1 ctcLink Project Update ctcLink Steering Committee
April 9, 2019 Choi Halladay - District Vice President for Administrative Services Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director

2 Agenda Item Description Duration Facilitator 1. Welcome 1 Minute
1.  Welcome 1 Minute Christy 2.  Approval of Minutes 2 Minutes Choi 3.  cELC Update (Roles/Alignment Document) 10 Minutes 4.  ctcLink Program Status Remediation (CCS, TCC Updates) Deployment Group 2 Deployment Group 3 Deployment Group 4 PM Summit - May 6-7; DG5 & DG6 focus – May 8 20 Minutes 5.  Deployment Group Alignment Decision for Shoreline CC 6.  Online Admissions Application Solution Update Dennis 7.  Continuing Education RFP Update Abraham   8.  Subgroup Update for Steering Committee Charter/Membership 5 Minutes Subgroup Members 9.  Action Items Review and Agenda Items for Future Meeting - Executive Sponsor Next Steps Janelle/Reuth 10.  Meeting Closure

3 Ctclink Minutes – Approval
March 12, 2019

4 cELC Update College Roles & Alignment Document

5 Ctclink program status
Remediation Deployment Group 2 Deployment Group 3 Deployment Group 4

6 ctcLink Remediation Status Reports – March 18 to 29, 2019
Solution Status Due Date Campus Solutions 13 of 45 remain open DG3 Financial Management 14 of 39 remain open DG2 Human Capital Management 9 of 25 remain open Faculty Workload Package 2 Testing. Complete DRS Redistribution Development in Progress April 2019 Absence Management College UAT Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Billing/-Party Billing April 2019 Budget Planning Form Work Group Jan 2020 Online Admissions App Governance Continuing Education Vendor Negotiations Chart of Accounts Due Date Status FirstLink Adoption / OCM Workshops Jan. 31, 2019 Complete Establish New CoA Development Environment Jan. 31, 2019 New Departments/Programs and old department mapping from CCS Feb. 15, 2019 Configuration Complete / Functional Unit Testing Feb. 28, 2019 System Integration Testing / Parallel Close April 12, 2019 In Progress Complete College Configuration Review Sessions Not Started COA Training April 22, 2019 Configure Remaining CoA Related Updates in the CoA Development Environment April 30, 2019 User Acceptance Testing May 1, 2019 Readiness Gate / Go-No Go Decision June 1, 2019 Production Cutover July 1, 2019 Community Colleges of Spokane R Remediation Items progress this period Security Audit Controls – Urgent Security Issues not addressed; request sent 12/13/ security issues UATs are in process of being scheduled. Accurate Reporting for DRS & PEBB - Ready now for System Integration Testing. New SBCTC ticket created to address DRS redistribution Student Billing – Code overwritten in test environment. Now back in QA process. Pending UAT Third Party billing – Failing System Integration Testing. UAT TBD. FY Close – see previous slides. Book to Bank - Cash Reconciliation - Focus now is on reconciling the 3 cash accounts making up our 18-million-dollar variance (same accounts for TCC). SBCTC Project team working on providing reports/workflow of behind the scenes ctcLink processing of the transactions going into these accounts. CCS request to be engaged on the strategy/tools planning for reconciling cash moving forward. *If status is yellow or red, describe why. Absence Management (PT & Adjunct) completed!! All remaining remediation conditions pending test validation and UATs. 39 open remediation tickets. Tacoma Community College G Accomplished this period See SBCTC status update for Remediation items, tickets, and worklist. Planned for next period Receive detail for open and closed remediation tickets from Christy and team. TCC SMEs participate in Budget Planning Tool workgroup.

