Bus. Hwy. 13 and Hawthorne Blvd. roundabout project March 28, 2019

Similar presentations


Presentation on theme: "Bus. Hwy. 13 and Hawthorne Blvd. roundabout project March 28, 2019"— Presentation transcript:

1 Bus. Hwy. 13 and Hawthorne Blvd. roundabout project March 28, 2019

2 Area Map Project Hawthorne Blvd.

3 Bus. Hwy 13 / Hawthorne Blvd.
Project Location Bus. Hwy 13 / Hawthorne Blvd. Hawthorne Blvd.

4 Estimated Future Traffic Volumes
Why Improvements? 13 (28) 9 (33) 17 (62) 7 (40) 4 (19) 6 (3) 364 (284) 60 (10) 23 (32) 4 (32) 130 (359) 14 (45) A recently completed traffic study found that existing delays on westbound Hawthorne are high during peak periods. Development / redevelopment in the area will soon make those delays much worse. The City thought it would be prudent to proactively make improvements before operations and safety become a significant problem. Hawthorne Blvd. Estimated Future Traffic Volumes 53 (140) 9 (33) 97 (156) 7 (40) 4 (19) 6 (3) 428 (314) 60 (10) 63 (94) 4 (32) 179 (412) 60 (211) Hawthorne Blvd.

5 Signal vs. Roundabout Roundabouts offer better operations since drivers only yield and are not required to stop. Signals require drivers to stop all the time, which increases delays and emissions. Roundabouts have been shown to reduce severe/fatal crashes dramatically compared to signals – drivers are forced to slow down through the intersection and less fixed objects to run into. Roundabout is primarily a one time investment, traffic signals have ongoing operating costs

6 Construction Overview
Start Construction April 2019 1st Traffic Shift April 2019 2nd Traffic Shift June 2019 3rd Traffic Shift July 2019 Anticipated Completion August (New Roundabout Opens!!) Major Construction Phases Four (4) Closures/Detours Hawthorne Blvd.…… …DETOUR via Cooper NW 21 Rd. at Hawthorne Blvd……… ….DETOUR via Temp. Access off Bus. Hwy 13 Large Truck Detour in final phase of construction………………………… DETOUR via Cooper Bus. Hwy 13 Remains Open to passenger traffic throughout construction

7 Construction Phases 1 and 2

8 Construction Phases 3 and 4

9 Detours