Overall Timeline (All Deployments)
Project Status – Jan. 21 to Feb. 1, 2019 Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget DG2 Training content development and UAT framework are behind and at risk Schedule Analyzing overlap between DG2 and DG3 tasks Monitoring scope and timing of Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope RTM needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget due to delayed hiring, timing of re-implementation of solutions (Continuing Education, Online Admissions Application, Budget) Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment is still underway due to the rework of key solutions. Deployment Group 2 is in the Construct Phase, focused on Functional Unit Testing of Configuration and delta changes, Data Conversion, and prep for UAT and UAT Training. Deployment Group 3 colleges completed the Initiation Phase/Gate 1 and have entered the Structure Phase/Gate 2 – Implementation Cycle, focused on self-paced Global Adoption (GDA) coursework in preparation for upcoming Business Process Fit/Gap sessions (BPFG). Contract negotiations are in progress for the new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement, while also implementing some interim fixes to the current OAA tool. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y DG2 Training content development and UAT framework are behind and at risk DG3 G DG3 Colleges all participated in the DG3 Kick Off meeting College resources have begun the GDA Courses in preparation of the BPFG Workshops. DG4 DG4 status reporting begins for the ctcLink Initiation Phase Dashboards Overall Timeline (All Deployments) LEGEND: High Medium Low
2
Top Risks Reported – as of Feb. 1, 2019
LEGEND: Critical High Moderate Low C H L M Risk Level Risk Description Mitigating Actions Submitted by (name, org/college), Deployment Group & Date Risk Owner (s) High Chart of Accounts (CoA) – User adoption and successful deployment (scheduled for July 1, 2019) is critical for Deployment Group (DG) 2 timeline. In November 2018, the FIN Team has developed and provided FirstLink Colleges (Tacoma and Spokane District) with documentation regarding the new CoA re-design.This information is instrumental in helping SMEs adopt the new Chart of Accounts and its associated business processes. FIN PM met with Spokane end of January for CoA workshops. Emmett Folk, ctcLink PM for FIN & HCM Team DG 2 Impacted, Risk Date 10/12/18 Clark – Student Financials (SF) and Finance (FIN) Coordination. Clark would like to have better coordination between the two areas and one point of contact. It is especially important for the configuration homework be coordinated to ensure all transactions are linked to FIN and GL (General Ledger). Susan Maxwell, Clark College PM All DGs Impacted, Risk Date 2/18/19 John Henry Whatley, ctcLink PM for CS and ctcLink Technical – Third Party Integration Retrofits for Products Released and Managed by ERP Support / Application Services Working with ERP Support and Application Services to determine which application interfaces that require retrofit work and the necessary steps to complete for unit and Functional Testing. Tara Keen, ctcLink Assistant Project Director DG 2 Impacted, Risk Date: 1/8/19 Tara Keen, Chandan Goel, Sandy Main Top Issues Reported – as of Feb. 1, 2019 LEGEND: High Moderate Low H L M Issue Level Issue Description Status Update Submitted by (name, org/college), Deployment Group & Date Issue Owner (s) High ctcLink Training - The development of the Training content is behind schedule due to the alignment of the training team and new approach to Training delivery. The training scope content is being defined and we are working with a vendor to help address the delay in the buildout of training content in preparations of training delivery for DG2 colleges and SBCTC. Gretchen Fulmer, ctcLink Training Manager DG 2 Impacted, Tied to Risk Date:11/9/18 and Issue Date:12/19/18 Dennis Colgan ctcLink SF (Student Financials) – Extract Logic for conversion needs to be reviewed for Cycle 3. Data services provided cross-walks to new fee codes, SF functional team have configured the new fee codes, SF conversion will run in a test instance this week. John Henry Whatley, ctcLink PM for CS Team DG 2 Impacted, Issue Date:11/12/18 Chandan Goel
3
Y ctcLink Quality Assurance Scorecard Overall Status
Moran Technology Consulting Report: January 2019 Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Governance framework continues to work as expected. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. Y Phase Scope QA concerned about implementation schedules for replacement solutions. Impacts to scope and schedule for DG 2 and DG 3 will be more defined once solutions are selected. Schedule Status DG 2 Go-Live date targeted for October 2019; overlap of schedules and resource constraints impacts all deployment groups. Focus on work streams for DG 2 while supporting DG 3 and DG 4 activities (schedule compression and complex allocation of key project resources). R Training This work stream is red, but is now trending yellow. PMO is taking appropriate actions (reallocating resources and working with a vendor on development support) to recover the schedule. Testing This work stream is yellow, but is now trending green given changes made by the PMO. DG 2 Testing work stream relies heavily on availability of functional project staff and the impact of resources with DG 2 and DG 3 overlap during specific phases. Configurations / Data Conversion DG 2 Colleges are beginning to work in Data Conversion Cycle #3. Assignment of technical lead roles were made by the PMO to improve control over the work stream. Chart of Accounts has now been configured; FLCs need to take ownership over their data management. Organizational Change Management (OCM) OCM is actively engaged in multiple areas, all focused on getting DG 2 and DG 3 colleges ready for deployment. DG 4 preliminary activities have started and remaining CPWs (Common Process Workshops) are scheduled. Project Staffing Staffing is okay at this time. Overlap of DG 2, DG 3 and DG 4 may require additional resources. Technical Environment SBCTC continues to monitor system performance; there have been no outages since early September 2018 and then early January PETA (Testing Software) was acquired and will require project and support resources. LEGEND GREEN YELLOW RED Risk Description Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost.