7 Project Status – March 18 to 29, 2019
Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget DG2 Training content development and UAT framework are behind and mitigations in place to reduce risk to delivery Schedule Analyzing overlap between DG2 and DG3 tasks Monitoring scope and timing of Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope Requirements Traceability Matrix (RTM) needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget New Technology Plan approved as well as Stage Gate #3 for OFM/OCIO Technology Pool funding Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment continues due to the rework of key solutions. Each Deployment Group (DG) is now engaged in the project at some level. DG2 is in the Construct Phase and the ctcLink project team is performing System Integration Testing (SIT). DG 3 is in the Structure Phase, focused on Business Process Fit/Gap sessions (BPFG) through May. DG4 is in the Initiation Phase, with most colleges nearing the halfway mark on deliverables. DG5 is also in the Initiation Phase. Project managers are learning the public status reporting process. DG6 will soon begin those activities. Contract negotiations are in progress for the new Continuing Education solution and the Online Admissions Application (OAA) work group is actively pursuing an OAA replacement.  The Budget Planning work group is reconvening to start the review and finalization of business and technical requirements. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y Significant progress in the build of Training content UAT framework and content being developed DG3 G College resources have been engaged in BPFG Workshops Conversion cycles have began DG4 College teams working on Initiation Phase activities Overall Timeline (All Deployments)

8 UAT SPRINTS TRAINING CONTENT DEVELOPMENT
Sprint 1 Training Materials, 95% complete - March 29, 2019 117 Quick Reference Guides created/updated 3 Overview videos created for FIN 49 PowerPoints created 15 Instructor-Led Training scripts created Sprint 1 Canvas shell complete Sprint 1 95% Apr 29 - May 10 71 days Sprint 2 40% May 20 - Jun 3 15 days Sprint 3 35% Jun 11 - Jun 24 14 days Sprint 4 10% Jul 2 - Jul 15 14 days Sprint 5 10% Jul 29 - Aug 9 12 days Sprint 6 10% Aug 19 - Aug 30 12 days 2019 Mar Apr May Jun Jul Aug 2019 2019 Today What is a Sprint? Each Sprint may be considered a “project” (no more than one month in length during which a completed, useable and/or releasable deliverable increment is created. A Sprint includes: goal of what is to be built, design and flexible plan to guide building, the work itself, the deliverable/product A new Sprint starts immediately after the conclusion of the previous. Sprints limit risk to one calendar month, enable predictability and ensure inspection/adaptation of progress toward specific goals in short time increments.

9 Deployment Group 2 Self-Reported Status – March 18 to 29, 2019
Clark College G Accomplished this period Full week of course catalog cleanup. Met with Bill, security role contractor and provided information for security roles SBCTC provided a demonstration of OSECE so we know what we are planning for. Business processes continue to be documented Planned for next period Continue to assign people and timelines to Change Action work plan UAT testers are being assigned Create an group for all PeopleSoft users SBCTC Agency Y Accomplished this period “Awareness” Overview for the agency – planning with project team completed 3/20 ADKAR Change Management Overview #3 and #4 completed 3/19, and 3/25 HCM CIA/CAP sessions completed for FMLA, Work-shifts, Reasonable Accommodations, and Establish Salary via Formula 3/27 Planned for next period Conduct and attend “Awareness” Overview for the agency scheduled for 4/3 9-10:30am in Cascade A/B Planned, but not completed Planning additional opportunities for agency employees to view / learn more about ctcLink prior to training *If status is yellow or red, describe why. SBCTC has completed cycle #4 homework and ready for Data Validation cycle #4 (DV4). We have some issues, but under control so far. Community Colleges of Spokane R Accomplished this period Chart of Accounts Redesign Execution meeting CCS Budget/Finance to begin reviewing/validating mapping spreadsheets starting April 5. Recommunicated CCS critical/urgent issues to SBCTC leadership. Lack of clear status from issues we communicated Dec. 13 and 28. FY Close – CCS continues to adjust journal entries. Planned for next period Security Role Redesign Waiting on support/process documents from SBCTC before we can plan and execute mapping exercise and validation. 4/5/19 - Budget/finance to start reviewing/adjusting mapping spreadsheets Need to build/confirm list of all areas impacted by new department IDs and programs. *If status is yellow or red, describe why. FY 16, 17, & 18. CCS is nearing completion of reconciling journal entry adjustments. CCS now targeting 4/15/19. Not able to start cash reconciliation until tools, process documentation provided by SBCTC. Urgent Security issues with sensitive financial and employee query data access available across all FLCs. Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Participated Chart of Accounts meetings. Received Chart of Accounts adoption schedule. Planned for next period Participate in Conversion Cycle Data Validation as needed Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Local SME participate in CE negotiations

