Minuteman Vocational Technical Regional High School Progress
January 22nd 2019 – February 25th 2019
2
February 25th View of Area A+B – Upper Level
MEP Ceiling Devices Installed. Millwork Installation in Progress
3
February 25th View of Area G – Upper Level
MEP Ceiling Devices Installed. Millwork Installation in Progress February 25th View of Area G – Lower Level Ceiling Grid Installation substantially complete. MEP Ceiling Devices Installation in Progress.
4
February 25th View of Area D – Upper Level
Prime & First Coat of Paint Substantially Complete. Ceiling grid installation to commence this week.
5
February 25th View of Area D – Gymnasium
Prime painting of walls, roof deck and MEP’s Substantially Complete. Rough-In of Overhead Electrical in Progress.
6
February 25th View of Area D – Mechanical Room
Terminations to equipment is in progress is nearing completion. Installation of insulation to commence this week.
7
February 25th View of Area E – East Elevation
Masonry Stone Veneer Complete at Lower Level. Metal Panel Soffit and Wall Panels in Progress. February 25th View of Area E – Faculty Parking Retaining Wall Construction in Progress.
8
February 25th View of Area E – Lower Level
Drywall installation substantially complete. Taping and Sanding activities in progress. February 25th View of Area E – Upper Level Installation of Railings at Skylight openings in progress. Soffit framing at openings in progress.
9
February 25th View of Area E+F – Cafeteria
Soffit framing in progress. Framing at along Bridge Level Substantially Complete. Installation of railings in space in progress.
10
February 25th View of Area F – Lower Level
Interior framing substantially complete. Sheetrocking & taping top of walls in progress. Rough-in of in-wall MEP’s in progress.
11
February 25th View of Area C – West Elevation
Masonry Veneer activities on the lower level complete. Window Installation Complete. January 22nd View of Area C – Mezzanine Level Overhead rough-in of major MEP’s complete. Painting of ceiling and MEP items complete. Concrete placement in misc metal stairs in progress this week.
12
February Construction Schedule Look Ahead:
Area A+B Continue Ceiling Grid Installation on Lower B Continue installation of Lights, Registers and other MEP devices in ceiling grid Continue Millwork installation on Upper B Commence Installation of Ceramic Wall Tile Area G Complete Ceiling Grid installation on the Lower Level Continue Millwork installation on Upper G Area D Complete Prime Painting on Upper Level Commence Ceiling Grid Installation Complete Mechanical Terminations to equipment in Mechanical Room Area E Complete Soffit Framing activities on all levels Complete Sheetrocking & Taping activities on all levels. Commence Prime Painting on all levels. Area F Complete Rough-In of in-wall MEP’s Commence Sheetrocking & Taping activities Area C Continue Rough-In of OH MEP’s over the theater & stage space. Concrete placement in misc metal stair systems. Exterior/Sitework Permanent power established to the building’s switchgear on schedule for February 26th Project team meeting with National Grid on 3/7 to obtain a schedule for the gas installation Complete the water main connection, test and flush system for use. Continue shaping the swales at the perimeter of the building