4
WA State Office of the Chief Information Officer (OCIO) Oversight
Overall Status Y WA State Office of the Chief Information Officer (OCIO) Oversight WA State Office of the Chief Information Officer (OCIO) Oversight OCIO Conditions to new ctcLink Investment Plan Approval Status G 1 Project must remain in-line with SBCTC and OCIO policies Complete 2 QA (Moran) to report to ctcLink executive sponsor and State CIO 3 Follow pre-determined OFM funding gates and approvals 4 Monthly status reporting 5 Continue reporting on Remediation items in Integrated Work Plan Y 6 OCIO approval of the 3 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application In Progress 7 OCIO must be notified prior to use of contingency funds N/A 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live Planned as Activities in Project Work Plans 9 Process and timeline for filling the SBCTC CIO position by 1/31/2018 Note: New ctcLink Investment Plan approved by OCIO, with above conditions, on Jan. 19, 2018.
5
Budget Status – as of Dec. 31, 2019
6
Deployment Group 2 Timeline (High Level Phases)
7
Pillar Status – Jan. 21 to Feb. 1, 2019 Human Capital Management
Campus Solutions G Accomplished this period OAA Quick Wins WebEx with SBCTC to finalize Enhancement Request Configurations for Cycle 3 Continue work on SAP Modification Continue work on SF 3rd Party Billing/Invoice Continue UAT material planning/build Review of Training materials Planned for next period Cycle 3 Data Validation with Clark Begin OAA Quick Win development and testing Define SIT Scope Continue SAP CPW modification work Continue SF remediation item (Third Party Billing) Continued Dual Processing testing Continue FIT testing SF conversion logic review Work on Local Configuration Guides Interviews for vacant CS Core Functional Analyst position Human Capital Management G Accomplished this period Continue UAT diagram/scenario updates and related content build Continued preparation and documentation updates for Conv. Cycle 3 Continued Functional Testing and updating/creating FNC Test scripts Continued review of Training content structure and materials Continued configuration build out in FNC environment Planned for next period Complete preparation and documentation updates for Conv. Cycle 3 Complete DG2 SIT Scope documentation Continue Functional Testing and updating/creating FNC Test scripts Continue review of Training content structure and materials Continue configuration build out in FNC environment Financial Services G Accomplished this period Continued UAT diagram/scenario updates and related content build Continued preparation and documentation updates for Conv Cycle 3 Continued Functional Testing and updating/creating FNC Test scripts Continued review of Training content structure and materials Continued configuration build out in FNC environment Planned for next period Complete preparation and documentation updates for Conv Cycle 3 Complete DG2 SIT Scope Documentation Continue Functional Testing and updating/creating FNC Test scripts Continue review of Training content structure and materials Continue UAT diagram/scenario updates and related content build Continue configuration build out in FNC environment Pillar Status – as of 6/8/2018
8
Workstream Status – Jan. 21 to Feb. 1, 2019
Communications G Accomplished this period ctcLink presentation at Public Information Commission, Jan. 23 DG3 Kickoff presentation development, meeting support, Jan. 28 Developed new biweekly status report incorporating DG2, DG3 timelines and DG4 dashboards Draft Executive Sponsor engagement survey Updated OCIO IT Projects Dashboard for January Reviewed/updated communications “Give and Gets” in DG3 schedule Production Issues Communications Plan update with Andy Planned for next period DG4 dashboard review meetings Begin ctcLink Glossary revision process Edit, format Training Approach document Testing Y Accomplished this period Continued completing data requests to support PETA (PeopleSoft Enterprise Test Automation) Continued to build the UAT framework in the reference center that will be used by the functional analysts to build UAT materials Functional analysts performed functional testing Resourced UAT material build project plan for campus community student financials and financial aid Complete the system integration scope definition spreadsheet that will be used to define scope Updated remediation software development lifecycle flow and distributed it to the ERP support and project team Created a UAT test plan prototype in OTM Planned for next period Continue completing data requests to