WORK PROGRESS OF KERALA TOWNS UPTO JANUARY 2007
2
7 Towns Scheme Sanctioned on 20 th Nov 2002
3
Construction of LT Lines, 11 kV Lines, 11 kV-UG Cable & 33 kV Lines
4
Reconductoring of LT Lines, 11 kV Lines & 66 kV Lines
5
Installation of DTs, AB Switches & 9 KVAR LT Capacitors
6
New 66 kV, 33 kV Substations
7
Installation of DT, Feeder & Border Meters
8
Renovation & Modernization of DTs & Substations
9
Computerised billing of sections & Computerised data logging at SS
10
Meter Calibration & Consumer Indexing
11
Funds Position Funds Position
12
26 Towns Sanctioned on 20 th September 2004
13
Construction of 11 kV Lines, 11 kV-UG Cable & Reconductoring of 11 kV Lines
14
Installation of DTs, AB Switches & 9 kVAR LT Capacitors
15
Renovation & Modernization of DTs & Substations
16
Installation of DT, Feeder & Border Meters
17
Computerised billing of sections, Computerised data logging at S/S & Call Centre
18
Consumer Indexing
19
Funds Position
20
13 Towns Sanctioned on 23rd March 2005
21
Construction of 11kV Lines, 11kV-UG Cable & Reconductoring of 11kV Lines
22
Installation of DTs, AB Switches & 9kVAR LT Capacitors
23
Renovation & Modernization of DTs & Substations
24
Installation of DT, Feeder & Border Meters
25
Computerised billing of sections, Computerised data logging at SS & Call Centre
26
Consumer Indexing
27
Funds Position
28