Download presentation
Presentation is loading. Please wait.
Published bySuryadi Kusuma Modified over 5 years ago
1
Mitre III Building McLean VA Debra Schroeder Structural Option
2
Overview Depth: Breadth: Looked at different floor systems
Investigated alternate lateral systems Performed a vibration analysis on redesigned floor systems Breadth: Cost analysis of new systems Alternate façade investigated
3
Presentation Outline Existing Conditions Depth Work Alternate Façade
-Floor systems/vibration -Lateral systems Alternate Façade Conclusions
4
Existing Building
5
Existing Building Located in McLean VA
8 Story Composite Steel Frame office building Height = 120 ft 180,000 SQ FT Façade: Mostly Precast Concrete Panels
6
Existing Building Structure
Existing Floor System: 3 Bays Outer two 42’ in length Central 43’ in length Typical Member Sizes: (not included in Moment Frame) Beams: W21X50 Girders: W18X35 W21X50 Columns: W12X65 W14X283 Foundation: Poor soil conditions on site required geopiers to be used to support structure
7
Existing Building Structure
Lateral Resisting System: Moment Frame Locations of Moment Frames
8
Proposed Changes to Structure
Floor System Investigate the effects of Shortening spans Alternate lateral systems Shear walls Braced Frames
9
Reducing Bay lengths Possible Outcomes: - Lower Costs
- Decrease amount of steel in building - Decrease weight of building
10
Reducing Bay Lengths Shortened Spans:
Outside Bays reduced to ½ original length Central Bay reduced to a 14 foot section and a 29 foot section
11
Results Members smaller than in existing building
Vibration Analysis: Design not sufficient to control vibration Options: 1. Increase Concrete deck depth 2. Use Normal Weight Concrete instead of Lightweight Concrete 3. Change Member Sizes
12
Results New Member Sizes: Cost of new structure: $2,200,000
Beams: W16X31 Girders: W18X40 Cost of new structure: $2,200,000
13
Conclusion New floor system did not produce outcomes that were expected Redesign floor system with long spans
14
Existing Bay Lengths Results
Member sizes reduced from existing structure Lighter façade Elimination of moment frame Vibration not a controlling factor Typical sizes of new members: Beams: W21X44 Girders: W18X35 Cost of new system: $2,225,000
15
Conclusion The best option for the floor system is the longer spans
Allows for unobstructed office layout Difference in the amount of material Minimal Possible increase in construction costs with shorter spans
16
Lateral Systems
17
Overview Designed shear walls and braced frames for new structure
Wanted to eliminate moment frame
18
Alternate Lateral System
Placement of Shear walls and Braced Frames Double angles used for braced frames
19
Alternate Lateral System Results
Shear Walls Cost: $304,000 Best at controlling deflections Braced Frames Cost: $145,000 Original design not adequate Changed to X braces in order to control deflection Some walls needed to be moved in order to accommodate braces
20
Conclusions Used braced frames:
Connections to shear walls would be difficult Cost of shear walls much greater than braced frames
21
Overview System Amount of materials used Pros: Cons:
Estimated cost for materials 1. Shortened spans 817 tons -Smaller, lighter members -Additional columns do not allow for unobstructed floor plan -Additional Cost for construction -Typically does not satisfy floor vibration criteria $2,200,000 2. Long spans 824 tons -Allows for unobstructed floor plan -Less costly to erect -Slightly larger members $2,225,000 3. Shear Wall 3073cy -Stiffer than braced frames -Less expensive than moment frame -Difficult to connect to diaphragms -More costly than Braced frames $304,000 4. Braced Frame 54 tons -Connections easier -Less expensive than moment frame and shear wall for material and construction -Require some rearrangement of architecture -Allows slightly larger deflections than shear wall $145,000
22
Overview Total Cost of new System: $2,370,000
Cost of existing system: $2,907,000
23
Alternate Façade
24
Alternate Façade Goals: New Material: Maintain Existing appearance
Improve upon existing system Cost Function New Material: Fiber Reinforced Concrete Panels
25
Alternate Façade Benefits of Fiber Reinforced Concrete Panels:
Does not require thick concrete cover so panels can be up to 66% lighter Can reduce structural member sizes Can reduce construction costs Increased R-Values Able to maintain existing appearance Cost increase from regular panels
26
Conclusions Floor Systems: Lateral Systems: Alternate Façade:
Keep existing long spans Lateral Systems: Braced Frames Alternate Façade: Fiber Reinforced Concrete Panels
27
Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.