10 Deployment Group 3 Self-Reported Status – March 18 to 29, 2019
Cascadia College G Accomplished this period Pillars finalizing all GDA canvas courses for BPFG attendance Attended all BPFG sessions to date Completed all Pillar BPFG homework assignments due this period Submitted Cascadia College Roles to SBCTC (minus Go-Live Team) Planned for next period Preparing for Data Validation Cycle #1 Continue scheduling attendance to BPFGs and complete homework Olympic College Y Accomplished this period Attended BPFGs in all pillars Submitted BPFG Homework Continued Data Cleansing Created Faculty Change Agent Network Contracts Planned for next period Homework Data Cleansing Attend BPFGs Hire third Analyst Planned, but not completed Additional Change impact Assessment Workshops Peninsula College G Accomplished this period Continued to participate in BPFG sessions. Submitted BPFG homework assignments per BPFG session requirements. Participated in conversation with Peninsula College Steering Committee, DG3 PMs and SB staff regarding a BPFG schedule change option presented by SB. PC voted unanimously to stay with the current schedule. Planned for next period SMEs continue to participate in BPFG Sessions. Continue to coordinate and submit BPFG homework assignments Continue conversation regarding Go Live date. Pierce College District G Accomplished this period SMEs attended/participated in BPFG sessions. Completed all homework to date. SMEs completed GDA courses (all Pillars). Internal communications – intranet site is live and will continue to update as needed. Planned for next period SMEs continue GDA course completion. SMEs attend/participate in BPFG sessions SMEs complete homework assignments. Planned, but not completed Complete additional Change Impact Analyses. Review applicants for project positions. Onboarding of newly hired project employees. Review and update internal Training Plan with college Training Team. Lower Columbia College G Accomplished this period Work with Alignment Team to complete current BPFG sessions and homework Complete onboarding critical staff through PS fundamentals Work with staff to assemble training requirements and logistics for project team Hosted Several BPFG sessions on campus. Planned for next period Continue SME participation in all GDA and BPFG sessions as needed. This includes completion of Change Impact Assessments work as an outcome of BPFG. Continue on campus messaging and communication about ctcLink Continue to develop forecasting tools to track staff workload and project hours.

11 Deployment Group 4 Dashboard Reports – March 18 to 29, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of March 29, 2019 Centralia College 34% Edmonds Community College 57% Highline College 47% Seattle Colleges (3) Wenatchee Valley College 44% DG4 Pre-Implementation and General Timeline G

12 Spring 2019 PM summit Agenda Prep Dates
In collaboration with college from each DG Dates May 6 & 7 – All colleges May 8 – DG5 and DG6 focus on initiation activities to get ready for implementation (DG4 participation optional) Location: Wenatchee Valley College

13 Deployment group alignment
Deployment Changes: Bellevue: DG4 to DG5 Columbia Basin: DG4 to DG6 Shoreline: DG5 to DG6 requested

14 INITIATION schedule highlights
This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment. Activity DG3 DG4 DG5 DG6 Begin Initiation Phase Work (Identify project manager, create project schedule, begin readiness efforts) Feb 2018 March 2018 July 2018 March 2019 Start Public Reporting (status reports, risks & issues) Dec 2018 Jan 2019 Nov 2019 Gate 1: Implementation Readiness July 2019 Oct 2019 July 2020 Implementation Phase Jan 2019 – Feb 2020 (Depends on DG2 Go-Live) Jan 2020 (Depends on DG3 Go-Live) Sept 2020 (Depends on DG4 Go-Live) Go-Live Feb 2020 Oct 2020 Feb 2021 Oct 2021 The message to college presidents meeting (WACTC) in February is that ALL COLLEGES are to be engaged in the project at some level. The time is now for all colleges to be engaged in ctcLink. Revised 2/20/2019

15 Online Admissions (OAA) Update
OAA Quick Wins (current improvements to application in production for FLCs) Final interviews with colleges and universities OAA Work Group feedback OAA Work Group recommendation

16 Continuing Education Update
Negotiations update Questions Global approach for consistent student experience Pricing aligned based on college size and enrollment Integration for ctcLink CampusCE baseline

17 Steering committee Charter
Steering Committee Charter Review Subgroup update on progress Recommendations for addressing colleges post- production that may no longer have an Executive Sponsor: which title is required for nomination to serve on ctcLink Steering Committee?

18 Other Discussion Items
Executive Sponsor Next Steps

19 Questions?