BI-19 Process Improvement

Similar presentations


Presentation on theme: "BI-19 Process Improvement"— Presentation transcript:

1 BI-19 Process Improvement
Sea Water Injection Department

2 Project Charter Problem Statement : Cost Of Poor Quality :
During period, 37% (12 out of 32) BI-19 projects were not completed within estimated time and budget ± 10%. Cost Of Poor Quality : Reduced ROI due to long cycle time Budget under or overrun Supplement budget request after the fact Project Objective : Complete 100% BI-19 Projects within projected time and budget. Defect Definition : Any BI-19 Project which exceeded ER time (2 years) or ER budget variance by ± 10% Critical To Quality ( CTQ) : Project cycle time should be 2 years or less. Actual cost should be within budget ± 10% Goal: Defect Rate: 0 No time extension or Supplement Budget request after the fact

3 Engineering Package Development
High Level Process Map MCC / ER Closing 3 – 4 Months (Finish) ER Approval (Start) Material Procurement 10 – 12 Months My first point is to give background and history of the Spare Parts Stocking Guidelines: In 1992, a study team was formed to evaluate solutions to control spare parts growth. Click As a result, the Spare Parts Stocking Guidelines were implemented in 1993. In 1999 the Equipment Templates that provide the initial stocking levels were enhanced based on consumption history to further control spare parts growth. Click hyperlink In 2005 further enhancements were implemented on equipment templates. The intention of these updates was to optimize spares while retaining Service levels to customer organizations. In 2007, we started our initiative to conduct a comprehensive review on the SP Stocking Guidelines. Engineering Package Development 8 -10 months Execution Period 6 – 8 Months Total Period = 27 – 34 Months 3

4 Current Process Map BI-19 Planning (Execution Phase) Yes Is there
comments ? In House Design ? No Engineering Prepare Detail Design Initiate PDR 30 % Design Review Yes 6-8 months Yes No Is there comments ? Is there comments ? No Engg Package No 90 % Design Review 60 % Design Review Yes Accepted Yes Ops Issue Maintenance Order Planner request Material / DC Procurement Material Received Material Staged No SFC / PO Procurement Wrong or Additional Review Material Spec. Yes Const. Phase No Award contract Re-order Material

5 Current Process Map Start Construction Final Closing
BI-19 Construction (Execution phase) SFC / PO Procurement Approve SFC / SO Mobilize Contractor Start Construction Submit Spare Parts Data Packages Close All Yes Items In MCC Final Closing MCC Signature Commissioning Submit all Required As Built Packages Submit NMR and OM

6 Cancelled Under budget Over budget
Completed Projects Cancelled Under budget Over budget

7 Quality tools Flow chart Cause & effect diagram Pie diagram