support the PETA (PeopleSoft Enterprise Test Automation) implementation Obtain approval of the UAT test plan in prototype in Oracle Test Manager from the project team Continue to build the UAT framework in the reference center that will be used by the functional analysts to build UAT materials Continue functional testing Define SIT scope Create SIT test plan in OTM Build the CS-FA UAT material build section of the project plan Finalize UAT Material build section of the project plan *If status is yellow or red, describe why. Overlapping project tasks that utilize the same resources may impact testing task completion. Functional testing is currently behind schedule and may impact the start of system integration testing. UAT material build scope definition is behind schedule. Technical Y No Report out for this period due to change in key technical roles. Training R Accomplished this period Uploaded, captioned and posted GDA content into 6 pillar GDA Canvas courses. Performed QA analysis prior to delivery. Worked with Angela, Kaci, Corinne to build custom SharePoint list to manage training inventory Met with vendor regarding build and delivery of “just in time” training for Pre-UAT training for the Finance Pillar. SOW signed and onboarding forms completed for six vendor resources Onboarding two new resources Continued work to define training scope, work assignments, activity durations, and dependencies Planned for next period Work with Functional Team to continue strong push to define training scope, work assignments, activity durations, and dependencies for Pre-UAT training delivery Continue work with Angela and Kaci to build custom list in SharePoint New resource onboarding Planned, but not completed Finalize training scope – Pre- UAT Training as well as long-term training with new approach *If status is yellow or red, describe why. Quantity of needed materials as well as build time. Shift in scope definition due to GDA and Pre-UAT training. Potential of missing targeted dates in Project Schedule Training scope definition shifted to “just in time” Pre-UAT training. This will be accomplished by late January to mid - February. Organizational Change Management G Accomplished this period Worked with PMO and Communications teams to finalize tasks on college repeatable schedule Refined schedule, canvas courses, registration sheets and secured locations for all of the BPFG sessions for DG3 Held a CS End of Term CPW 2 day session Planned for next period Continue to work with CPW Facilitators and Functional Teams to determine scope for upcoming sessions Continued planning for Guided Pathways Requirements Gathering Workshops
9
Deployment Group 2 Self-Reported Status – Jan. 21 to Feb. 1, 2019
Clark College G Accomplished this period Completed 100% of Change Action Plans Presented information to Pillar 2 of guided pathways about the functionality of advising, academic progress, and MyPlanner Scheduled Validation sessions for February and working on training materials Continued work on communication plan Planned for next period Finalize Communication Plan Assign people and timelines to Change action work plan SBCTC Agency G Accomplished this period SBCTC Agency January homework completed Change Impact Analysis and Planning underway with over 10 business processes completed. FIN and Payroll UAT effort completed Executive Sponsor approved design of 2019 plan Planned for next period Complete HCM UAT Homework, Feb. 15, 2019 SBCTC Working Group charter to be revised based on 2019 plan, new estimated completion date, Feb. 15, 2019 Complete adding detail to the 2019 plan for deputy executive director review, Feb. 15, 2019 Additional ADKAR training to be scheduled by Feb. 15, 2019 Community Colleges of Spokane R Accomplished this period Chart of Accounts – kickoff meeting (OCM), and department ID mapping exercise, 80% complete. CCS budget/finance team near completion with finalizing new dept IDs and programs. Planned for next period Security Role Redesign: Waiting for Finance Matrix with Business Processes added. Due end of January. Matt Connelly to develop process/plan and schedule for completing this work. Chart of Accounts Redesign: CCS finalize new CoA structure CCS complete mapping remaining 20% of existing Dept IDs Work on Organizational Change Management Plan Confirm SBCTC tasks vs. college tasks Start building schedule/timeline with SBCTC *If status is yellow or red, describe why. Remediation Conditions in progress. SBCTC making progress, but “RED” until UATs scheduled. FY 16, 17 & 18 closed by SBCTC on 11/30/18. CCS needs to make Journal Entry adjustments for FY 16, 17 & 18 to address $18,000,000 variance. 1/31/19 requested completion date. CCS nearing completion of defining new Chart of Accounts structure/strategy. Urgent Security issues with query data access still unresolved. Pending status/update from SBCTC. Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Planned for next period Participate in Conversion Cycle 3 Data Validation as needed Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings
