HOMEWORK ASSIGNMENT— MRP PROBLEMS

Similar presentations


Presentation on theme: "HOMEWORK ASSIGNMENT— MRP PROBLEMS"— Presentation transcript:

1 HOMEWORK ASSIGNMENT— MRP PROBLEMS Now try problems 1, 3, and 5 (parts a, c, and d) on pp in your textbook. Answers to these problems are on the slides that follow. Note that problem 5 is very challenging, and will be done in detail in class.

2 Note: G is equivalent to G(1) and H is equivalent to H(1)
F(2) G H J(2) D(4) L(2) J(2) A(4) D(2) J: 2 x 2 = 4 L: 1 x 2 = 2 A: 1 x 4 = 4 D: 2 x 4 = 8 J: 1 x 2 = 2 D: 1 x 2 = 2 Note: G is equivalent to G(1) and H is equivalent to H(1) Simply increase the size of the screen to read this slide. Totals: F = 2; G = 1; H = 1; J = 6; D = 10; L = 2; A = 4

3 1b. Again, increase the size of the screen. Stapler Top Assembly
Base Assembly Cover Spring Slide Assembly Base Strike Pad Rubber Pad 2 Slide Again, increase the size of the screen.

4 Need 40 End Items 3a. 3b. Total: 110 + 50 + 200 = 360
B(2) J(3) G(2) B(2) H(4) B(2) L(2) C K(3) 3a. Total LT: a. L: 2 x 40 = 80 C: 1 x 40 = 40 K: 3 x 40 = 120 –10 –15 –20 70 25 100 B: 2 x 70 = 140 B: 2 x 25 = 50 B: 2 x 100 = 200 –30 110 You may have to increase the size on the screen to at least 75% to fully see the above slide. Total: = 360 3b. The longest lead time is 7 weeks. Thus, 8 – 7 = 1, the beginning of week 1.

5 5a. Product Structure Tree
K W G(3) M(2) Z(3) H(4) N(2) L

6 5d. 5c. Note that problem 5d continues on the next three slides.
Master Schedule Weeks 1 2 3 4 5 6 7 Quantity 100 P LT = 1 wk. Beg. Inv. Gross requirements Scheduled receipts Projected on hand Net requirements Planned-order receipts Planned-order releases 5d. Note that problem 5d continues on the next three slides.

7 K LT = 2 wk. Beg. Inv. 1 2 3 4 5 6 7 Gross requirements 100 Scheduled receipts 10 30 Projected on hand Net requirements 90 70 Planned-order receipts Planned-order releases

8 G(3) LT = 1 wk. Beg. Inv. 1 2 3 4 5 6 7 Gross requirements 270 210 Scheduled receipts Projected on hand 40 Net requirements 230 Planned-order receipts 253 231 Planned-order releases

9 H(4) LT = 1 wk. Beg. Inv. 1 2 3 4 5 6 7 Gross requirements 360 280 Scheduled receipts Projected on hand 200 40 Net requirements 160 240 Planned-order receipts Planned-order releases