1 ctcLink Project Update ctcLink Steering Committee
March 12, 2019 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director

2 agenda Item Description Duration Facilitator 1. Welcome 2 Minutes
Christy 2. Approval of Minutes 3 Minutes Choi 3. ctcLink Program Status Remediation (CCS, TCC updates) Deployment Group 2 Deployment Group 3 Deployment Group 4 Deployment Group 5 & 6 30 Minutes 4. College ctcLink Roles/Responsibilities Alignment Document Action Item: Motion Discussion & Approval (if vote is still needed) 15 Minutes Christy/Dani 5. ctcLink Training Approach Action Item: Discussion & Approval 10 Minutes Dani 6. Security Redesign Johnathan 7. Online Admissions Application Solution Update 5 Minutes Dennis 8. Propose Forming Subgroup for Steering Committee Charter/ Membership Action: Who will lead the subgroup? 9.  Action Items Review and Agenda Items for Future Meeting Janelle

3 Ctclink Minutes – Approval
February 26, 2019

4 Ctclink program status
Remediation Deployment Group 2 Deployment Group 3 Deployment Group 4 Deployment Groups 5 & 6

5 ctcLink Remediation Status Reports – Feb. 18 to March 1, 2019
Solution Status Due Date Campus Solutions 13 of 45 remain open TBD Financial Management 14 of 39 remain open Human Capital Management 9 of 25 remain open Faculty Workload Package 2 Testing. Complete DRS Redistribution Development in Progress March 2019 Absence Management College UAT Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Billing/Third-Party Billing Budget Planning Form Work Group Jan 2020 Online Admissions App Governance DG2 Continuing Education Vendor Negotiations DG3 Chart of Accounts Due Date Status FirstLink Adoption / OCM Workshops Jan. 31, 2019 Complete Establish New CoA Development Environment Jan. 31, 2019 New Departments/Programs and old department mapping from CCS Feb. 15, 2019 Configuration Complete / Functional Unit Testing Feb. 28, 2019 System Integration Testing / Parallel Close April 12, 2019 Not Started Complete College Configuration Review Sessions COA Training April 22, 2019 Configure Remaining CoA Related Updates in the CoA Development Environment April 30, 2019 User Acceptance Testing May 1, 2019 Readiness Gate / Go-No Go Decision June 1, 2019 Production Cutover July 1, 2019 Community Colleges of Spokane Y Remediation Items progress this period Security Audit Controls – See previous slide Absence Management (PT & Adjunct) UAT held Feb. 28. UAT Passed, but scope did not include a fix for calculation error for FT Faculty – Personal Holiday Faculty Workload PKG UAT held March 4-5. Delayed due to Absence Management sign-off. Accurate Reporting for DRS & PEBB Pending UAT to be scheduled. Student Billing – Pending UAT and Implementation Third-Party billing – Dev work done Feb. 8. Need status update. FY Close – See slide 9. *If status is yellow or red, describe why. Remediation Conditions making recent progress, but waiting for successful UATs and implementation. Tacoma Community College G Remediation Items progress this period See SBCTC status update for Remediation items. *If status is yellow or red, describe why.

6 Other ctcLink Project Activities – Status as of March 1, 2019
New Solution Status RFP Publish Solution Decision Continuing Education RFP was developed and approved by Governance RFP proposals due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Governance approved procurement and decision of Vendor Vendor has been contacted to begin Negotiations to Contract. 10/15/2018 Negotiations Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft universities and colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions on 2/12/2019 Work Group to Review feedback from College discussions to provide recommendation to Governance. TBD January 2019 February 2019 March 2019 Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution If needed, develop RFP Physical Inventory (Asset Tracking) Vendor Solutions being evaluated Evaluate new PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 DG3 (February 2020) Accessibility Continued discussions with Appsian (formerly Grey Heller) Identify accessibility vendor to assist with testing of ctcLink RFP is required Develop RFP DG2 (October 2019)

