Energy and the New Reality, Volume 1: Energy Efficiency and the Demand for Energy Services Chapter 9: Community-Integrated Energy Systems L. D. Danny Harvey harvey@geog.utoronto.ca harvey@geog.utoronto.ca This material is intended for use in lectures, presentations and as handouts to students, and is provided in Powerpoint format so as to allow customization for the individual needs of course instructors. Permission of the author and publisher is required for any other usage. Please see www.earthscan.co.uk for contact details. www.earthscan.co.uk Publisher: Earthscan, UK Homepage: www.earthscan.co.uk/?tabid=101807www.earthscan.co.uk/?tabid=101807
2
Community-Integrated Energy Systems consist of one or more of: A network of insulated underground pipes to distribute heat from various heat sources to where it is needed A network of insulated underground pipes to distribute cold water from a central chilling facility or natural source of cold water to where it is needed Cogeneration or a central heating plant Trigeneration or a central cooling plant Seasonal underground storage of heat or coldness
3
Figure 9.1 Pre-insulated district heating pipes in Copenhagen Source: www.logstor.comwww.logstor.com
4
The worlds largest district heating systems are in: St Petersburg 237 PJ/yr Moscow 150 PJ/yr Prague 54 PJ/yr Warsaw 38 PJ/yr Bucharest 37 PJ/yr Seoul 36 PJ/yr Berlin 33 PJ/yr Copenhagen 30 PJ/yr New York 28 PJ/yr Stockholm 27 PJ/yr
5
Figure 9.2 Percent of total space heating requirements met by district heating Source: Maker and Penny (1999, Heating Communities with Renewable Fuels: The Municipal Guide to Biomass District Energy, Natural Resources Canada and USA Department of Energy, www.nrcan.gc.ca)
6
District Heating Highly worthwhile if waste heat from electricity generation can be captured and used (cogeneration) This will reduce GHG emissions only if fossil fuel electricity production elsewhere is displaced, or if biomass is used If the absence of cogeneration, district heating can save energy through the more efficient operation of central boilers than of individual boilers (usually at part load) in individual buildings, although this advantage will not exist if new, condensing boilers are used in individual buildings
7
Other sources (besides electricity production) for heat for district heating are Sewage water (16 o C in February in Tokyo) Steam from incineration plants powering heat pumps to extract heat from the exhaust of the incineration plants (done in Sweden) Low-grade geothermal heat in the return branch of a geothermal heating system, upgraded with heat pumps
8
Heat can be distributed either as steam or as hot water. Hot water provides a number of efficiency advantages due to its lower temperature than steam: Less heat loss to the surroundings Less sacrificed electricity production Lower temperature heat sources can be used (in the absence of a heat pump, the heat source has to be warmer than the temperature at which heat is distributed) The lower the temperature at which heat is distributed, the better from an efficiency point of view
9
Figure 9.3 Variation in electricity generation efficiency, overall efficiency and electricity-to-useful heat ratio in a gas combined- cycle system as the temperature of the heat supplied to the district heating system varies. Source: Spurr and Larsson (1996)
10
Strategies for reducing the required supply temperature: Upgrade building thermal envelopes so that radiators do not need to be as hot as otherwise while still providing sufficient heat, and (in new developments) use radiant floor heating (which reduces the required temperature to 30 o C or so) Use larger and more effective heat exchangers between the district heating hot water flow and the building hot water flow, so that there is less of a temperature drop between the two Increase the flow rate and/or use a peaking plant to boost the supply temperature during the coldest month
11
Upgrading old District Heating Systems In many countries of Eastern Europe and the Former Soviet Union Distribution systems are steam-based and lose up to 30 per cent of the heat that they carry The systems are also over-sized and so tend to operate at partial capacity (which lower efficiency) The buildings that they serve often lack thermostatic controls and are poorly insulated Thus, in these countries the large potential energy savings is not in the expansion of district heating with cogeneration, but in the improvement of the efficiency of the existing system and of the buildings that they serve
12
Summary for District Heating Comparing modern district heating systems with modern on-site heating (using condensing boilers), there is little if any efficiency gain if generating heat centrally What little gain there is could be offset by distribution losses Reducing the losses in existing systems can yield large savings Taking heat from the generation of electricity with fossil fuels (cogeneration) will not reduce fossil fuel use if the alternative for electricity generation is to use renewable energy sources (such as hydro- electric power)
13
