Water Storage Investment Program Schedule
Event Date Public Benefit Ratio (PBR) Review Applicant Notification February 1, 2018 PBR Review Posted to WSIP Portal February 2, 2018 Applicant Appeals Due February 23, 2018 Reviewer Responses to Appeals Posted April 20, 2018 Commission 3-day Meeting to Determine PBRs May 1 – 3, 2018 Preliminary Application Scores Posted May 25, 2018 Commission 3-day Meeting to Determine Scores June 27 – 29, 2018 Final Scores and Application Ranks Posted July 6, 2018 Commission 3-day Meeting, Maximum Eligibility Determination July 24 – 26, 2018