7 Project Status – Feb. 18 to March 1, 2019
Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget DG2 Training content development and UAT framework are behind and at risk to delivery Schedule Analyzing overlap between DG2 and DG3 tasks Monitoring scope and timing of Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope RTM needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget due to delayed hiring, timing of re-implementation of solutions (Continuing Education, Online Admissions Application, Budget) Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment continues due to the rework of key solutions. Deployment Group 2 is in the Construct Phase/Gate 3, focused on Functional Unit Testing of Configuration and delta changes, Data Conversion, and prep for SIT, UAT and UAT Training. Deployment Group 3 colleges are in the Structure Phase/Gate 2, focused on Business Process Fit/Gap sessions (BPFG). Deployment Group 4 is in the Initiation Phase/Gate 1 and is performing public status-reporting on Initiation Phase activities. Contract negotiations are in progress for the new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement, while also implementing some interim fixes to the current OAA tool. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y DG2 Training content development and UAT framework are behind and at risk to delivery DG3 G College resources have been engaged in GDA Courses and BPFG Workshops. PMs have started reporting their college status DG4 DG4 status reporting has begun with the ctcLink Initiation Phase Overall Timeline (All Deployments)

8 Deployment Group 2 Timeline (High Level Phases)
Deployment Group 2 – DG2 Deployment Group 2 Timeline (High Level Phases) G

9 Deployment Group 2 Self-Reported Status – Feb. 18 to March 1, 2019
Clark College G Accomplished this period Winter quarter meetings held – Faculty Senate Leadership Cycle 3 Data Validation. Communication Plan finalized Executive Cabinet approved a budget for to include funding for two new analyst positions. Executive Sponsor to campus Finalize staff needed for the five, week-long work sessions with SBCTC Planned for next period Continue to assign people and timelines to Change action work plan SBCTC Agency G Accomplished this period ADKAR Change Management Overviews #1 completed March 1. Assets for Data Validation. Estimated completion date Feb. 22. SBCTC Agency intranet site completed Feb. 28. Kanban board up and running on 4th floor near watercooler to track status in an agile fashion Planned for next period Conversion cycle #3 Data Validation effort continuing through March 8 – waiting for response on request for HR extension to March 16. SBCTC Agency intranet site “published,” via . Estimated March 4. Planned, but not completed Planning an “Awareness” overview for the agency – working with project team Planning additional opportunities for agency employees to view / learn more about ctcLink prior to training Community Colleges of Spokane R Accomplished this period Chart of Accounts – Budget/Fin team handed off initial draft 90% complete to SBCTC on Feb. 21. Weekly status meetings with Emmett Folk have been requested. Reviewed new Training Approach and responded with feedback and questions. Planned for next period Security Role Redesign - Waiting on documents from SBCTC. Chart of Accounts Redesign College ctcLink Roles - Needs discussion with CCS cabinet members. *If status is yellow or red, describe why. Remediation Conditions in progress. SBCTC making progress. FY 16, 17, & 18. CCS still has to reconcile all accounts Urgent Security issues with query data access Waiting on final documents for Security Role Redesign from SBCTC. Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Reviewed and submitted feedback for training approach Furnished Assets to be loaded for Asset Conversion for Cycle 3 Requested status of Chart of Accounts Planned for next period Participate in Conversion Cycle 3 Data Validation as needed Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Local SME participate in CE negotiations Local SME attend Chart of Accounts status call

10 Deployment Group 3 Timeline (High Level Phases)
Deployment Group 3 – DG3 Deployment Group 3 Timeline (High Level Phases) G

11 Deployment Group 3 Self-Reported Status – Feb. 18 to March 1, 2019
Cascadia College G Accomplished this period Pillars working on completing GDA canvas courses for BPFG attendance Completed data error extracts (quarterly and conversion #1) Attended all BPFG sessions to date International Programs completed/submitted homework assignments Planned for next period Continue completing GDA courses Continue scheduling BPFGs and complete homework Update/submit Cascadia College Roles (from SBCTC Template) Pierce College District G Accomplished this period Continued SME/attendee identification and enrollment for BPFG sessions. Continued work with Communications Team on updating communications for internal and external stakeholders. SMEs attended/participated in CS, HCM and FIN BPFG sessions in person and via WebEx. SMEs completed GDA courses. Worked on Change Action Plans. Clean-up Data Extract Error files. Planned for next period SMEs continue GDA course completion. SMEs attend/participate in BPFG sessions in person and via WebEx. Continue working on communications plan and activities. Continue working on Change Action Plans. Planned, but not completed Develop timeline for review process of applicants for project positions. Onboarding of newly hired project employees. Review Training Plan with Training Team. Olympic College G Accomplished this period Attended BPFGs in all pillars Started BPFG homework Created process to manage homework Continued data cleansing Started Faculty Change Agent Network Started Executive Assistant Change Agent Network Planned for next period Homework Data cleansing Planned, but not completed Additional Change Impact Analyses (CIAs) Peninsula College G Accomplished this period The predominant effort during this period was to complete GDA courses and attend BPFG Session either onsite or via WebEx. Continue to adjust BPFG Session attendee list and in-person/WebEx participation based on increasing understanding of session content and guidance from SBCTC. SMEs have reviewed and updated Legacy where appropriate for Conversion Cycle #1/Data Extracts. Planned for next period SMEs continue with GDA courses SMEs continue to participate in BPFG Sessions Continue to coordinate and submit homework assignments from BPFG Sessions Continue discussions around updating the Communications Plan Lower Columbia College G Accomplished this period Work with Alignment Team to complete current BPFG sessions and homework Complete onboarding critical staff through PeopleSoft fundamentals Work with staff to assemble training requirements and logistics for project team Planned for next period Continue SME participation in all GDA and BPFG sessions as needed. This includes completion of CIA work as an outcome of BPFG. Continue on campus messaging and communication about ctcLink Continue to develop forecasting tools to track staff workload and project hours.

