Presentation is loading. Please wait.

Presentation is loading. Please wait.

LCLS Overview John N. Galayda, SLAC April 23, 2002

Similar presentations


Presentation on theme: "LCLS Overview John N. Galayda, SLAC April 23, 2002"— Presentation transcript:

1 LCLS Overview John N. Galayda, SLAC April 23, 2002
Project Description Project Management The Next Two Years LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

2 Project Description Prime performance parameters
0.8 – 8 keV SASE Free Electron Laser Electron beam 4.5 – GeV, from SLAC Linac Peak power in SASE bandwidth 8 GW Peak brightness 1033 photons/(mm2 mr2 0.1%BW) Pulse duration  230 femtoseconds Pulse repetition rate 120 Hz LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

3 LINAC COHERENT LIGHT SOURCE
Sand Hill Rd LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

4 Project Description Electron Beam Handling Systems 1.2.1 Injector
Photocathode gun and drive laser 150 MeV linac Located in Sector 20 off-axis injector spur LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

5 Project Description 1.2.2 Linac SLAC linac tunnel X-band RF
Bunch Compressor 1, 250 MeV Superconducting wiggler Bunch Compressor 2, 4.5 GeV Reconfiguration of transport to Final Focus Test Beam Area 7 MeV rf gun Linac-X L =0.6 m new Linac-3 L =550 m Linac-0 L =6 m Linac-1 L =9 m Linac-2 L =330 m 14.35 GeV 21-1b 21-1d X 21-3b 24-6d 25-1a 30-8c undulator L =120 m ...existing linac BC-1 L =6 m DL-1 L =12 m BC-2 L =22 m DL-2 L =66 m 150 MeV 250 MeV 4.54 GeV SLAC linac tunnel LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

6 Project Description 1.2.3 Undulator Systems
121 meter undulator channel, housed in extended FFTB Diagnostics for x-ray beam and electron beam 3420 187 421 UNDULATOR 11055 mm Horizontal Steering Coil Beam Position Monitor Quadrupoles Vertical Steering Coil X-Ray Diagnostics LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

7 Project Description 1.3 Photon Beam Handling Systems
1.3.1 X-ray Transport, Optics and Diagnostics Front end systems – attenuators, shutters, primary diagnostics Optics – the prerequisites for LCLS experiments 1.3.2 X-ray endstation systems Hutches, Personnel Protection Computer facilities for experiments Laser for pump/probe experiments Detectors matched to LCLS requirements Essential Infrastructure for the LCLS Experimental Program LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

8 Project Description 1.4 Conventional Facilities
Final Focus Test Beam Extension Hall A Hall B LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

9 LCLS R&D Collaboration
FEL Theory, FEL Experiments, Accelerator R&D, Gun Development, Undulator R&D LLNL UCLA LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

10 LCLS R&D, Preconceptual Design Organization
LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

11 Conceptual Design Institutional Responsibilities
LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

12 LCLS Conceptual Design Individual Responsibilities
LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

13 LCLS PED Organization LCLS DOE Review, April 23, 2002
John N. Galayda, SLAC

14 Advisory Bodies, through the conceptual design phase
LCLS Scientific Advisory Committee Phil Bucksbaum, Univ. Michigan Roger Falcone, UC Berkeley, Chairman Rick Freeman, UC Davis Andreas Freund, ESRF Janos Hajdu, Uppsala Jerry Hastings, NSLS (SLAC-SSRL) Richard Lee, LLNL Ingolf Lindau, SSRL / Lund Univ. Gerd Materlik, RAL Simon Mochrie, Yale Keith Nelson, MIT Francesco Sette, ESRF Sunni Sinha, UCSD Z. X. Shen, Stanford Gopal Shenoy, ANL-APS Brian Stephenson, ANL Joachim Stohr, SSRL LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

15 Advisory Bodies, through the conceptual design phase
LCLS Technical Advisory Committee Bill Colson, Naval Postgraduate School (NPS), Chairman Jerry Hastings, (SLAC) Pat O'Shea, University of Maryland (UMD) Jörg Rossbach, Deutsches Electronen-Synchrotron (DESY) Ron Ruth, Stanford Linear Accelerator Center (SLAC) Ross Schlueter, Lawrence Berkeley National Laboratory (LBNL) LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

16 Advisory Bodies for PED Phase
LCLS Machine Advisory Committee Reporting to Laboratory Director Membership broadened to span the project scope Accelerator physics X-ray systems, Engineering project management LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

17 Budget – $FY2002 Total Estimated Cost $196.5M
Project Engineering and Design (direct) $ M Construction(direct) $106.2M Overhead $ 23.1M Contingency $ 37.5M LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

18 Budget – FY2005-2007 Construction
Total Project Cost $ 233.0M Total Estimated Cost $ 215.9M ETC $ 174.6M Contingency $ M Other Project Costs $ M R&D (FY1999-FY2002) $ 5.9M Startup $11.2M LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

19 Schedule Three-year construction schedule, FY2005 start
Project Start October Injector Beam to Linac June Linac Beam to BC April Project Completion September 2007 LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

20 Risk Assessment - Technical
Accelerator SASE theory validated by experiments Computation/simulation tools highly developed, agree with experiments Slice emittance at undulator is a key measure of technical risk Project goal 1.2 mm-mrad normalized emittance at the undulator entrance Saturation at 8 keV achieved for 1.5 mm-mrad, with 122 meter undulator channel Saturation at 8 keV achieved for 1.9 mm-mrad with 150 meter undulator channel Ample safety factor for saturation at 0.8 keV Undulator Prototype in hand Peak field goal exceeded Chamber prototyping LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

21 Risk Assessment - Technical
X-ray Optics Power densities in Hall A limit choices to low-Z materials Power densities in Hall B are tractable X-ray Endstation Systems Routine technical risks LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

22 Risk Assessment - Schedule
Critical path for injector commissioning Gun laser testing a PED activity in FY2004 Critical path for undulator procurement 4 months for commissioning FEL Consider expedited procurement of undulator raw materials Beneficial Occupancy of Hall B Tight installation schedule if construction starts in FY06 120 Hz array detectors Rapid exploitation of the LCLS, post-project LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

23 The Next Two Years Now – prerequisites for CD-1
Conceptual Design Report Baseline Range Estimate for Total Project Cost Preliminary Hazards Analysis Report Draft Acquisition Execution Plan NEPA strategy Draft Project Execution Plan Draft Memorandum of Agreement for Partner Labs Project Management Plan LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

24 The Next Two Years March 2003 - Critical Decision 2
Target January 2003 for EIR Definition of Performance Baseline Layout Drawings Design Handbook containing subsystem and component specifications Refined Cost Estimate Identification of long-lead procurement needs prior to CD-2 Baseline Change Control External Independent Review (EIR) Independent Cost Estimate (ICE) LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

25 Firm basis for cost and risk assessment
Gun Design Undulator Prototype Optics Fabrication Techniques Chicane for advanced accelerator R&D with ultrashort electron bunches Cost-effective magnet fabrication techniques developed for NLC LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC

26 LCLS is an Extraordinary Scientific Opportunity
LCLS ready for CD-1 Approval On track for CD-2, March 2003 Outstanding work, cooperation in the collaboration Specific areas of risk identified and targeted for resolution Ready to go LCLS DOE Review, April 23, 2002 John N. Galayda, SLAC


Download ppt "LCLS Overview John N. Galayda, SLAC April 23, 2002"

Similar presentations


Ads by Google