Building for Learning Project Photo Progress Report December 2009 Project commencement 21 st September 2009
2
December new on-site substation for power required.
3
December – carpet, ceilings and windows in modernised Administration area
4
December – steel, bond deck arrives for 1 st Floor
5
December – underground cable boring and concrete footings for stairways and elevator
6
December – Company Directors tour with Graeme Connelly – girls were happy, boys were serious. L-R. Chairperson Kerryn Dwyer-Parish, Director Jan Wyatt-Brown, Director Alison Mitchell, Corporate Services Manager Pauline Butler, Builder Graeme Connelly, Director Rod Jones, Director David Ryan.
7
December – bracing underneath bond deck and steel ready for concrete floor above
8
Final preparations and then concrete pour starting 6am, 22 nd December – 150 tonne concrete
9
22 nd December – 11 truck loads of concrete