1 2040 Long Range Transportation Plan Update
Project Kick-Off October 8, 2015

2 2040 LRTP UPDATE TEAM TPO Project Manager – Kate Daniel
Atkins Project Manager – Wiley Page Sr. Planners David Haight Phil Shad Wiatt Bowers LRTP Marketing – Kelly Robertson (BowStern)

3 PURPOSE OF THE LRTP Blueprint to maintain and enhance our regional transportation system Consider current needs and forecasted future growth List of multi-modal transportation projects to be funded through 2040 (cost feasible) Maintain currency by updating every five years to consider changes in growth and travel patterns * Current 2035 LRTP was adopted in March 2012

4 ELEMENTS OF THE LRTP 2040 LRTP Cost Feasible Plan Goals & Objectives
Data Forecasts Needs Assessment Financial Resources

5 Goals and Objectives Goals and Objectives serve as the guiding principles of the plan. They will help determine the projects that are ultimately included in the plan. Will be the basis for developing the project evaluation criteria

6 2040 Needs Assessment Begins with the forecasting of conditions using the current transportation network Followed by development of alternatives Road projects Transit projects Bike/Pedestrian projects Operational projects

7 2040 Needs Assessment Ultimately the Okaloosa-Walton Transportation Planning Organization will adopt a multi-modal Needs Plan for 2040 This will likely be a mix of transit, bicycle, pedestrian and roadway projects

8 Cost Feasible Plan How do we set priorities within funding constraints? We will strive for a balanced plan that functions well as a mobility system. For the 2040 Cost Feasible Plan we have $150M in Other Arterial funds and $175M in SIS funds to work with.

9 STEERING COMMITTEE Made up of members of the TPO’s Technical Coordinating Committee (TCC) and Citizens’ Advisory Committee (CAC) Will meet throughout the update to guide process Help promote the workshops throughout the community

10 SCHEDULE Activity 2015 2016 2017 Approved Scope of Services April
Consultant Notice To Proceed July Congestion Management Plan September-December January Goals and Objectives November – December January – April Public Workshop #1 February/March Evaluation Criteria February –June Financial Resources Public Workshop #2 April/May Needs Plan Development February-July Public Workshop #3 August Cost Feasible Plan Development August – December January-February Documentation Continuous

11 LRTP Steering Committee
Will meet 6 to 8 times throughout the LRTP Update process

12 CONTACT INFORMATION Project Manger Consultant Manager Kate Daniel Wiley Page TPO Staff Atkins

13 How to Get the community Involved
Mailing List Newsletters Web Project Workshops Community Group Presentations

14 QUESTIONS