12 Deployment Group 4 Dashboard Reports – Feb. 18 to March 1, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of March 1, 2019 Centralia College 27% Edmonds Community College 57% Highline College 40% Seattle Colleges (3) 47% Wenatchee Valley College 34% DG4 Pre-Implementation and General Timeline G

13 College INITIATION engagement schedule
This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment. Activity DG3 DG4 DG5 DG6 Begin Initiation Phase Work (Identify project manager, create project schedule, begin readiness efforts) Feb 2018 March 2018 July 2018 March 2019 Start Public Reporting (status reports, risks & issues) Dec 2018 Jan 2019 Nov 2019 Gate 1: Implementation Readiness July 2019 Oct 2019 July 2020 Implementation Phase Jan 2019 – Feb 2020 (Depends on DG2 Go-Live) Jan 2020 (Depends on DG3 Go-Live) Sept 2020 (Depends on DG4 Go-Live) Go-Live Feb 2020 Oct 2020 Feb 2021 Oct 2021 Revised 2/20/2019

14 Deployment groups & timeline

15 Ctclink quality gates & milestones
INITIATION STRUCTURE CONSTRUCT TRANSITION DEPLOY Project Planning (Checklists & Templates) Global Design Adoption (GDA) Determine Exception Solutions Production Cutover Planning Go/No Go Decision Business Process Fit/Gap (BPFG) Update BP Flows Production Environment Prep Pre-User Acceptance Testing Training Start Change Impact Analysis & Change Action Plan Update BP Flows Update CEMLIs User Acceptance Testing Production Cutover Local Configuration Update Configuration Chart of Accounts Redesign (DG2 only) End-User Training Production Validation Training Materials Analysis/Build Convert and Validate Data Build PeopleSoft Environments Security Matrix Mapping UAT Test Definition Performance Testing Milestone Sign-Off Functional Testing Security Redesign (DG2 only) UAT Materials Build Legacy System Shutdown Procedures in Place Finalize Local Configuration Guides Prepare QA Environment Identify Exceptions Organizational Change Management Assessments Begin Prepare Parallel Environment Design Extensions Cutover Mitigation Planning GO LIVE System Integration Testing Prepare or Update Test Scripts GATE 1 PEER REVIEW Production Go/No Decision Map Supplemental Systems Data Parallel Testing Lessons Learned OCM Assessment, Activities & Deliverables for Colleges & SBCTC College Project Charter Resource Plan & Budget Plan Deliverables Legacy BP Mapping Initial Supplemental Systems Analysis Change Impact Analysis 25% GDA and BPFG Participation Supplemental Systems Data Mapping Initial Config Guides Sign-Off UAT Definition Sign-Off Change Impact Analysis 50% Design Requirements Sign-Off Security Matrix Mapping Data Validation Sign-Off Change Impact Analysis 75% OCM Readiness Checklist UAT Sign-Off End-User Training Policy/Procedures Updated Cutover Plans, Legacy Shutdown Procedures Change Impact Analysis 100% College Cutover Plan Go/No Go Sign-Off Milestone Sign-Off Config Guides Sign-Off College Lessons Learned Rev

16 College ctcLink Roles/Responsibilities Alignment Document
Discussion and feedback Approval Next steps – present to WACTC

17 Training Approach Discussion and feedback Approval

18 Security Re-Design Discussion and feedback Approval

19 Online Admissions Application Solution update
Discovery update (PeopleSoft CS Customers) Next steps

20 Steering committee Charter Update
Propose forming subgroup for Steering Committee Charter/Membership Discuss membership requirements to include: College leaders as part of ctcLink Project College leader engagement post-ctcLink Project

21 Questions?