1 ASHRAE Annual Conference Sustainability Project Denver Rescue Mission Energy Efficiency Upgrades 1130 Park Avenue West, Denver, CO 80205 2013 Learn More @ www.ASHRAEDenver2013.org

2 WHO... 2013 In-depth energy assessment, technical design assistance, and the potential for high efficiency system installations WHAT... Our local ASHRAE chapter membership community Since 2008, each host city ASHRAE chapter has conducted a sustainability demonstration project of their choosing WHY...

3 2013 The Project 3-story, 23,000 sq.ft. building built in 1928 Tens of thousands of people come to this facility each year for shelter, food, and support

4 2013 The Facility Offices, two chapels, a library, a kitchen, a clinic, a dormitory and other ancillary spaces 3 meals per day, dorms open each night

5 2013 HVAC Systems Large boilers and steam radiators with old valves Constant volume make-up air unit (MAU) for dorms Constant exhaust for showers (4) split system AC units (offices, library, clinic) (4) evap cooling units (dorm, chapel, dining room)

6 Historical Energy Use 2013

7 Utility Data High EUI and Cost

8 2013 Utility Data Typical profile but high use

9 2013 Project Goals: Help the facility operate more sustainably with lower energy use and better Indoor Air Quality - Lower annual energy costs over 30%

10 Energy Efficiency Upgrades 2013 1.Lighting Upgrade 2.Replacement of (4) Split Systems 3.Installation of DDC System 4.Steam System Upgrades 5.Replacement of MAU with ERV 6.Replacement of (2) DHW Heaters, Increased Capacity, Low Flow Shower Heads 7.Installation of Solar DHW System

11 2013 ECM: Lighting Upgrade Currently 2 and 4-ft T-12 with magnetic ballasts Older exterior lights Limited occupancy sensors Older Exit Signs Project: Upgrade fixtures and add sensors

12 2013 ECM: Replace Split Systems Replacing (4) units - offices, library, clinic New units are 21 SEER* @ ARI Conditions *SEER = cooling output during a typical cooling-season divided by the total electric energy input during the same period(BTU/W*hr)

13 2013 ECM: Installation of DDC System Tie together HVAC equipment, zone thermostats, on/off enable Provide equipment scheduling, temperature control, unoccupied setback, and remote access

14 2013 ECM: Steam System Upgrades Thermostatic valves and steam traps in disrepair Replace valves and steam traps Address system leaks

15 2013 ECM: Replacement of Make-Up Air Unit (MAU) with Energy Recovery Ventilator (ERV) Tie restroom exhaust into ERV to capture heat Continuous ventilation for better IAQ

16 2013 ECM: Replacement of (2) DHW Heaters, Increased Capacity, Low Flow Showers Currently only (2) 80 gal tanks Adding more capacity and upgrading to 86% efficiency

17 2013 Energy Saving Estimates

18 Team and Fundraising 2013

19 Thank you Project Team! Technical Team: Owner Liaison and Program Support – Energy Outreach Colorado Project Management and Energy Support – Eaton Energy Solutions Mechanical and Plumbing Design – MKK Consulting Engineers, Inc Energy Audit – Investive Building Projects (formerly LONG Energy Solutions) Pricing and Contractor Liaison – US Engineering Solar Assessment – Shamrock Sales Energy Monitoring – ATS Steam System Assessment – Dick Scott Structural Assessment – Jirsa Hedrick & Associates General Contractor – C&D Management Lighting Assessment – Illumination Systems Fundraising: Fundraising Lead – Western Mechanical Solutions Finance and Sponsor Tracking – Mtech Publicity and Promotions: Promotions, Materials – Shaffer Baucom Website – John Eisel Promotions, Fundraising – IMS

20 2013 Thank you Sponsors & Donors! Platinum annexAir C & D Builders, Inc. Denver Office of Strategic Partnerships Mtech XCEL Energy Silver Apricus CAMUS Hydronics Ltd. Cooper Lighting Johnson Controls Lohmiller & Company Carrier West McKinstry Patron Air Purification American Mechanical Services CFM Company Curb Technologies Davenport Family Gift Fund Hercules Industries Ideal Electric, Inc. Investive Building Projects RMH Group Slattery & Company TRANE Denver Winslow Crane Services Co. Gold Alerton ASHRAE Rocky Mountain Chapter ASHRAE Society ATS Rocky Mountain Ferguson Enterprises, Inc. McNevin Co. US Engineering Bronze Digital Communications Partner Denver Water M-E Engineers, Inc. MKK Consulting Engineers, Inc. Water Technology Group Western Mechanical Solutions Associate ASHRAE Black Hills Chapter James Waechter P.V.C. Specialties Company Shaffer Baucom Engineering & Consulting Supporter Aaron Zimmerman Brian Lynch C&D Insulation, Inc.

21 2013 BE PART OF THE SOLUTION! LEARN MORE AND DONATE @ www.ASHRAEDenver2013.org General Project and Donation Inquiries: sustainable@rockymtnashrae.com


Download ppt "ASHRAE Annual Conference Sustainability Project Denver Rescue Mission Energy Efficiency Upgrades 1130 Park Avenue West, Denver, CO 80205 2013 Learn More."

Similar presentations


Ads by Google