1 Jon Jensen Associate Staff Engineer
Base Case Basics Jon Jensen Associate Staff Engineer Western Electricity Coordinating Council

2 Western Electricity Coordinating Council
Purpose “People who work together will win, whether it be against complex football defenses, or the problems of modern society.” -Vince Lombardie “If everyone is moving forward together, then success takes care of itself.” -Henry Ford Western Electricity Coordinating Council

3 Western Electricity Coordinating Council
Introductions From the WECC Staff: Doug Tucker Enoch Davies Jon Jensen Nick Hatton Western Electricity Coordinating Council

4 Western Electricity Coordinating Council
Discussion Outline WECC Base Case Building Procedure Reporting Data Anomalies Western Electricity Coordinating Council

5 Base Case compilation Schedule
DATE DATA REQUEST MAILED DATE DATA DUE TO SUB COORD DATE L&R INFO DUE TO SUB COORD DATE DATA DUE TO AREA COORD DATE DATA DUE TO STAFF STAFF SEND CASE FOR REVIEW DATE COMMENTS DUE TO AREA COORD DATE AREA COORDINATOR COMMENTS DUE TO STAFF STAFF FINALIZE DATE 2015 HS4-OP 07/18/14 08/01/14 08/08/14 09/12/14 09/26/14 10/10/14 10/17/14 10/31/14 2015 LS1-OP 08/15/14 08/22/14 10/24/14 11/14/14 HW1 10/03/14 11/07/14 11/21/14 11/28/14 12/05/14 12/19/14 2025 HS1 12/12/14 12/26/14 01/02/15 01/09/15 01/23/15 HW3-OP 01/16/15 01/30/15 02/13/15 02/20/15 03/06/15 LW1-OP 02/27/15 03/20/15 2016 HSP1-OP 02/06/15 03/13/15 03/27/15 04/10/15 04/17/15 05/01/15 HW1 04/24/15 05/08/15 05/15/15 05/22/15 06/05/15 2021 HS2 04/03/15 05/29/15 06/12/15 06/19/15 06/26/15 07/10/15 2016 HS3-OP 07/03/15 07/17/15 07/24/15 07/31/15 08/14/15 2016 LS1-OP 08/28/15 2018 HS1-S 09/11/15 09/25/15 10/02/15 10/16/15 20XX-Regional 08/07/15 08/21/15 10/30/15 11/06/15 11/20/15 HW1 11/27/15 12/04/15 12/18/15 2026 HS1 12/11/15 12/25/15 01/01/16 01/08/16 01/22/16 Western Electricity Coordinating Council

6 Base Case Building Power flow
From each AC we should receive the following: Area Specific power flow data L&R spreadsheet Any dynamic model changes/updates Any tie line changes (must be coordinated!!!) List of significant changes Any additional info that will help with base case compilation Western Electricity Coordinating Council

7 Western Electricity Coordinating Council
Creating a Raw Case Western Electricity Coordinating Council

8 The Master Tie Line File
Contains raw data for the following: Branches Transformers Line connected shunts DC lines (Bus, Line, DCC) Transformer impedance tables Interface data (Paths) Branch interface data Zones Owners Area Interchange Western Electricity Coordinating Council

9 Western Electricity Coordinating Council
Tying It All Together Western Electricity Coordinating Council

10 Area Interchange Schedules
BC Hydro Interchange with Northwest 2300 MW Northwest Interchange with BC Hydro -2300 MW Western Electricity Coordinating Council

11 Power Flow Solution and Data Checking
Island check Tie line check Edit table checks Mustfix.p Checks.p svdsnap.p Pathmoni.p Tappfixer.p Dchk Baseloader.p InsertTurbine.p Overload check (Line & Path) Solution check InsertLID.p InsertGENID.p FillRatingsPSSe.p DCINTMT.p Replog PowerWorld PTI Conversion Western Electricity Coordinating Council

12 Questions About Power Flow Compilation?
Western Electricity Coordinating Council

13 Base Case Building - Dynamics
The Master Dynamics File (MDF) Models Updates in PSLF format Temporary vs. permanent changes Motor load modeling Condenser and pump check Unused models Composition load models Western Electricity Coordinating Council

14 Initializing Dynamics Data
Reading in the MDF Missing data Duplicate models Modstat.p Built into PSLF 17.0 Initialization Governor errors/warnings Exciter errors Western Electricity Coordinating Council

15 Western Electricity Coordinating Council
Running and Plotting A no-disturbance run The alldyns.p disturbance routine Ringdown Double Palo Verde Outage Loss of PDCI Post-transient solution Disturbances Metcalf-Moss landing, Tesla-Metcalf Comanche-Daniels Park Colorado River – Red Bluff Hells Canyon – Brownlee N-0 Overloads-Operating cases Western Electricity Coordinating Council

16 Western Electricity Coordinating Council
Plotting Plotting the channel file Searching for the largest deviation (spread) Plotting parameters Western Electricity Coordinating Council

17 Base Case Building - Comments
Types Submitted in EPCL, EPC, .m, or by list MUST be made to review case Changes to tie lines must be coordinated Extensive data changes Western Electricity Coordinating Council

18 Questions about Dynamics and Comment Submission?
Western Electricity Coordinating Council

19 Reporting Data Anomalies
Master Tie Line File Data Series Compensation New Phase Shifters Additional Solution Tools Any Area Substitution Data PSS Exemptions Dynamics Data Study Report Suggestions Western Electricity Coordinating Council

20 Western Electricity Coordinating Council
Questions Jon Jensen Western Electricity Coordinating Council