1 Lord Tennyson Elementary School
PARENT ADVISORY COUNCIL 30 May 2016 Lord Tennyson Elementary School Seismic Upgrade Project

2 3 Option 1: Seismic Upgrade 4 Option 2: Full Replacement 5 Schedule
PRESENTATION OUTLINE 1 Catchment & Capacity 2 Existing Buildings 3 Option 1: Seismic Upgrade 4 Option 2: Full Replacement 5 Schedule 6 Comparison of Options Lord Tennyson Elementary Seismic Upgrade Project

3 4 Option 2: Full Replacement
1 Introduction Option 2 Full Replacement Site plan with modular building removed (dashed red) Allowable area: 3,709 m2 reduced from 5,131 m2 total existing area Temporary accommodation not required Lord Tennyson Elementary Seismic Upgrade Project

4 siting diagram Lord Tennyson Elementary Seismic Upgrade Project
Option 2 Full Replacement Capacity 60 kindergarten grades 1-7 Capacity to be capped at 2016 level of 452. Allowable area: 3,709 m2 (reduced from 5,146 m2 existing area) Temporary accommodation not required Lord Tennyson Elementary Seismic Upgrade Project siting diagram

5 construction phasing Lord Tennyson Elementary Seismic Upgrade Project
1 2 3 4 Lord Tennyson Elementary Seismic Upgrade Project construction phasing

6 kindergarten building considerations
existing FDK building Opportunity to retain Kindergarten Building 20 spaces in existing Full Day Kindergarten building 15 spaces in existing wood frame building Lord Tennyson Elementary Seismic Upgrade Project kindergarten building considerations

7 5 Schedule 1 Introduction
Lord Tennyson Elementary Seismic Upgrade Project

8 schedule Preliminary Project Schedule
17 months Design 21 months Construction Lord Tennyson Elementary Seismic Upgrade Project schedule

9 1 Catchment & Capacity Lord Tennyson Elementary Seismic Upgrade Project

10 catchment & capacity Lord Tennyson Elementary Seismic Upgrade Project
operating capacity: 406 enrollment: 434 utilization rate: 107% 10-year projected enrollment: growth (demand greater than capacity) Lord Tennyson Elementary Seismic Upgrade Project catchment & capacity

11 2 Existing Buildings Lord Tennyson Elementary Seismic Upgrade Project

12 existing building Lord Tennyson Elementary Seismic Upgrade Project
school building play field kindergarten kindergarten Existing building 3-storeys  primarily non-combustible brick-clad building 3 wings constructed wood-frame Kindergarten ancillary building #94B constructed 1926 full-day Kindergarten modular ancillary building constructed 2012 5,164 m2 total existing area Facility Condition Index data for all 2 buildings and site; note High FCI of 0.50 for the main building 3 storey masonry school, 5,164 m2, (only building part of seismic upgrade project) 1 storey wood frame kindergarten, 1926 1 storey modular kindergarten, 2012 Lord Tennyson Elementary Seismic Upgrade Project existing building

13 ground floor & basement plan
Lord Tennyson Elementary Seismic Upgrade Project ground floor & basement plan

14 seismic risk rating Lord Tennyson Elementary Seismic Upgrade Project
out-building moderate seismic risk 1958 block low to moderate seismic risk 1958 gym moderate seismic risk Option 1 Seismic Upgrade Seismic risk diagram showing 3 blocks as H1 highest risk. H1 = HIGHEST RISK extensive structural and non-structural seismic upgrades required no viable partial replacement option possible due to high risk condition and form of building Lord Tennyson Elementary Seismic Upgrade Project seismic risk rating

15 3 Option 1: Seismic Upgrade
Lord Tennyson Elementary Seismic Upgrade Project

16 1 Introduction SPIR review
Lord Tennyson Elementary Seismic Upgrade Project SPIR review

17 Seismic Upgrade Considerations
Deferred Maintenance Costs would remain after seismic upgrade Temporary accommodation required (off-site) Lord Tennyson Elementary Seismic Upgrade Project seismic upgrade considerations

18 6 Comparison of Options 1 Introduction
Lord Tennyson Elementary Seismic Upgrade Project

19 Option 1 Seismic Upgrade Option 2 Full Replacement Options comparison
Deferred maintenance remains; aging building systems Temporary accommodation required during construction Shorter construction duration (18 months) Drop-off and pick up along West 10th Avenue Option 2 Full Replacement Meets project objectives. Complies with current codes and standards Temporary accommodation not required during construction Longer construction duration (21 months) No on-site play field during construction Lord Tennyson Elementary Seismic Upgrade Project Options comparison