1 Hybrid & Module Testing Status
Week of 12/12-12/16 12/12-12/16

2 UCSB Hybrid Testing Status
12/12-12/16

3 FNAL Hybrid Summary As of 12/16/2005 12/12-12/16

4 TOB Hybrid Testing Failures
This (Last) Week None Cumulative 7 Shorts in PA 2 Shorts on APV 6 Noisy channels-usually entire chip or chips 2 a few open and noisy channels 3 too many shorts 4 shorts & noisy channels 3 many noisy and short channels 3 scratched PA 2 Too many opens 2 Opens & shorts 1 Damaged during testing 1 many open & noisy channels 6 Global failure 12/12-12/16

5 TEC Hybrid Testing Failures
This (Last) Week 1 global shorts 1 too many shorts, noisy 1 few shorts and noisy 3 damaged 2 too many noisy 3 too many shorts Cumulative 5 damaged at repair 2 too many noisy one open 1 too many shorts and noisy 1 two chips noisy and shorted 5 too many noisy channels 2 all chips noisy 6 global failure 10 shorts and noisy channels 9 scratch on PA 2 messy PA 3 too many open, noisy, short channels 5 too many shorts 12/12-12/16

6 Fermilab Hybrid Test Details
A new graduate student/technician…… High first time failure rate on TEC’s, as usual: low count of tested hybrids 12/12-12/16

7 US Hybrid Testing Status
12/12-12/16

8 UCSB ARCS Testing Status
12/12-12/16

9 UCSB ARCS Testing Failures
This Week Cumulative 12 with too much current 2 after backplane bonding 4 due to residue on sensors 1 already repaired 2 with >2% bad channels 1 with bad DCU Repairable 1 with CF frame shorted to HV 1 with bad Dec. Mode chip 1 with bad Peak Mode chip 1 with chip with too low noise 1 with bad chip 1 with funny LED test 1 with chip out of synch 1 failed on rod 1 CMN 12/12-12/16

10 UCSB ARCS Testing Results
2519 Total Tested 2489 Grade A 3 Grade B 27 Grade F This week: 8 of channels bad (0.020%) Total Production: 625 of channels bad (0.041%) 12/12-12/16

11 UCSB ARCS Testing Results
Total Production: 625 of channels bad (0.041%) This week: 8 of channels bad (0.020%) 12/12-12/16

12 UCSB Backplane Testing
12/12-12/16

13 UCSB LT Testing Status Failed module has too much current 12/12-12/16

14 FNAL LT Testing Status Modules , , 9522, , 9495, 9530, 9534, 9536, 9539 were tested Dec 12 – Dec 15. All passed LT. Weekly – 20 modules passed LT. 12/12-12/16

15 FNAL LT Testing Status 12/12-12/16

16 US LT Testing Status 12/12-12/16