Wye/Wye 120/208 4 wire Transformer Bank

Similar presentations


Presentation on theme: "Wye/Wye 120/208 4 wire Transformer Bank"— Presentation transcript:

1 Wye/Wye 120/208 4 wire Transformer Bank
© 2018 Iowa Association of Electric Cooperatives

2 OSHA Required Tailgate Discussion Topics
Hazards Associate with the job Work Procedures Involved Special Precautions Energy Source Controls PPE Required The five topics required by OSHA to discuss in the tailgate. First letter from each topic = How Well Should Everyone Plan © 2018 Iowa Association of Electric Cooperatives

3 Work Procedures Involved Hazards associated with the job
Special Precautions Energy Source Controls Personal Protective Equipment Be sure to record your emergency location and post in a location everyone on the crew knows. Have your PPE and First Aid kit available Be sure your AED is accessible. A safe job begins with a thorough inspection of… Tools Be certain all of your tools are in good shape. Equipment Make sure your trucks are all in working order take time to preflight your equipment and insure there are no surprise. Line/Structure Look over the line and structure. Are there any potential hazards? (Broken insulators, damaged wire, clearances over roads or from trees?) Be aware of your work area, be sure to cover anything you can reach touch or fall into. And anything that can reach touch or fall into you! Discuss all PPE needed for the job and wear your PPE. Be sure to inspect your equipment prior to use. Identify all voltages you are exposed to. Be sure to have all of your Arc-Flash protective gear on. Identify a dedicated observer Working in traffic exposes you to hazards that are difficult to control. Give the vehicles plenty of time to see and avoid you! Follow the manual of traffic control for your area. Slips trips and falls are some of the most common injuries, look for hazards that could cause this. Be sure to inspect and wear your fall arrest harness. Here are the five topics again with signs and bubbles to jump start tailgate discussion!! Click on the icon to bring up a text box. Click on the icon again to make the text box go away Gets the crew involved. Gives the feeling of knowing it is ok to ask questions, give suggestions, see something, say something! The next slides will get directly into the task at hand. Visual, written and audio will all be used here! There are suggestions in the notes as to what to discuss. This will get the Team involved, creating communication channels to open! © 2018 Iowa Association of Electric Cooperatives

4 Hang the required hardware
Note the side that has two cutouts is opposite the system neutral. © 2018 Iowa Association of Electric Cooperatives

5 Parallel all of the transformers internally.
Ground all of the transformer cases as well as the transformer cluster. © 2018 Iowa Association of Electric Cooperatives

6 Connect the primary jumpers
Connect the primary jumpers. Leaving the high side jumpers connected to the system neutral until the entire connection is completed. H1 H2 © 2018 Iowa Association of Electric Cooperatives

7 You may use single bushing transformers for this connection
Connect the H2 bushings together and connect them to the system neutral and ground. You may use single bushing transformers for this connection © 2018 Iowa Association of Electric Cooperatives

8 You may use single bushing transformers for this connection
Connect the H2 bushings together and connect them to the system neutral and ground. You may use single bushing transformers for this connection © 2018 Iowa Association of Electric Cooperatives

9 Connect all X2’s together with a jumper of equal capacity to the secondary phase wires.
Neutral © 2018 Iowa Association of Electric Cooperatives

10 Connect the secondary phase wires to the X1’s.
Neutral Power Power Power © 2018 Iowa Association of Electric Cooperatives


Download ppt "Wye/Wye 120/208 4 wire Transformer Bank"