August 2008 WATCH YOUR STEP! CONSTRUCTION PROJECTS UNDERWAY!
2
August 2008 Construction Update Facilities Planning & Campus Development August 2008
4
SOAR High School Campus Temporary Classrooms S5 & S6 Complete - August 2008 Permanent Campus Nine Classrooms, Administrative Building, Restrooms Completion - January 2009
5
August 2008 T100 Student Services Modular Building Disabled Student Services Test & Assessment Center Completion – September 2008
6
August 2008 T100 Site Layout T100
7
August 2008 Radiologic Technology Lab Child Development Center Playground Upgrade 2008-09 Grant Funded Projects
8
August 2008 Measure R Projects
9
August 2008 Project: Agriculture Labs & Greenhouses Occupancy: August 2009
10
August 2008 Project: Agriculture Labs & Greenhouses Two Labs, Lathe House, Shade House, Prep Areas, Four Greenhouses, Demonstration Garden, Faculty Offices, Orchard, Arboretum and Storage Buildings
11
August 2008 Project: Facilities Services & Warehouse Occupancy: January 2009
12
August 2008 Project: Facilities Services & Warehouse 22,000 Square Foot Receiving/ Warehouse Building Facilities Services – Shops & Offices to Support: Maintenance, Grounds, Custodial, Transportation, Campus Events, Recycling, HazMat and Facilities Planning
13
August 2008 Project: West Campus Expansion Parking Lot #1 258 Spaces Complete
14
August 2008 Project: West Campus Expansion Parking Lot #3 723 Spaces Complete
15
August 2008 Project: West Campus Expansion Parking Lot #2 253 Spaces January 2009 Completion
16
August 2008 Project: West Campus Expansion Soccer Fields Complete Run/Walk PAR Course December 2008 Completion
17
August 2008 Project: West Campus Expansion P. E. & Athletic Fields Spring/Summer 2009 Completion Stadium Renovation Spring/Summer 2009 Completion
18
August 2008 Project: Campus Utilities Infrastructure SEWER PIPE – 632 FEET ELECTRICAL CONDUIT – 32,400 FEET STORM DRAIN PIPE – 833 FEET FIRE WATER PIPE – 9,336 FEET DOMESTIC WATER PIPE – 10,541 FEET IRRIGATION WATER PIPE – 18,500 FEET NATURAL GAS – 4,340 FEET COMMUNICATIONS – 51,750 FEET CHILLED WATER PIPE – 7,680 FEET MID 2009 COMPLETION
19
August 2008 Project: Campus Network Infrastructure Voice & Data System Upgrades: Complete
20
August 2008 Project: Auto Body Addition Occupancy: January 2010
21
August 2008 Project: Auto Body Addition 5,500 Square Foot Complex Includes: Multimedia Classroom, Two Downdraft Paint Booths, Paint Mixing Room, Two Paint Prep Bays, Two Garage Bays, Frame Bay and Tool Room
22
August 2008 Project: Theatre Arts Facility Occupancy: Fall 2010
23
August 2008 Project: Theatre Arts Facility 400 Seat Multi-Purpose Theater, 32,000 Square Foot Facility, Green Room, 2,700 Square Foot Main Stage, Two Side Stages, Set & Costume Design Areas
24
August 2008 Project: Central Plant/MDF Occupancy: Summer 2009
25
August 2008 Project: Central Plant/MDF Central Plant - Provide Cooling For All Campus Buildings Utilizing New Energy Efficient Variable Speed Drive Chillers MDF – Main Distribution Facility For All Campus Voice & Data Networks
26
August 2008 Project: Health & Science Building Occupancy: Spring 2012
27
August 2008 First Floor Plan Lecture Rooms 11 Classrooms 590 Seats 23% Increase in Lecture Space Office Space 74 Offices 2 Meeting Rooms 2 Work Rooms
28
August 2008 Second Floor Plan Computer Lab Tutorial Lab 9 Health Science Labs 14 Science Labs Planetarium Cafe
29
August 2008 Project: Student Services Building Future Projects Submitted for State Review Project: Art & Music Expansion Project: Fitness & Wellness Center Project: High Technology Learning Center
30
August 2008 Project: Palmdale Campus Site Acquisition: Complete 25 th Street East & Barrel Springs Hwy.
31
August 2008 Facilities Planning & Campus Development Web Page Additional Information www.avc.edu/Measure R Construction Projects Information