DH Summary (continued) District heating can still provide a number of energy advantages over on-site heating Easier opportunities to store heat (within the network and in insulated thermal reservoirs or underground) Easier to switch fuels for heating (potentially important if we make the transition to hydrogen in the future) Easier to directly use renewable energy - biomass for cogeneration - electric heat pumps to use excess wind-generated electricity when it is available - geothermal heat
14
Non-Energy Advantages of District Heating Quiet and vibration-free heating at building sites No need for emission of exhaust gases at the building site Reduced upfront costs for the building developed Savings in space, maintenance and insurance costs
15
District Cooling Centralized operation of multiple chillers, each running at the fraction of full load that maximizes overall efficiency, can yield large energy savings compared to operation of equal sized chillers in individual buildings The use of larger chillers in centralized plants yields further savings, as larger chillers are more efficient than small chillers Savings from these two factors of up to 45% have been achieved
16
Non-energy advantages of district cooling Quiet and vibration-free cooling at building sites Savings in space, maintenance and insurance costs Reduced upfront cost for the building developer No need for cooling towers on individual buildings (reducing on-site costs and risks related to legionnaires disease) Frees up roof space for roof-top gardens or solar collectors (PV or thermal)
17
Societal Cost of District Cooling Systems Compared to On-site Chillers
18
The total cost of district cooling can be less than for cooling of individual buildings, in spite of the cost of installing a district cooling pipe network, because Less total cooling capacity is needed (the peak loads of individual buildings do not all occur at the same time, so the system peak is less than the sum of the peaks of all the buildings in the system) Less total backup capacity is needed (it is not uncommon to have 2 equal-sized boilers or chillers in a given building, with one serving as backup. In a centralized system with 10-12 heating or cooling units, there might be only 1-2 backup units) Unit purchase costs are less for larger boilers and chillers Smaller operation and maintenance costs per unit of heating or cooling capacity
19
Cogeneration and Trigeneration
20
Cogeneration Sizing Options For one case study, energy savings is maximized if the cogeneration unit is about half the size that maximizes the area under the load duration curve Net energy savings initially increases as hours of operation increases and some heat is thrown away, because more less-efficiently generated electricity is displaced with more hours of operation As more heat is thrown away, the effective (marginal) efficiency of electricity generation decreases. When the marginal efficiency drops to that of the central powerplant x transmission efficiency, a further increase in the hours of operation will increase the overall energy use
21
Figure 9.4a,b Cogeneration sizing strategies: (a) maximizing the useful heat delivered (by maximizing the area of the rectangle under the load duration curve), (b) reducing the size of the cogeneration unit but maximizing the number of hours that it operates per year. Source: Voorspools and Dhaeseller (2006, Applied Thermal Engineering 26, 1972–1981, http://www.sciencedirect.com/science/journal/13594311) (a) (b)
22
Figure 9.4c,d Cogeneration sizing strategies: (c) Sizing the cogeneration unit as in (a) but with longer operation and some wasted heat; (d) using multiple units. Source: Voorspools and Dhaeseller (2006, Applied Thermal Engineering 26, 1972–1981, http://www.sciencedirect.com/science/journal/13594311) (c) (d)
23
Trigeneration Involves taking heat from a steam turbine and using it to drive an absorption chiller Taking heat results in reduced electricity output The sacrificed electricity could instead by used in an electric chiller to produce chilled water for cooling purposes An absorption chiller, while not needing electricity for the basic cooling operation, requires greater auxiliary electricity use than an electric chiller for the operation of the cooling tower The net result is that it is often better to maximize electricity production, even though this requires throwing away some waste heat, and using the extra electricity in large and efficient electric chillers
24
Pollutant emission with cogeneration These can go up or down compared to separate production of heat and electricity, depending on the efficiencies and emission factors for the cogeneration facility and the alternative systems Differences in human exposure to emissions, related to the location and altitude of the emission sources, must also be considered.
25
Cost savings with decentralized electricity production through cogeneration Costs with decentralized production will tend to be lower due to Reduced transmission and distribution costs (from an average of $1300/kW to $100-200/kW) Less needed powerplant capacity due to lower transmission and distribution losses Less needed backup capacity (4-5% instead of 15%) due to having many smaller units subject to random failure Revenue obtained by sale of heat produced through cogeneration