Presentation is loading. Please wait.

Presentation is loading. Please wait.

EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE

Similar presentations


Presentation on theme: "EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE"— Presentation transcript:

1 CLAUSE 33 - RIAI CONTRACT AUGUST 2017 EDITION DETERMINATION BY EMPLOYER
EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE POST DETERMINATION FINAL ACCOUNT Dispute resolution

2 EMPLOYER’S COMMON LAW RIGHTS
FUNDAMENTAL BREACH ALLOWS REPUDIATION OF THE CONTRACT (Dundalk S C v Roof Spray 1979) – Contract Law in Ireland, Robert Clark REPUDIATION CANCELS THE NEED FOR PERFORMANCE OF CONTRACT MUST BE A FUNDAMENTAL BREACH INJURED PARTY ENTITLED TO DAMAGES REPUDIATION IS NOT MANDATORY CONTRACT PROCEDURE EASIER TO FOLLOW ESSENTIAL TO CONSULT EMPLOYER Dispute resolution

3 DETERMINATION IN CLAUSE 33 – REASON 1
33 (a) (i) – (iv) DEFAULT BY CONTRACTOR wholly suspends work without reasonable cause fails to proceed with reasonable diligence ignores notice to remove defective work or improper materials doesn’t work per contract is in serious breach of obligations in Architect’s opinion Dispute resolution

4 33 (a) (i) – (iv) SOME DEFAULT IN DETAIL
wholly suspends work without reasonable cause “suspends” means “stops temporarily” “wholly” means “completely” or “totally” “reasonable” means “sensible”, “fair”, “logical”, “moderate” fails to proceed with reasonable diligence “diligence” means having “care and perseverance” Dispute resolution

5 DEFECTIVE WORK OR IMPROPER MATERIALS
MIGHT INCLUDE strip foundations instead of piles change to unsuitable roofing materials MIGHT NOT INCLUDE change in skirting material wrong colour paint CONSIDER ALTERNATIVES IN THE CONTRACT defects – clause 31 or other contractor per clause 2 Dispute resolution

6 DETERMINATION IN CLAUSE 33 – REASON - 2
CL. 33 (b) INSOLVENCY Bankruptcy Liquidation Receiver Petition for an Examiner Dispute resolution

7 PROCEDURE 33 (a) DEFAULT FOR DEFECTIVE WORK OR IMPROPER MATERIALS 33 (a) (iii) written notice from the Architect requiring removal no specific contract requirement about delivery of the notice ALL DEFAULTS IN 33(a) 1st NOTICE FROM ARCHITECT SPECIFYING THE DEFAULT by registered post or letter delivered to Contractor DEFAULT CONTINUES FOR 10 WORKING DAYS Dispute resolution

8 PROCEDURE 33 (a) DEFAULT 2nd NOTICE EMPLOYER DETERMINES CONTRACTOR’S EMPLOYMENT within 10 working days (maximum) by registered post or letter delivered to Contractor NOTICES CAN’T BE GIVEN UNREASONABLY OR VEXATIOUSLY NOTICE IS VOID IF EMPLOYER IS IN SERIOUS BREACH AT TIME OF NOTICE DOESN’T PREJUDICE EMPLOYER’S ANY OTHER RIGHTS DETERMINES EMPLOYMENT BUT NOT THE CONTRACT Dispute resolution

9 PROCEDURE 33 (a) DEFAULT AFTER 1st NOTICE IS GIVEN
CONTRACTOR CAN’T REMOVE HIS PLANT, MATERIALS OR GOODS EMPLOYER HAS LIEN ON THEM UNTIL CONTRACTOR COMPLIES LIEN EXPIRES AFTER 1 MONTH UNLESS EMPLOYER TAKES POSSESSION OF SITE AND WORKS LIEN NOT ON SC’S PLANT, MATERIALS OR GOODS UNLESS CERTIFIED AND PAID Dispute resolution

10 PROCEDURE 33 (b) INSOLVENCY
NOTICE FROM EMPLOYER DETERMINING CONTRACTOR’S EMPLOYMENT by registered post or delivered to Contractor MOST COMMON REASON FOR DETERMINATION NO PREJUDICE TO EMPLOYER’S CONTRACT RIGHTS Dispute resolution

11 PROCEDURE AFTER DETERMINATION 33 (c)
EMPLOYER CAN EMPLOY AND PAY OTHERS TO FINISH THE WORKS CAN USE ALL PLANT, MATERIALS, ETC. ON SITE CONTRACTOR ASSIGNS BENEFIT OF SUB-CONTRACTS, IF REQUIRED EMPLOYER PAYS ASSIGNED SCs FOR WORK DONE AFTER DETERMINATION CONTRACTOR REMOVES HIS THINGS WHEN SPECIFIED BY THE ARCHITECT IF HE DOESN’T, EMPLOYER CAN SELL THEM WITH NETT PROCEEDS HELD FOR CONTRACTOR Dispute resolution

12 PROCEDURE AFTER DETERMINATION
EMPLOYER CAN PROVIDE SITE SECURITY – 33 (d) if in Architect’s reasonable opinion existing security is not adequate can be done after 1st notice per 33 (a) or determination per 33 (b) done at Contractor’s cost for maximum 1 month Dispute resolution

13 PROCEDURE AFTER DETERMINATION
PRACTICAL STEPS secure the site ASAP consult bondsman consider how to replace the Contractor liaise with principal SCs Dispute resolution

14 FINAL ACCOUNT CLAUSE 33 (c) (iv)
NO PAYMENT TO CONTACTOR UNTIL COMPLETION WORK IS DONE no certificates or payment of outstanding certificates COMPLETION COST VERIFIED IN A REASONABLE TIME ARCHITECT CERTIFIES EXPENSES PROPERLY INCURRED NOTIONAL FINAL ACCOUNT FOR ORIGINAL CONTRACTOR SETTLEMENT BALANCE PAYABLE TO CONTRACTOR OR TO EMPLOYER Dispute resolution

15 BOND NOTHING IN CONTRACT – FOLLOW BOND CONDITIONS
ESSENTIAL TO LIAISE CLOSELY WITH BONDSMAN INSOLVENCY MIGHT NOT TRIGGER THE BOND INFORM BONDSMAN ASAP WHEN DETERMINATION IS STARTED AGREE HOW TO PROCURE REPLACEMENT CONTRACTOR & SCs SCSI GUIDANCE NOTE ON CONSTRUCTION SECURITY AND PERFORMANCE DOCUMENTS Dispute resolution

16 PRINCIPAL SUB-CONTRACTORS
SCs WITH ORIGINAL CONTRACTOR MIGHT BE DETERMINED MAINTAINING COLLATERAL WARRANTIES AND BC(A)R DEAL MIGHT BE NEEDED AGREE WITH BONDSMAN Dispute resolution

17 THANK YOU Dispute resolution


Download ppt "EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE"

Similar presentations


Ads by Google