10
Deployment Group 4 Dashboard Reports – Feb. 7, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis Change Impact Analysis & Action Plan Development College/District As of Feb. 7, 2019 Bellevue College No data Centralia College 25% Columbia Basin College 12% Edmonds Community College 52% Highline College 35% Seattle Colleges (3) 47% Wenatchee Valley College 28% DG4 Pre-Implementation and General Timeline G
11
ctcLink Remediation Status Reports – Jan. 21 to Feb. 1, 2019
Remediation/Solution Status Due Date Campus Solutions 13 of 45 remain open The date will be driven by replacement solutions still TBD Financial Management 14 of 39 remain open Human Capital Management 9 of 25 remain open Faculty Workload Package 2 postponed due to calculations issues discovered during testing, work in progress to resolve. March 2019 DRS Redistribution Waiting on approval of formula from SBCTC and then can complete the development. Absence Management ERP Support SIT and then college UAT Feb 28, 2019 Security Audit Controls Incorporated into Security Redesign Begin Security Mapping in March Student Billing Student Billing Feb 28, 2019 / 3rd Party Invoice March 2019 Budget Planning Sub-committee began Jan 2019 to review, finalize requirements Decision for utilization of PBCS or need for RFP March 2019 Online Admissions Application OAA workgroup reviewing other OAA options. Discussions, demos with preferred college solutions. Decision for Custom Solution or need for RFP February 2019 Continuing Education RFP closed, proposals evaluated and vendor demos completed. Recommendation by work group to Governance pending. Vendor and Solution Approved February 2019 Community Colleges of Spokane R Remediation Items progress this period Closing Fiscal Years - SBCTC closed FY 16,17, 18 on 11/30/18. SBCTC opened 3 periods for us in 2019. Security role redesign – Security roles matrix final drafts for CS and HCM handed off to working group for review. Waiting on Finance matrix with business processes added. Absence management (adjunct & part-time faculty). Testing complete. UAT scheduled for week of 2/11. DRS & PEBB - Back in development. Calculations rejected by SBCTC. SBCTC working on revising calculations. Faculty Workload Improvements. In test. UAT targeting 3rd week of March. Need by March 1 for Spring contracts. Student third-party billing – Student Billing – SBCTC issues migrating into PST environment. 3rd Party billing – dev complete by 2/8. Then into project and SIT testing. *If status is yellow or red, describe why. Remediation Conditions making recent progress, but waiting for UATs to be scheduled/held. SBCTC making progress, starting to schedule UATs, but waiting for invites. Impact of delayed UATs/Training overlapping with CoA, Security redesign work, audits, and EOY tasks. Tacoma Community College G Accomplished this period Participated in OAA “Quick Wins” review Planned for next period Retrieve status documentation and details from SBCTC on remediation for review.
12
Other ctcLink Project Activities – Status as of Feb. 1, 2019
New Solution Status RFP Publish Solution Decision Continuing Education RFP was developed and approved by Governance RFP proposals due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Vendor demos scheduled for December 19, 2018 Governance approved procurement and decision of Vendor Additional approval for Implementation Approach on 2/12/2019 10/15/2018 January 2019 Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft universities and colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions on 2/12/2019 If needed, develop RFP TBD February 2019 Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution Physical Inventory (Asset Tracking) Vendor Solutions being evaluated Evaluate new PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 Delayed to evaluate new functionality within PS Accessibility Continued discussions with Appsian (formerly Grey Heller) Identify accessibility vendor to assist with testing of ctcLink Work with procurement to understand if RFP is required N/A DG2 System Integration Testing – March 2019