Leveling
2
Leveling : is the procedure used to determine difference in elevation between points that are some distance from each other
3
General Terms Elevation: is a vertical distance above or below reference datum Level line: is a line in level surface, a level surface is a curved surface. Mean sea level: reference datum that is universally employed in surveying studies
4
Leveling Concepts
5
Types of Surveying Levels
Automatic Digital Tilting Dumpy Rotary Laser
6
Engineers’ Automatic Level
8
Definitions for differential levelling
Bench Mark (BM): is a permanent point of known elevation ( published) Temporary Bench Mark: (TBM): is semi permanent point on known elevation. (nails in the rod of trees, not publish) Turning Point (TP): is a point temporarily used to transfer an elevation. Back sight: is a rod reading taken on a point of known elevation. Height of Instrument (HI): is the line of sight through the level. HI= Elev. BM + BS
9
Foresight (FS):is a rod reading taken on TP, BM , TBM to determine its elevation. HI-FS= Elev. of TP(or BM or TBM) Intermediate Sight (IS): is a rod reading taken in any other point where the elevation is required. HI-IS=Elev.
10
Leveling Procedure – One Setup
11
Leveling Procedure – One Setup
12
Leveling Procedure – One Setup
13
Leveling Procedure – Multiple Setups
14
Ex 1: complete accompanying set of differential leveling and perform the arithmetic check.
Station BS (m) HI (m) FS (m) Elevation (m) BM3 1.613 TP1 1.425 1.927 TP2 1.307 1.710 TP3 1.340 1.273 0.780
15
Ex 2: complete accompanying set of differential leveling and perform the arithmetic check.
Station BS FS Elevation BM7 4.368 82.206 TP1 6.907 4.538 TP2 4.680 8.800 TP3 3.730 5.978 TP4 8.464 5.245 3.598
16
Ex 3: A sport hall to be constructing shown in Figure 1
Ex 3: A sport hall to be constructing shown in Figure 1. Laing out the site required to start from a known elevation point. Point A at the adjacent road street was chosen to be the starting known elevation point. The elevation of point A is 265 m and the reading was taken with a level is 2.72 m. The reading was taken with a level at point B is 1.09m. Determine the following: 1- The elevation of the sport hall 2- The level of the sport hall with respect to the adjacent road street.
18
Ex 4: If the sight of 1. 097 m is taken on BMA (Elev. = 312
Ex 4: If the sight of m is taken on BMA (Elev.= m), and another sight of m is read on point X. calculate the H.I. and the elevation of point X.
19
Reciprocal leveling
20
Peg Test: The purpose of this test is to check the line of sight through the level is horizontal.
21
Peg test - Place two stakes at distance of (60-90 m) apart. - The level is setup midway(paced) between the two stakes - Road readings are taken at both locations. - If the line of sight through the level is not horizontal, the errors in road readings (Δl1) at both points A &B are the same. - The level is moved to the one of the points (A). - Road then held at A and then at B and normal sighting is taken (a2 &b2).
22
Peg test Example : refer to peg test figure First setup: Rod reading at A, a1= m Rod reading at B, b1= m The difference in elevation =0.172 m Second setup: Rod reading at A, a2= m Rod reading at B, b2= m The difference in elevation =0.163 m
23
Peg test From second setup there is an error. The second reading b2 would have been = m While the reading is m. So the error (Δl2) = = m along 60m distance The error is 0.009/60= m/m . Therefore, the collimation factor C is equal to m/m
25
Level Loop Adjustment E= 186.273-186.258= 0.015
Correction= cumulative dist./total distance BM Loop distances (km) Field elevation correction Adjusted Elevation 20 201 0.8 0.003 202 2.4 0.008 203 3 0.010 4.7 0.015
26
Mistakes in levelling 1- Misreading the meter rod value. 2- Not holding the rod in the correct location. 3- Resting the hand on the tripod while reading the rod 4- Entering the rod reading incorrectly (switching BS and FS). 5- Making mistakes in the note reduction arithmetic, 6- Mistakes in rod reading that do not form part of arithmetic check. Such as intermediate sights.
27
Suggestions for leveling work
1- Tripod legs should be tightened. 2- The surveyor should read the rod at either the top or the bottom of the cross hair. 3- Never move the level before a FS is taken. 4- Check to ensure that the level bubble remains centered. 5- Arithmetic can be eliminate by having the other crew members checking the notes. 6- All crew members should try to develop strict routines for doing their works.