Southern Arizona Modelers
New Runway Construction April 2016
2
First the surrounding area of the old runway was cleared and scraped.
3
Prep work being done in the pit area.
6
Here comes the asphalt grinder.
7
Asphalt grinder starting with the taxiways.
9
Harry and members leveling out the ground asphalt.
10
Here we go, out with the old!
15
No turning back now with the last bit of asphalt to go.
17
The ground asphalt was then smoothened out.
18
Then watered down. Then watered down.
19
Then rolled. Thank you Empire Equipment!
21
Howard and members setting survey stakes.
26
The runway was then graded to the level of the survey stakes.
29
A little prep work by the asphalt workers.
31
The first bit of asphalt going down. Starting with the taxiways.
33
Some SAM members on hand anxious to get to work.
37
The start of the new runway!
41
After the taxiways and the edge of the runway down we can start leveling out the edges.
After the taxiways and the edge of the runway were down we can start leveling out the edges.
44
About half way done, waiting for the next asphalt truck.
About half done, waiting for the next asphalt truck.
45
With the new runway completely down we can finish the edges.
47
With the runway work complete, the outlying area was smoothened and rolled.
48
The new runway, ready for some smooth landings!
The new runway, ready for some smooth landings. Thank you Pima Asphalt Inc.!