WP 2 Update Fire Detection and Extinguishing FCC Collaboration
Workshop on fire protection for physics research facilities 20-21 June 2017 European Spallation Source WP 2 Update Fire Detection and Extinguishing FCC Collaboration Art Arnalich – HSE-SEE-XP A. Arnalich HSE-SEE-XP EDMS no:
3
20.06.2017 - A. Arnalich HSE-SEE-XP
WP2 break down WP2.1 Intervention forces, coverage, times and existing procedures Overview about regional intervention forces, their alarm procedures, coverage in terms of reachability of objects within the legal time frames and, if already in place, intervention procedures on particle physics objects. WP2.2 Draft Intervention procedures Based on WP 2.1 draft of intervention procedures for incident response taking into account tactical site information such as access, maps, known hazards, supervised areas etc. pp. WP2.3 Extinguishing systems Proposal of compensatory measures in terms of fire suppression where WP2.1 and WP2.2 show, that no legal, or efficient intervention, in due time is possible. WP2.4 Signal failure analysis Analysis to be carried out by ESS to verify the suitability of fiber optical connections for safety and safety-related systems. CERN's IT studied already the attenuation of fibers due to ionizing radiation, a direct contact can be provided. WP2.5 Draft report and final discussions Discussion and interpretation of the current results, wrap-up for final report on the deliverables ESS-DE-1 and ESS-PS-1 A. Arnalich HSE-SEE-XP EDMS no:
4
WP2 action list (agreed 08/11/2016 at FCC Workshop Lund)
STEP ACTION DUE INVOLVED 1 Preliminary documentation report for WP2.1 and WP2.3 31/12/2016 FNAL, ESS/RYSD, MAXIV, DESY DONE 2 Draft version of WP2.2 Draft Intervention Procedures DONE HALTED CERN 3 Review of Draft version WP2.2 Draft Intervention Procedures FNAL, ESS/RYSD, MAXIV, DESY DONE HALTED 4 Signal Failure Analysis ESS DONE 5 Development, meeting to draft WP2.5 Draft report and final discussions FNAL, ESS/RYSD, MAXIV, DESY 6 Final version of WP2.5 Draft report and final discussions CERN A. Arnalich HSE-SEE-XP EDMS no:
5
20.06.2017 - A. Arnalich HSE-SEE-XP
WP2 update FCC project still working on baseline Single tunnel cross section Fire Smoke extraction A. Arnalich HSE-SEE-XP EDMS no:
6
20.06.2017 - A. Arnalich HSE-SEE-XP
WP2 update Current LHC fire response/detection not enough Smoke extraction ➞ higher resolution fire detection Delayed response ➞ additional fire response (robot, sprinklers) A. Arnalich HSE-SEE-XP EDMS no:
7
20.06.2017 - A. Arnalich HSE-SEE-XP
WP2 update Performance Based-Design adopted for fire safety ➞ performance criteria ➞ fire safety design reference ➞ assessment tools (FRPAM) A. Arnalich HSE-SEE-XP EDMS no: