would you reduce the project? What would be your cost savings? Note: Use the expected times for Normal Project Time.


Download ppt "Reducing Project Duration"

Similar presentations


Ads by Google