Download presentation
Presentation is loading. Please wait.
1
Industry Representative
February Program Review Team Pit Roach B2Logic to L-Edit Translator (BLT) Team *Daman Oberoi Zach Heath John Chezem Advisors Dr. Peter Osterberg Dr. Aziz Inan Industry Representative Mr. Dave Dunning, Intel 22-Jan-04 University of Portland School of Engineering
2
Overview Project Review Accomplishments Milestones March Plans
Current Project Concerns Conclusion 22-Jan-04 University of Portland School of Engineering
3
Functional Block Diagram
Project Review BLT B2Logic to L-Edit Translator Functional Block Diagram 22-Jan-04 University of Portland School of Engineering
4
Accomplishments TOP 1.0 approval Initial Unix version of BLT working
Reverse engineering of 24 Hr Clock (1998 SR Design) completed Web page updated Development of GUI for Windows BLT in progress 22-Jan-04 University of Portland School of Engineering
5
24 Hour Clock 22-Jan-04 University of Portland School of Engineering
6
Kokanee 22-Jan-04 University of Portland School of Engineering
7
Steelhead 22-Jan-04 University of Portland School of Engineering
8
Milestones Number Description Original 9/26/04 Previous 1/22/04
Present 2/22/04 1 Product Approval 10/09/03 2 Project Plan Approval 11/03/03 3 Chip Send-Off 11/26/03 4 Design Release 12/05/03 5 Theory of Operations Approval 02/11/04 6 Macromodel Operational 02/16/04 7 UNIX-Compatible Version 03/01/04 8 Graphical Interface 03/15/04 9 Prototype Release 04/08/04 10 Founder’s Day Presentation 04/13/04 11 Instruction Manual 04/18/04 12 Final Report 04/20/04 13 Post Mortem Presentation 04/26/04 22-Jan-04 University of Portland School of Engineering
9
Plans for March Continue writing instruction manual
Polish up working version of Unix BLT Begin optimizing BLT process (.bat File) Continue developing GUI (Windows only) Investigate the possibility of including user-defined components in the BLT library Update/Maintain website 22-Jan-04 University of Portland School of Engineering
10
Current Project Concerns
Faulty CMOS chips Making a complete, thorough, and concise manual in a timely manner BLT code may need changes for GUI to work correctly 22-Jan-04 University of Portland School of Engineering
11
Conclusion Project Review Accomplishments Milestones February Plans
Current Project Concerns 22-Jan-04 University of Portland School of Engineering
12
Questions? Check out our website:
22-Jan-04 University of Portland School of Engineering
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.